Piling
-
Site
-
Description
-
Prepared by
-
Sub Contractor / Self-Delivery
-
Sub Contractor
-
Location
-
Drawing Reference
Work Item
Preparation
-
Date
-
Obtain piling mat design
-
Piling mat at correct level
-
Check setting out of pile locations
-
Check requirement for load/Integrity testing
-
State requirement
-
Establish cut off levels
-
Ensure debonding foam is secure and correct length
-
Check reinforcement cage
-
Method statement/risk assessment in place
Application
-
Date
-
As built of piles surveyed at cut off level
-
Reinforcement projection correct
-
Integrity tests undertaken
-
Load test undertaken
Final Inspection
-
All areas complete for final inspection
-
Notification of Inspection raised
-
Approved for commencement of next Trade
Remarks
-
undefined
Final Sign Off
Name & Signature
-
For Brims -
-
For Client