1. Administration and First Aid

  • Has an audit on administrative procedures been carried out for this project?

  • 1.1 Safety Management Plan available or review?

  • 1.2 Site inductions for workers, sub-contractors & visitors being carried out in accordance with SMP?

  • 1.3 Supervisory arrangements in accordance with SMP?

  • 1.4 Required training, licenses and skills register maintained in accordance with SMP?

  • 1.5 SWMS for High Risk Construction Work reviewed and monitored in accordance with SMP?

  • 1.6 Sub-contractor SWMS reviewed in accordance with SMP?

  • 1.7 Incident Notification process in accordance with SMP?

  • 1.8 Site safety inspections, safety walks, or audits carried out in accordance with SMP?

  • 1.9 Toolbox meetings, site meetings or other consultative arrangements being conducted in accordance with SMP?<br> Take photos of toolboxese tic.

  • 1.10 Emergency response plan displayed on site?

  • 1.11 Emergency evacuation procedure displayed on site/

  • 1.12 Adequate First Aid kit on site?

  • 1.13 Access available to trained first aider/s?<br> Copy of certificate

  • 1.14 Plant and equipment register maintained in accordance with SMP?

  • 1.16 Hazardous chemical/substance register maintained in accordance with SMP?

  • 1.17 Safety Data Sheet register maintained in accordance with SMP?

  • 1.18 Safety Data Sheets available on site?

  • 1.19 Traffic Management Plan in place in accordance with SMP?

  • 1.20 Does SMP identify any activities requiring permits to be used, (i.e. Hot Works, Excavation Work)?

  • 1.21 Is an Environmental Management Plan in place for the site?

  • 1.2.1 Pick 3 persons signed in for the day and check against induction records.<br> Take photos of induction form.

  • 1.3 Is the first aid shed/office clearly identified as such with the correct signage. (White cross on green background)?

  • 1.4 Open the 1st aid kit and check for certification every 12 months.

  • 1.5 How many 1st aiders are on site. Should be a ratio of 1 to 25 in a high risk/construction environment?

  • 1.6 Is there a first aid room ? Should be a facility for this if 100 workers or more.

  • 1.7 How is 1st aid managed ? Principal contractor is responsible to ensure they supply it or the sub-contractor manages it and has available 1st aiders.

2. Site Security

  • 2.1 Site fencing adequate to prevent unauthorised access?

  • 2.2 Is Site Signage displayed, and in a prominent and easily visible place?

  • 2.3 Does signage include the name of the PC carrying out the building works?

  • 2.4 Does signage give the location of the site office?

  • 2.5 Specify an after hours contact number?

HIGH RISK ACTIVITIES

3.1 Working at Heights

  • 3.1 Are there workers working at heights above 2m on site today?

  • 3.1.1 Has a SWMS for this task been implemented ?<br> Photo of SWMS.

  • 3.1.2 Are adequate fall protection measures in place?

  • 3.1.3 Are Fall Arrest Devices (FAD) being used as the means of fall protection (i.e. Harnesses)?

  • 3.1.4 Is there evidence that the FAD has been regularly inspected and maintained?<br>Photo of inspection tag.

  • 3.1.5 Are workers trained in use of FADs. Photo of Safe Working at Height certificate.

  • 3.1.6 Have permanent anchor points been inspected and certified within the last year ?<br>If used take photo.

  • Is there a permit system to use a harness ?<br>Copy of permit.

  • 3.1.8 If there is a permit system has it been filled in and is a copy with the worker ?

  • 3.2 Are Extension ladders being used to access work areas?

  • 3.2.1 Are ladders in good condition and safe for use?<br>Photo of ladder.

  • 3.2.2 Are ladders adequately secured top and bottom?

  • 3.2.3 Are ladders erected at approx a 1:4 ratio?

  • 3.2.4 Is ladder erected to extend 1 metre past step off point?

  • 3.3 Are Step Ladders being used to access elevated work areas?

  • 3.3.1 Are ladders in good condition and safe for use?

  • 3.3.2 Are ladders specified for industrial use?

  • 3.3.3 Are ladders being used in accordance with manufacturers recommendations (i.e. not or electrical work/do not stand on top two rungs)?

  • 3.4 Are Elevated Work Platforms (EWP) being used to access elevated work areas (i.e. Scissor lifts, boom lift)?

