Title Page
-
Vessel Serial Number
-
Customer
-
Date
-
Prepared by
-
Work order Number
NOTE: All vessels MUST be checked and all works completed prior to dispatch from CES site and recorded in vessel file
-
1. Product and Safety Relief Settings: Please select product first by touching 'Response'
- 684 - LOX Medical
- 673 - LOX Laser
- 686 - LOX Industrial
- 687 - LOX Hospitality
- 702 - LIN Scientific
- 712 - LIN Laser
- 719 - LIN Industrial
- 723 - LIN Hospitality
- 731 - LAR Welding
- 734 - LAR Scientific
- 738 - CO2 Dry Ice
- 740 - CO2 Welding
- 755 - CO2 Hospitality
- Other
-
Safety Relief Settings:
-
Safety Relief Settings:
-
24 bar
-
24 bar
-
Product and Code:
-
2. Is liquid withdrawal required?
-
3. Is decant fill required?
Checks to be Carried Out
Checks to be carried out
-
Is the vessel clean and in good condition? e.g. free of spider webs, debris and tank exterior is not soiled
-
Are all labels attached correctly according to LiMSS document 'CESPRC-09-610-RSP - CRYOSPEED Cryotank guide, Table 6. Cryotank Label Locations with Dimensions'?
This includes latest BOC logos, valve position labels, operating and safety instruction labels for specific gas service, including Customer Service number: 131 262 and CES contact number: 1800 624 006 -
BOC Logo
-
Product Label
-
No Smoking
-
Safety Notice
-
'Do not vent' sticker (CO2 only)
-
Schematic drawing on vessel, valve handle colour coding and numbering compliant with BOC Vessel Specification in LiMSS document 'CESPRC-09-610-RSP - CRYOSPEED Cryotank Guide'?
-
Valve handle colouring correct?
-
Valve numbering correct?
-
Schematic drawing on vessel?
-
Does P&ID match the piping on tank?
-
If required, is the CRYOSPEED conversion kit installed as per standard work procedure in EMOC?
-
Do vessel and thermal relief valves match gas service, are they tagged and dated? (Please enter tag numbers and dates)
Please enter tag numbers and dates here (touch 'Add Element' or the plus sign to begin)
-
Tag name (e.g. PV1)
-
Tag Number:
-
Date on tag:
-
Existing condition:
-
Is gas service fill coupling installed and tested? <br>(Refer to drawing 'D405-1052_S1 - Technical Details for Standard Cryotank Vessels' in LiMSS document 'CESPRC-09-610-RSP - CRYOSPEED Cryotank Guide' for specific details)
-
Check and set pressure build, economiser and back pressure regulator (CV1, CV2 and CV3) as per Table 5 in drawing 'D405-1052_S1 - Technical Details for Standard Cryotank Vessels' in LiMSS document 'CESPRC-09-610-RSP - CRYOSPEED Cryotank Guide'
-
Is GASLOG telemetry unit installed?
-
Gaslog Serial Number:
-
Are gauge indicator stickers marking 'Normal Operating Pressure' and 'Relief Valve' set points in place?
-
Are gauges marked 'Indication Only'?
-
Is 'OK Staff' in place?
-
Is Data Plate in place?
-
Has the vessel been purged prior to delivery?
-
Please select the purge gas used
-
Please give details on why a vessel purge was not completed
-
Please attach as many photos as required showing: 1. Vessel labels and schematics 2. Valve handles 3. Fill coupling 4. Telemetry system 5. Indicator stickers marking 'Normal Operating Pressure' and 'Relief Valve' set points 6. 'Indication Only' tags and 'OK Staff' plate
-
Additional comments:
Sign Off
-
Completed by:
-
Name:
-
Signature
-
Date:
-
Checked by:
-
Name:
-
Signature
-
Date: