  • Job No.

  • Conducted on

  • Design Member

  • Completed By

  • Is a Design Register Sheet (DRS) set up for the project?

  • Are all relevant sections of the DRS complete?

  • Are all project drawings including consultant & subcontractor drawings included in the register?

  • Is a designers risk assessment completed highlighting both site risks and residual As-Built risks?

  • Has a DRA drawing been produced or included within the scope drg / scope of works?

  • Are all drgs issued to site / QS team in sufficient time to capture orders and details?

  • Are all dates recorded including return visits?

  • Hyperlink or scan / photo of relevant planning and/or building control including any conditions discharged or outstanding.

  • Has the site visit register been filled in sufficiently?

  • Has a project overview been carried out with the line manager prior to drawing issue?

  • AUDITOR NOTES:

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.