Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1. General
-
1.1 Did company representative accompany inspector?
-
1.2 Are all Safety/HazCom/Emergency Programs on site?
-
1.3 Are OSHA posters/emergency numbers posted?
-
1.5 Are safety meetings held/documented?
-
-
1.6 Are first aid kits available & properly stocked?
-
1.7 Are fire extinguishers available/charged/inspected?
-
1.4 Are confined space hazards identified & addressed?
-
1.8 Are all rebar/pipe & other impalement hazards capped/protected?
-
1.9 Are gas cylinders properly used & stored?
-
1.10 Is material storage proper?
-
1.11 Is housekeeping and sanitation proper & enforced?
-
1.12 Are flammable materials in approved containers & properly labeled?
-
1.13 Are all hand/power tools properly used/maintained/stored?
-
1.14 Are all operations performed at least 10 feet from overhead power lines?
-
1.15 Are competent flagmen properly dressed, trained & posted?
-
1.16 Are barricades/traffic control through & around site proper?
-
1.17 Are access/egress locations with a change in elevation >19 inches provided with stairs, ladders or ramp?
2. Equipment
-
2.1 Are parts/equipment free from damage?
-
2.2 Are all guards in place & working properly?
-
2.3 Is all equipment properly maintained & inspected?
-
2.4 Do backup alarms work?
-
2.5 Are equipment operators properly trained?
-
2.6 Are seatbelts operative & used?
-
2.7 Are aerial/scissors lifts properly used?
-
2.8 Are forks on the ground when parked?
-
2.9 Is the forklift operator in the seat with a raised load?
3. Personal Protective Equipment
-
3.1 Is all PPE provided by the employer?
-
3.2 Is respiratory protection proper?
-
3.3 Is hearing protection used & proper?
-
3.4 Is proper foot protection worn?
-
3.5 Is proper head protection worn?
-
3.6 Is proper eye protection worn?
-
3.7 Is hand protection/clothing proper?
-
3.8 Is PPE hazard assessment complete & on file?
-
3.9 Is Appendix D on file for voluntary respirator use?
4. Electrical
-
4.1 Are GFCI's or AEG Program in use?
-
4.2 Is temporary lighting used & proper?
-
4.3 Are Lockout/Tagout procedures in place & used?
-
4.4 Are temporary cords properly used & maintained?
-
4.5 Do all boxes/panels have covers & are all circuits labeled?
-
4.6 Are arc flash hazards identified & addressed?
-
4.7 Are generators over 5kv properly grounded?
5. Fall Protection
-
5.1 Are fall protection plans required & in place?
-
5.2 Is fall protection provided at heights over 6 feet?
-
5.3 Is fall protection equipment inspected & maintained?
-
5.4 Are stairways properly protected & used?
-
5.5 Are ladders properly used & maintained?
-
5.6 Are all floors holes properly covered or protected?
-
5.7 Is the roofer's warning line system/roof monitor system proper?
6. Steel Erection/Cranes
-
6.1 Is site access/layout/storage area proper?
-
6.2 Has GC provided all written documents for erection process to begin?
-
6.3 Is a Steel Erection Plan required & in place?
-
6.4 Is crane setup proper?
-
6.5 Is crane properly maintained/copy of annual inspection available?
-
6.6 Is rigging hardware inspected daily?
-
6.7 Are loads properly rigged/carried?
-
6.8 Are areas under swinging loads properly barricaded & enforced?
-
6.9 Are rigger & signalperson trained/qualified?
-
6.10 Are steel erection procedures proper?
-
6.11 Are 2-bolt connections/4 bolt column anchor requirements followed?
-
6.12 Are connector requirements in compliance?
-
6.13 Does Controlled Decking Zone meet standards.
-
6.14 Are employees using fall protection above 15 feet?
-
6.15 Are oxygen & acetylene bottles properly used & stored?
-
6.16 Is a Hot Work Permit completed & posted when required?
-
6.17 Is perimeter safety cable properly installed & used?
7. Masonry/Scaffolding
-
7.1 Is scaffold competent person on site?
-
7.2 Are all scaffold users properly trained?
-
7.3 Are scaffold erection/disassembly procedures proper?
-
7.4 Is fall protection provided for erectors/dismantlers?
-
7.5 Are baseplates/mud sills stable & proper?
-
7.6 Are all scaffold frames pinned together?
-
7.7 Is scaffold tied to structure using stiffbacks?
-
7.8 Are scaffold frames/planks/parts free of damage & defects?
-
7.9 Are walk/work planks properly installed & set?
-
7.10 Are guardrails properly installed & used?
-
7.11 Are toe boards/warning line properly installed & used?
-
7.12 Is scaffold access proper?
-
7.13 Are masonry walls properly braced?
-
7.14 Is the Limited Access Zone set & enforced?
-
7.15 Are mixer operations proper?
-
7.16 Is wet-cutting or respiratory protection in place?
8. Trenching/Excavating
-
8.1 Is the trench competent person on site?
-
8.2 Is the trench/excavation inspected daily?
-
8.3 Has a proper soils analysis been conducted?
-
8.4 What is the soil type?
-
8.5 Is employee protection proper for soil type & depth?
-
8.6 What type of employee protection is in place?
-
8.7 Is safe access/egress provided?
-
8.8 Are water removal procedures proper?
-
8.9 Has the trench been evaluated as a confined space?
9. Summary
-
The overall rating for this audit is?
-
Comments
-
Supervisor signature