  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • This document is to be used in conjunction with the Final Design Approval Drawings supplied by CFSGAM Ð this checklist is for internal use only

  • Date:

  • Tenancy No

  • Tenancy Name

  • Inspection by:

Shopfront & Signage

  • Demising wall finish is complete as per approved drawings?

  • FHR cupboards treated as part of shopfront?

  • Materials & signage to shopfront is complete as per design approved drawings ?

  • Materials to shopfront are finished neatly with no gaps, scratches nor marks ?

  • No hand written posters / signage to shopfront ?

  • Only 1 primary signage to shopfront?

  • Shopfront sign is on and operational?

  • Illumination to primary signage is evenly spread throughout with no dark spots?

  • Signage is positioned in correct position and location as per plans?

  • Cables, wiring, clips, transformers, lamps, tubes, labels or plates to signage are to be concealed?

  • Fixings to signage are concealed, no screw heads visable?

  • No commercial brands are displayed other than approved trading name?

  • Internal signage is installed in correct location as per approved plans?

  • Glazing to shopfront is clean and scratch fee?

  • Silicone to glazing to be completed neatly and not applied thick?

  • Recessed glazing channels to shopfront?

  • Half height fins are installed (if applicable)?

  • No tag lines?

  • Corner protection?

Door Closure

  • Closure in open position, must be completely concealed from customer view?

  • Floor locking plates & holes are finished flush with floor?

  • Guides to closure are recessed in surrounding shopfront structure?

  • Closures glass or acrylic infill are clean?

  • Shopfront sign is on and operational?

  • Motorised shutters are operational?

  • Ensure storage space for removable mullions has been provided in BOH or out of sight?

Mall Bulkhead

  • Mall bulkhead is made good and painted to centre colour specifications?

  • Sprinkler heads not damaged (if applicable)?

Exit Signage

  • Edge lit blade exit sign installed?

  • Exit sign control gear and boxing are fully recessed?

Window Display & Merchandising

  • Shopfront window display area is merchandised?

Plasma Screens

  • Kiosks not to project beyond lease line?

  • To be installed flush with shopfront?

  • Completed as per design approved plans?

  • Screens are on and operational?

  • Cables, wiring, clips, transformers, lamps, tubes, labels or plates to plasma screens are concealed?

  • No moving images allowed Ð only static?

Floor Treatment

  • Floor treatment to tenancy is as per approved plans?

  • Floor levelling to shopfront line is finished flush with mall tile?

  • Mall tiles to shopfront area rectified with no gaps, chips or grout missing?

  • Recessed protective metal angle butt-joins the mall tile?

  • Tile ingo to shopfront area complies with centre specific tile finish?

  • If carpet is applied to the internal of tenancy, carpet is smooth with no folds or trip hazards?

  • If tiles are applied to the internal of tenancy, tiles are level, cleaned and grouted?

  • External tenancies to have approved recessed door matt?

Ceilings

  • Ceiling is constructed as per approved plans?

  • Should grid ceiling be approved, all tiles are in place and no damaged tiles?

  • Flush plaster ceiling is smooth finish?

  • Flush plaster ceiling is painted?

  • Thermostat is affixed to location as per Mechanical Consultant Report?

  • A/C services ÐSupply Air Registers & Return Air Registers are positioned in accordance with Mechanical Consultant Report?

  • Access panel for roller shutters to be free of marks and flush with ceiling?

Access Panels

  • Access panels are flush mounted 600x600

  • Access panels are located in appropriate positions to access essential services

Open Ceilings

  • Centre roof and services are spray painted out?

  • A/C Services Ð Registers, cushion boxes are hung / fixed in safe manner?

  • A/C services ÐSupply Air Registers & Return Air Registers have been positioned in accordance with Mechanical Consultant Report?

  • A/C distribution hard duct is installed?

  • Thermostat is affixed to location as per Mechanical Consultant Report?

  • Inter-tenancy walls are extended to the roofline?

Lighting

  • All wiring to be concealed?

  • Lighting layout is as per approved plans?

  • Lighting specifications is as per approved plans?

  • Lighting is on and operational?

  • No globes out?

  • No flashing lights?

  • No surface mounted circuits?

Sprinklers

  • All Scutchen plates are installed?

  • ÔOrangeÕ Safety guards off?

  • Fire Extinguisher has been installed?

  • Fire blanket has been installed?

First Aid

  • First Aid Kit located in store

Internal of Fitout

  • Painted areaÕs are neat and streak free?

  • Fixtures and fittings specifications are as per approved plans?

  • Fixtures and fittings layout is as per approved plans?

  • No chips or cracks to fixtures and fittings?

  • All plumbing pipes and connections are concealed?

  • Graphics to internal of fitout is installed?

  • Graphics to internal of fitout is not damaged?

  • Service counter to be at lease 1200 from lease line unless otherwise approved?

Statutory Signage

  • In place as per Building Code (i.e. fire access, switchboard, etc)?

Security

  • Intruder warning light not allowed outside shopfront?

General Comments

  • General comments from inspection:

Inspection Signoff

  • Inspected by:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.