Curtain wall site inspection form
-
Client: Wates construction
-
Job title: Wembley Park NW07 NW08
-
MPrice inspection
-
Location
-
Block or phase
Curtain wall frame inspection
General
-
Is frame set out to correct gridline and datum?
-
Is frame level and plum?
-
Deflecting block installed and sealed
-
Is the movement gap as per detail 10-15mm?
Fixings and brackets
-
Are brackets isolated where needed?
-
Are the correct flat plates fixed to the set dimensions?
-
Are the correct galvanised packing shims used?
-
Are the correct fixings (countersunk on SFS & tek head on mullion) used?
-
Have the bolts been torqued to the correct settings.?
Gasket
-
Has the correct gasket been used?
-
Is gasket clean and damage free?
-
Have vulcanised corners been fitted and sealed correctly?
-
Are drainage channels clear of debris?
-
Is frame clean and clear of debris?
-
Are thermal breaks in acceptable condition?
Glass inspection
-
Have the correct shoes been used ?
-
Is the glass even to the gasket margins?
-
Is the glass sitting on packers ?
-
Glass free from damage and clean ?
-
Correct glass spec use for frame type and location ?
PRESSURE PATES & CAPS
-
Have the correct pressure plates been use?
-
Have the plastic washers been used ?
-
Have the correct length screws been used and torqued to the correct settings.?
-
Is there a deflection gap as per detail?
-
Have the correct caps been used and a maximum of 3mm gap between mullion and transom ?
FIRE STOPS
-
Have all fire stops been installed correctly & spec used I.E correct fixings, brackets, compression, fire mastic?
Pictures of curtain wall
-
Pictures of curtain wall
Comments
-
Are there any comments?
Signatures
-
On behalf of MPrice
-
On behalf of Wates