Title Page

  • Elevation

  • Mast climber

  • Levels

  • Commencement date

  • Certa Manager

Installation

Pre Installation checklist

  • Are drawings construction issue?

  • Are drawings the most current spec?

  • Have project specific calculations & drawings been developed for the system?

  • Is the substructure in line with the current system tolerances?

  • Have Gridlines and Datums been provided by GMI?

  • Has area been handed over from GMI to Certa?

Installation

Breather Membrane

  • Has correct materials been delivered to site?

  • Has Breather membrane been Installed in line with Certa Construction issue drawings?

  • Has tape been installed with overlaps at min. 100mm horizontal / 150mm vertically. (Note Do not begin a vertical lap within 300mm of corner)

  • Evidence

Top hats & Helping hands

  • Has correct materials been delivered to site?

  • Has setting out been checked against G/L and fixed with staggered pattern (250mm staggered pattern)

  • Have vertical centres (600 max typically, 150 at base) stagger as shown on 1st fix rail drawing?

  • Have studs been filled with insulation?

  • Have brackets been fixed correctly, 2 fixings for standard bracket, 3 for deadlock?

  • Have vertical T/L rails been fixed into helping hand (2 fixings for standard bracket, 4 for deadlock)?

  • Have the movement joint separation between vertical rails (level provided on drawings) been checked?

  • Evidence

Fire Barrier

  • Has the correct materials been delivered to site?

  • Has the number of fixings and orientation of spikes for both horizontal and vertical barriers been checked to ensure they are fitted centrally in barrier?

  • Have centres of fixings been checked to 250mm in from barrier edge, and 500mm centres thereafter?

  • Have horizontal barriers been tightly abutted (sealed if over 5mm wide) with max. 25mm void, mitred at corners?

  • Have vertical barriers been tightly abutted and sealed with approved FR mastic if over 5mm wide and with min 5mm compression?

  • Where applicable, have vertical rails obstructing horizontal barriers and brick slips gaps been sealed with PFC intumescent silicone, adhesion of product to checked prior to handover?

  • HOLD POINT RELEASE

  • Evidence

Insulation

  • Has thickness been checked, 230mm (2 slabs 170mm and 60mm) joints staggered.

  • Has insulation been fixed as per Rockwood guidance, min 70mm in diameter. (Min 1no stainless steel fixing per insulation)

  • Evidence

Brick slips

  • Has correct materials been delivered to site?

  • Have rails been fixed to each bracket?

  • Has brickslip bond and returns been checked?

  • Welded bracket fixed level, and back to concrete with 4no fischer resin anchor bolts at 200mm, drill hole 14 x 180mm

  • Have continuous horizontal channels fixed with 4no s/s M10 bolts?

  • Have helping hand brackets been fixed to channel with 3no s/s Tek screws?

  • Have centres of terracotta holding hooks been checked?

  • Has infill above / below terracotta band had a splice connector used with 8 BM-LS22 fixing?

  • Has an inset mesh been fixed utilising start bar fixings at base and dressed on top of terracotta band?

  • Is pointing completed, consistent and matches sample. Any excess is cleaned off slips

  • Evidence

Snagging

Snagging

  • Has area been snagged by a Certa manager?

  • Photos of identified snags

  • Photos of closed out snags

  • Can Final QA checks be carried out?

Final QA Checks

Certa QA Manager or Senior Manager final QA inspection

  • Have all sections of this form been complete?

  • Has sufficient evidence been provided?

  • Has area been de snagged?

  • Is area ready for handover?

  • Final QA photos

Handover

  • Certa Manager

  • On behalf of Certa RC

  • GMI Manager

  • On Behalf of GMI

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.