Rough-Ins
-
Are all the GRD boxes installed in the correct locations per the drawings?
-
Are all the TEF's installed per the drawing?<br>
-
Is the T-Stat wire pulled and terminated to the Heat Pump?
-
Is all of the duct installed to allow proper airflow?
-
Are the duct hangers installed every 4-6'?
-
Are the duct hangers installed to allow proper airflow?
-
Is the Dryer Exhaust box installed per the drawings?
-
Are all heat pumps installed per the contract drawings?
-