  • 3.4.1 Are EWPs in good condition and safe for use?

  • 3.4.2 Are log books being regularly filled out?<br>Photo of log book.

  • 3.4.3 Are High Risk Work Licenses required for this type of plant? Boom lifts over 11m require (WP) license.

  • 3.4.3.1 Are operators appropriately licenced?

  • Take copy of license.

  • 3.4.3.2 If a boom lift is used are operators using a connected safety harness?

  • 3.5 Are Mobile Scaffolds being used to access elevated work areas?

  • 3.5.1 Are Mobile Scaffolds in good condition and safe for use?

  • 3.5.2 Does mobile scaffold have internal ladder access?

  • 3.5.3 Are work platforms fitted with kick boards?

  • 3.6 Are there excavations deeper than 1.5 Meters on site ?

  • 3.6.1 Is the excavation battered, benched or shored to prevent a collapse.

  • 3.6.2 Is safe access provided? (Ladders, ramped access that is clear of loose material and not excessively sloped or steps cut into bank less each than in height)

  • 3.6.6 Are barricades in place to prevent falls ?

4. Plant and Equipment

  • 4.1 Is Mobile Plant being used on site today (backhoe, telescopic handler, mobile crane, vehicle loading crane)?

  • 4.1.1 Is Mobile Plant in good condition and safe for use?

  • 4.1.2 Has a SWMS for HRCW been implemented for this work?

  • Has a risk assessment or a JSA been conducted ?

  • 4.1.3 Is Traffic Management Plan in place in accordance with SMP?

  • 4.1.4 Has mobile plant been regularly inspected, tested and maintained?

  • 4.1.5 Does mobile plant involve lifting equipment?

  • 4.1.5.1 Are slings, chains and associated lifting equipment regularly inspected and well maintained? A dated tag or similar should be visible.

  • 4.1.5.2 Is SWL information displayed?

  • 4.1.5.3 Are operators appropriately licensed (HRWL). Should have DG or Dogman class.?

  • Take photo of license.

  • 4.2 Are Electrical Power Tools being used on site today?

  • 4.2.1 Are Power Tools in good condition for use?

  • 4.2.2 Are Power tools tested and tagged in accordance with AS/NZ 3012:2010?

  • 4.2.3 Are Power Tools specified for industrial use?

  • 4.2.4 Are Power Tools supplied through a portable RCD?

  • 4.2.5 Are portable RCD's tested and tagged in accordance with AS/NZ 3012:2010?

  • 4.3 Are Extension Leads being used on site today?

  • 4.3.1 Are Extension Leads in good condition and no exposed wires?

  • 4.3.2 Are Extension Leads tested and tagged in accordance with AS/NZ 3012:2010? Minimum every 3 months

  • 4.3.3 Are Extension Leads appropriately suspended off the ground?

  • 4.3.4 Are Extension Leads being used correctly (i.e. not joined together)?

  • 4.3.5 Are portable RCD's tested and tagged in accordance with AS/NZ 3012:2010?

  • 4.4 Are Electrical Portable Outlet Devices (EPODs) being used on site today (power boards)?

  • 4.4.1 Are EPODs suitable for construction work (i.e. not domestic type)?

  • 4.4.2 Are EPODs in good condition and not damaged?

  • 4.4.3 Are EPODs tested and tagged in accordance with AS/NZ 3012:2010?

  • 4.5 Is other Electrical Plant being used on site today (cement mixers, tile elevators, etc)?

  • 4.5.1 Is the identified equipment in good condition and safe for use?

  • 4.5.2 Is the identified equipment tested and tagged in accordance with AS/NZ 3012:2010?

  • 4.5.3 Is the identified equipment supplied through a portable RCD?

  • 4.5.4 Are portable RCD's tested and tagged in accordance with AS/NZ 3012:2010?

  • 4.6 Are items of Plant powered by petrol or diesel motors being used on site today (cement mixers, tile elevators, etc)?

  • 4.6.1 Is the identified equipment in good condition and safe for use?

  • 4.6.2 Is the identified equipment set up in well a ventilated area?

  • 4.6.3 Are fuel containers adequately stored in well ventilated and secure area?

  • 4.7 Are petrol or diesel generators being used on site today?

  • 4.7.1 Are Generators in good condition and safe for use?

  • 4.7.2 Are generators fitted with a built in RCD?

