Title Page
-
Site conducted
-
Quality Control Check Name
-
Conducted on
-
Account used
-
Location
-
Elevations
-
Elevation
-
Floor Level
- level 1
- level 2
- level 3
- level 4
- level 5
- level 6
- level 7
-
Section(s)
- Section 1
- Section 2
- Section 3
- Section 4
- Section 5
- Section 6
- Section 7
- Section 8
Waterproofing / Sealing / ME010 /
-
Has the ME010 been installed correctly around window perimeters as per Illbrook recommendations & bonded with SP025
-
Please describe the nature of the issue
-
Has this now been rectified and reinspected?
-
Please describe what actions were carried out to rectify the issue
-
Is the Tyvek breather membrane sealed at all joints and damage free?
-
Please describe the nature of the issue
-
Has this now been rectified and reinspected?
-
Please describe what actions were carried out to rectify the issue
-
Are the Tyvek horizontal laps at minimum 100mm overlap. & Vertical laps at 150mm overlap
-
Please describe the nature of the issue
-
Has this now been rectified and reinspected?
-
Please describe what actions were carried out to rectify the issue
Completion
-
Are there any other notes relevant to this particular Elevation/Scaffold Level not covered by the previous questions?
-
Are there any other photos relevant to this particular Elevation/Scaffold Level not covered by the previous questions?
-
Sign below to confirm that questions above have been answered truthfully and with all relevant due diligence having been carried out. Please include the person's name.
-
Russell Roofing Signature