Site conducted
-
Location
-
Conducted On
-
Prepared By
EMPLOYEE TRAINING & CERTIFICATIONS
-
Employees engaged in ammonia transfer operations are current on (3 year) CVA Ammonia Handler Certification?
-
Employees engaged in pulling ammonia trailers hold appropriate CDL and Endorsements?
RESPIRATORY PROGRAM COMPLIANCE
-
Employees engaged in ammonia transfers have completed a medical evaluation and are current on fit testing?
BULK PLANT COMPLIANCE
-
EMERGENCY WATER - adequate clean water in tanks that provide immediate access for first aid?
-
WORKING WALKING SURFACES - All working walking areas are maintained in safe condition?
-
COMBUSTIBLES - Areas within 10' of storage tanks and piping are free of vegetation and combustible items?
-
RISER STANDS - free of defects and provide adequate access to fill nurse tanks (without standing on tires)?
-
WIND SOCKS - free of defects and in the immediate area of the ammonia bulk plant?
-
LEAKS - ammonia storage and transfer systems are free of leaks?
-
HOSES - NH3 transfer hoses are in good condition and within the marked replace-by dates?
-
MAINTENANCE & REPAIR - ALL tanks, piping, pipe fittings, valves, and safety devices are in proper working order and maintained in a manner to prevent rust and deterioration?
-
MARKINGS & SIGNS - All required signs and markings are properly placed, free of damage, and legible?
-
SAFETY EQUIPMENT - chemical gloves, respirators with (min. of 2) extra sets of NH3 respirator filter cartridges, rain coats, and rubber boots are available at bulk plant during filling operations?
-
SECURITY - bulk plant and fill hoses are properly secured when plant is unattended?
NURSE TANK SAFETY
-
All nurse tanks are safe before sending out to customer (emergency water saddle tanks, safety chains, free of leaks, proper markings, etc.)
NURSE TANK INSPECTIONS
-
TANK UNIT NUMBER
-
LIST OF DEFECTS - Inspect for damage, maintenance & repair issues, SMV Emblem, safety chains, plumbing, emergency water tanks.
-
PHOTOS
OBSERVATIONS
-
PPE - Proper use of PPE (Gloves, Respirator, Long Sleeves) with 25 feet of loading platform?
-
WHEEL CHOCKS - Proper use of wheel chocks when filling tanks?
-
HITCH PIN / KEYS - Hitch pin or keys removed before filling nurse tanks?
-
FILLING PROCESS / SEQUENCE - Employees follow proper processes and sequence when filling nurse tanks?
-
HOSE END VALVES - Proper handling of hose end valves and storage of hose end valves when filling nurse tanks?
-
OTHER OBSERVATIONS
Certification
-
Auditor Signature
-
Facility Representative