Title Page
-
Principle Contractor/Contractor Name
-
Network Supervisor Name
-
Project Address
-
Project Number
-
Project OK to proceed
-
Pre-Start Check Date
-
Site Work Check Date
-
Location
Clarity about the construction phase plan (CPP)
-
Are roles and responsibilities shown in CPP?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Is there an induction & register for the Site copy ?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Is the Contractor aware of and taking account of the key hazards & pre-construction information?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Is the Contractor clear on their scope of work and working to a design/plan?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are permit requirements (incl SCO) clear?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are Site rules shown in the plan?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Is it clear which risks are being managed by Cadent (e.g. SCO) and which the contractor is managing ?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Has the contractor got adequate SUPERVISION and monitoring planned?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Is the communication to any sub-contractors of the CCP clear?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are scheduled 3 risks identified- excavations, working at height, HV, chemical & biological substances, drowning, earthworks and tunnels, caissons with compressed air atmosphere, assembly and/or dismantling of heavy prefabricated components?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
Site area & Handover
-
Will/has the project been discussed between pre-construction & construction personnel, e.g. Handover at commencement of project?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are all Site plans available in the CPP, including Gas and Electric drawings including a process for refreshing drawings on longer projects?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are there Site rules in the CCP and will they be COMMUNICATED, accessible on Site & understood by workers?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Is there a layout plan for the site, e.g. Vehicle parking/movements, welfare?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Has appropriate signing (including safety signs), Lighting and Guarding been considered for the site?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are welfare arrangements adequately planned ?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Has adjacent site use been considered, e.g. HGV's obstruction, evacuation of?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
Emergency Plan
-
Are response procedures in place for all identified emergency situations?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Is there a process in place for reporting injuries?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Will first aid kit be available and checked?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
RAMS check & Controls
-
Has the contractor an up to date site specific risk assessment that adequately IDENTIFIES safety and environmental hazards?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are Risk assessments Site specific and are the controls adequate?
- Pre-Start Yes
- Pre-Start No
- During Site Work Yes
- During Site Work No
-
Are the risk assessment controls that were planned in place?
-
If Temporary Works are required, has the Temporary Works design been checked by a competent person, registered on a Temporary Works register and been approved by the Temporary Works Coordinator?
-
Are the correct PERSONNEL on site and with evidence of qualifications available if required ?
-
Can the contractor confirm that the correct PLANT is being used on site and any maintenance records are in date?
-
Can the contractor confirm that appropriate PPE is being used?
-
If Temporary Works are required, has the Temporary Works design been checked by a competent person, registered on a Temporary Works register and been approved by the Temporary Works Coordinator?
-
Are the contractors aware of and working to appropriate Policies, Procedures & Standards specific to the works being undertaken?
Site Control Duties
-
Is it clear who is in control of the works areas(s)?
-
Is there evidence of control of safe access, egress, and site demarcation?
-
Is there evidence that people coming onto site are being inducted?
-
Has the site register been updated? (At start and during the work)
Scope of Changes on site
-
Have any changes of scope by Cadent been auctioned appropriately?
-
Does the contractor know when & how to contact Cadent if things change?
-
Have any changes on site been reflected in the RAMS, pre-authorised in the permit and been appropriately briefed?
-
Cadent representative signature.