Plumbing Rough-In
-
Are all of the Water Closets installed 12.5" from the frame and 16.5" to 18.5" from side wall?
Shower Valves
-
Are the Shower Valves secured to the studs?
-
Are the Shower Valves installed perpendicular to the floor?
-
Are the Shower Valves far enough out of the wall and 6" from cc to entry?
-
Are the Shower Valves installed on the same end as the tub drain?
-
Is the rough-in for the lav's and kitchen sink's located within the cabinet locations per the details?
-
Is all of the pex secured properly to studs to prevent vibration or movement?
-
Is all of the pex pipe installed overhead and within walls protected with nail plates?
-
Are boca plates installed where pipes are susceptible to being penetrated with finishing nails?
-
Is the Condensate Drain installed 24" A.F.F. within cabinets?
-
Is the water supply to the room stubbed out far enough from the wall?
-
Is all of the Firecaulking finished?
-
Are all stub outs at least 6" out of the wall?
-
Are Shower Pans flush to the ground?
-
Are tubs at 28" A.F.F. and on center with drain valve?
-
Are the Toilet supply left of center 6" to 8" to the bottom of the box?
-
Are the Mixing Boards installed and access panels laid out?
-
Are the boxes in the corridor and adjoins walls fire rated?
-
Are shower valves 42.5" A.F.F.?
-
Are shower pans protected?
-
Is the strapping every 32" for pex?
-
Are the hot water mains installed?
Testing
-
Has the Waste and Vent System been tested?
-
Has the Domestic Water System been tested (pex and cpvc)?<br>
-
Has the Waste and Vent System been tested?
-
Has the Domestic Water System been tested (pex and cpvc)?
Post Drywall Install
Tubs
-
Are they set?
-
Is the overflow installed?
-
Have they been tested?
Drop-Ins
-
Are they set?
-
Is the overflow installed?
-