Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location
  • Operative being assessed

Tools and equipment

  • Calibrated, certificated test standpipes

  • Electronic test equipment

  • Pressure testing warning signs (MP mains)

  • Pipe anchorage systems. (Refer to SGN/WI/DIS/4.2.2 - Anchorage systems operating up to 7bar <br>– operatives)

  • Air compressor 80cfm-100cfm, foot pumps

Installation of standpipes &pressure gauges

  • Standpipes and gauges must be connected in accordance with Figure 95 in (SGN/WI/ML/2) and the following
    must be carried out:

  • Standpipes must be located at all extremities of the new main and incorporate a relief valve set to<br>lift at a pressure 10% above the specified test pressure

  • Pressure test instruments must be installed so that they can be read and operated without <br>entering the trench or standing in line with the end of the main

  • Pipe systems under test must be restrained against movement. For all fused systems, it is<br>sufficient to backfill the pipe under test

  • Test standpipes must all be of welded construction, have a current test certificate and be tested <br>for soundness immediately prior to testing the pipeline or main

  • Warning notices must be prominently displayed to warn that pressure testing being carried out

Pressure test requirements

  • Suitable test instruments are bourdon test gauges for LP mains or electronic testers for both LP and MP <br>mains. The following must be checked before pressurising the main:

  • As determined by the Operation Manager an NRO/RO procedure must be authorised and all safety precautions carried out prior to the test commencing

  • To minimise the effect of temperature variation; the main under test should be backfilled as much <br>as possible and If the effects of temperature are to be taken into account this will be detailed in<br>the NRO/RO procedure

  • Both LP and MP mains must be maintained at 350mbar air pressure, post testing, if purging and <br>commissioning is delayed

  • All fittings must be approved for use

  • Test the pressure relief values on the standpipes to ensure that they are set to operate at 10% <br>above the test pressure

  • All values must be tested in the open position and sealed with a blank flange

  • As applicable the Operation Manager or Operative must brief all team members on the test <br>process prior to and during the test period

  • Use approved electronic test instruments that provide absolute pressure readings

Test requirements for MP mains

  • The Operation Manager will specify the pressure test requirements that will be<br>required and will provide a NRO/RO procedure. The following factors must be taken into account:

  • Noise levels whilst pressure testing is to be kept to a minimum

  • If a hydrostatic test is deemed necessary, then this must be undertaken in accordance with<br>Section G3, (SGN/WI/ML/2)

  • Creep occurring in PE pipe must be accurately accounted for

  • Where creep allowances are to be applied to PE mains tests, it is important that the exact <br>conditioning time is established by recording the time of commencing pressurisation and the time <br>at which the first test reading is taken. Conditioning time includes the effects of the 2-hour<br>stabilisation period. The Operational Manager will determine the conditioning time

Pressurisation of the main

  • A Competent Operative must be in attendance at the pressurising point during the pressurisation<br>period to ensure that the necessary safety requirements are met

  • No person must enter the designated test area or interfere with the pipe work whilst the pressure<br>is being raised

  • A single or twin tool compressor (80 cfm to 100 cfm) with an inline fitter or foot pump is adequate for pressurising the majority of pipe systems

  • Examine flexible pipes, hoses and their connections prior to use to ensure they are fit for their <br>intended purpose. They must be secured and anchored by a secondary restraining device, (whip<br>check) to prevent movement as a precaution in the event of failure<br>

  • Air must be introduced under controlled conditions into the main until the appropriate test<br>pressure is reached

  • The time of commencing pressurisation must be recorded on the test certificate

  • Do not over pressurise the main

Pressure test

  • Before the start of the test period, the temperature of the air in the main must be allowed to<br>stabilise before the test period commenced

  • For metallic mains and low-pressure PE mains, this will normally occur within 2 hours, and will be<br>indicated by a stable pressure reading

  • For Medium Pressure PE mains, the effects of creep must be taken into account and the <br>conditioning time allowed as specified by the Operation Manager

  • All exposed mechanical joints must be tested for leakage upon initial pressurisation with an <br>approved leak detection fluid

  • Following the period of the temperature stabilisation, the initial pressure reading must be taken. <br>For PE mains at MP (where the effect of creep is being taken into account) the first test readings<br>must be taken at the end of the conditioning time period<br>

  • A further pressure reading must be taken at the end of the test period

  • Where a long duration pressure test period (i.e. over 24 hours) is to be undertaken, the <br>Operational Manager may specify intermediate pressure readings; so, that the test may be<br>assessed and aborted at an early stage if there is an indication that the test will ultimately fail<br>

  • The Operative or Operational Manager responsible for the pressure test must completer the test <br>certificate

  • The Operative responsible for the pressure test must be in attendance at the end of the test to <br>witness de-pressurisation and this must be recorded on the test certificate

Test Failure

  • The test pressure should be reduced before carrying out an examination of the pipe work

  • All exposed connections plugs and external fittings must be re-examined for possible leakages by<br>leak detection fluid

  • Care must be taken to undertake any repairs with the appropriate tools without applying <br>excessive force

  • Where no obvious cause can be attributed to a pressure test failure and the test conditions have <br>not altered, the Operation Manager can decide to extend the test, using the final or an <br>intermediate test reading as the main starting point for the new period. However, if the mains<br>pressure has been reduced then the main must be re-pressurised to the test pressure and test<br>procedure carried out as above. In the case of pressure tests on MP PE mains, the revised creep<br>allowance must be established following calculation of the new conditioning time.

  • Where an MP PE main is to be retested following de-pressurisation, it must remain at atmospheric <br>pressure for a minimum of three hours before re-pressurisation, to allow creep from the original <br>test to relax. The creep allowance for the retest can then be obtained from the appropriate table

  • Where a test failed, further investigations using tracing techniques or sectioning of the main as <br>detailed by the Operational Manager can be carried out

De-pressurisation of main:

  • The air must be released by opening the vents on the pressure test standpipes or vent pipe<br>situated on the extremities of the main until atmospheric pressure within the main is achieved. <br>This ensures that the entire system under test has been included in the test

  • Due to the noise of the venting air, ear protection may be required<br>

  • Measures must be taken to minimise noise generated during de-pressurising and its impact of the <br>public

  • The Competent Operative must confirm, by checking the gauges installed at the extremities, that<br>the pressure within the whole of the main has been reduced to atmospheric

  • The Competent Operative responsible for the pressure test must record this information on the <br>test certificate before authorising further construction work to proceed

Test Records

  • The test certificate must be completed and passed to the Operational Manager or returned in the<br>project file on completion of the works.

Sign off

  • Name of assessor

  • Pass or refer for further training

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.