Title Page
-
TPG Job Number
-
DB Reference
-
Client
-
Site
-
Conducted on
-
TPG Engineer
Test Equipment
-
IR Tester Calibration Number & Due Date
-
M8 Torque Wrench & Due Date
General Checks
-
Paintwork
-
Incoming Connections Torque Tested
-
Outgoing MCB/RCBO Devices Fitted
-
Outgoing MCB/RCBO Devices Torque Tested
-
Outgoing Metering - P1 On CT Facing Outgoing Device
-
Incomer Metering - P2 On CT Facing Mains Incomer
-
Small Voltage/CT Cabling Pull Check On All Terminations
-
DB Switchboard Fully Vacuumed
-
Isolation Sliders Closed
-
Title Labels Installed As Per G.A Drawing
-
Surge Device Fitted & Connections Torque Tested
-
Metering Device Installed
-
Current Transformer Installed
- 250A/5A
- 160A/5A
- 125A/5A
- 100A/5A
- 250A/330mV
- 160A/330mV
- 125A/330mV
- 100A/330mV
-
Number Of Ways
-
PM3255 Metering Device
-
PM5110/PM5111 Metering Device
-
Rayleigh RI-F400/RI-F300 Metering Device
-
Rayleigh RI-360/380/460/480
End to End Continuity Test
-
Operate Mains Incomer Into Closed Position
-
Connect Test Probe 1 On Incoming Terminal - L1
-
Connect Test Probe 2 On End Of Main Busbar - L1
-
Connect Test Probe 1 On Incoming Terminal - L2
-
Connect Test Probe 2 On End Of Main Busbar - L2
-
Connect Test Probe 1 On Incoming Terminal - L3
-
Connect Test Probe 2 On End Of Main Busbar - L3
-
Connect Test Probe 1 On Incoming Terminal - N
-
Connect Test Probe 2 On End Of Main Busbar - N
-
Connect Test Probe 1 On Incoming Earth Bar
-
Connect Test Probe 2 On End Of Outgoing Earth Bar
-
Operate Mains Incomer Into Open Position
-
Operate Bus-Coupler Into Open Position
Insulation Resistance Test
-
ENSURE ALL FUSES HAVE BEEN REMOVED PRIOR TO TESTING
-
ENSURE SURGE MCB IS IN THE OPEN POSITION, IF 3P ENSURE NEUTRAL IS DISCONNECTED
-
TEST METER PRE TESTING BY SHORTING PROBES OUT AND CONFIRM 0MΩ
-
L1 - EARTH (MΩ)
-
L2 - EARTH (MΩ)
-
L3 - EARTH (MΩ)
-
L1 - L2 (MΩ)
-
L1- L3 (MΩ)
-
L2 - L3 (MΩ)
-
L1 - NEUTRAL (MΩ)
-
L2 - NEUTRAL (MΩ)
-
L3 - NEUTRAL (MΩ)
-
NEUTRAL - EARTH (MΩ)
-
TEST METER POST TESTING BY SHORTING PROBES OUT AND CONFIRM 0MΩ
-
ENSURE ALL FUSES HAVE BEEN RE-INSTATED POST TESTING
-
ENSURE NEUTRAL CABLE HAS BEEN RE-CONNECTED IF DISCONNECTED ON 3P DEVICE
Snagging Items
-
Item No.1
-
Item No.2
-
Item No.3
-
Item No.4
-
Item No.5
-
Item No.6
-
Item No.7
-
Item No.8
-
Item No.9
-
Item No.10
-
Item No.11
-
Item No.12
-
Item No.13
-
Item No.14
-
Item No.15
-
Item No.16
-
Item No.17
-
Item No.18
-
Item No.19
-
Item No.20
Sign off
-
TPG TEST ENGINEER
-
ASSEMBLED BY
-
SIGNATURE
-
TEST ENGINEER NOTES