  • 4.7.3 Are RCD's tested and tagged in accordance with AS/NZ 3012:2010?

  • 4.7.4 Are Generators set up in well a ventilated area?

  • 4.7.5 Are fuel containers adequately stored in well ventilated and secure area?

5. Scaffolds

  • 5.1 Is Modular or Kwik stage scaffold erected on site today?

  • 5.1.1 Is scaffold complete and safe for use?

  • 5.1.2 Does Scaffold have a current Scaffold Tag ? Date should be within 30 days expiry.

  • 5.1.3 Is access to work decks installed correctly and safe for use?

  • 5.1.4 Do work decks have adequate hand rails installed (top & mid rails)?

  • 5.1.5 Are kick boards installed on work decks?

  • 5.1.6 Are mesh guards installed where work decks have building materials stored on them?

  • 5.1.7 Are sole boards visible and every standard has one positioned under it ?

  • Is A frame or trestle type scaffold in use

  • Is adequate fall protection in place ?

  • Is there safe access to the work deck ?

6. Temporary Electrical Installation

  • 6.1 Is mains power connected to provide temporary power to site?

  • 6.1.1 Are socket outlets protected by an RCD?

  • 6.1.2 Does RCD have a current inspection Tag ?

  • 6.1.3 Does switchboard allow for leads to be entered so that lid can be closed without damaging leads?

  • 6.1.4 Is switchboard easily accessible and free of obstruction?

  • 6.1.5 Are enough switchboards installed to ensure leads do not need to be joined together to reach work areas?

  • 6.1.6 On multi level sites, are switchboards located to ensure leads are not run from one level to another?

  • 6.1.7 Are sockets outlets overloaded ?

  • 6.1.8 Does electrical contractor have an effective electrical isolation procedure?

  • 6.2 Are site sheds connected to mains power?

  • 6.2.1 Is supply to site shed hard wired to a circuit breaker?

  • 6.2.2 Is site shed supply cable installed to prevent mechanical damage?

  • 6.2.3 Are extension leads being run out of site shed to supply work areas?

  • 6.2.4 Are socket outlets in site shed protected by RCD?

  • 6.3 Are overhead power lines present on or adjacent on this site?

  • 6.3.2 Is plant or equipment operating near or under overhead conductors?

  • 6.3.1 Are power line conductors fitted with visual warning indicators (tiger tale, line flags) ?

7. Personal Protective Equipment (PPE) & Permit Works

  • 7.1 Does site have a sign indicating minimum PPE requirements, (i.e. hard hats, safety boots, Hi Vis)?

  • 7.1.1 Are workers wearing PPE in accordance signage requirements?

  • 7.2 Are workers wearing appropriate PPE for specific hazardous tasks, (i.e. using angle grinder)?

  • 7.3 Are any activities being carried out requiring a permit as identified in the SMP?

  • 7.3.1 Have permits been completed and approved prior to works commencing?

8. Work Environment

  • 8.1 Do workers have ready access to adequate amenities? (toilets, wash areas, lunch rooms, etc)

  • 8.2 Is site well maintained, clean and tidy, (i.e. good housekeeping)?

  • 8.3 Is lighting sufficient?

  • 8.4 Is adequate noise/ vibration control in place if required?

  • 8.5 Are there any other uncontrolled hazards not already covered

  • 8.6 Audio-metric testing. Ask for evidence of audiometric testing if applicable. Testing should be done if PPE is used as a control measure, i.e. ear plugs or muffs, and the worker has been there 3 months or more

9. Environmental Hazards

  • 9.1 Are adequate controls in place to prevent contaminants entering stormwater drains?

  • 9.2 Are adequate dust suppression controls in place?

  • 9.3 Are the excavations that could affect Underground services being worked on

  • 9.3.1 Is there a system in place to check for underground services such as a permit system?

  • 9.3.2 Has the system been implemented

  • 10.0 Are any works required to stop ? Provide detail.

Corrective Actions

  • All items identified in this audit must be addressed by the contractor responsible for the site.
    The contractor must use a risk based approach to address any issues. Where there is a need to implement an interim control until the hazard can be permanently addressed this must be documented.
    Where there has been a system failure DHA will require a written plan to address how the company will prevent a re-occurrence.

  • Enter any corrective actions that have been discussed onsite.

  • Additional photos taken from audit.

Sign Off

  • On site representative

  • Auditor's signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.