Title Page
-
Document number
-
Site conducted
-
Conducted on
-
Prepared by
-
Lot Number
-
GIS location data from device (Phone/Tablet etc)
Inspection Activity
-
Circuit number
-
Cable size (mm2)
-
Cable type
-
Circuit start point
-
Circuit end point
-
Earth cable and/or equipment name and type matches Cable Schedule
-
All underground joints have been installed as per manufacturer's instructions
-
Number of branch circuits and crimp connectione to main earth line installed
-
Test equipment model and serial number
-
Post installation continuity in Ohm's in main line from circuit start to circuit end
-
Ensure all branch line continuity is under 0.5 Ohms tested against circuit end or start
-
Ensure all Punchlist items are recorded for close out
Signoff
-
Earth cable and/or equipment is installed in accordance with AS3000 and supplied IFC drawings
-
Verified By
-
Date
-
Signature