Title Page

  • Conducted on

  • Prepared by

  • Location

TRILITY Definitions

  • TRILITY's own assessment of the site is represented by the condition scale and the criticality scale.

TRILITY Condition Assessment - Electrical and Mechanical

1 Very Good

  • Sound modern electrical and mechanical components in “as new” condition all operable and well maintained. No major investment required.

2 Good

  • As 1, but showing superficial wear and tear. Efficiency undiminished. Minor oil leaks and gland wear evident. Protective coatings still intact. Unlikely to require major overhauls or replacement within 10 years. Routine maintenance required, needs to be inspected within 5 years.

3 Moderate

  • All components functioning acceptably but showing significant wear and tear with minor failures and efficiency has diminished. Early signs of significant (rather than superficial) wear and tear, corrosion becoming apparent. No major work likely to be required within 5 years. Needs to be inspected within 5 years.

4 Poor

  • Function and/or running costs significantly affected by failures or maintenance needs, still functioning as 3 but effective life exceeded, requires major overhaul within 5 years.

5 Fail

  • Electrically unsafe, Health and Safety risk, not working or out of commission because unsafe to use, too unreliable or costly to run. Requires major overhaul or replacement within 2 years.

TRILITY Criticality Scale

  • 5 Very High

  • 4 High

  • 3 Medium to High

  • 2 Low to Medium

  • 1 Low

  • 0 Very Low

SA Water General Electrical Asset Condition Rating

  • The condition rating along with the associated estimated % of asset life remaining.

1 Very good 80% to 100%

  • Asset is in “as new” condition.
    Sound, fully functional modern electrical equipment.

2 Good 50% to 80%

  • Initial signs of deterioration.
    Sound, fully functional equipment. Minor deterioration of electrical equipment with signs of physical deterioration (e.g. minor discolouration). Deterioration has minimal impact on asset performance. Minimal short-term failure risk.
    Most overhauled assets expected to return to condition grade 2.

3 Fair / Moderate 25% to 50%

  • Satisfactory condition.
    Functional electrical equipment, with minor physical defects and some diminished efficiency. Appearance affected by deterioration. Minor components or isolated sections of the asset need replacement or repair, but asset still functions safely at adequate level of service.
    Consider operational intervention to restore condition grade and deter further deterioration.

4 Poor 10% to 25%

  • Asset is still functional but experiencing problems due to deterioration of the asset.
    Asset exhibiting significant signs of one or more of the following: physical damage, loss of insulation/potential for exposed live parts, signs of heat damage, deterioration, discolouration, physical wear and tear, corrosion and/or noise/vibration.
    Replacement or refurbishment required in short term; asset barely serviceable. Intervention to restore condition grade may still be economically viable.

5 Very Poor 0% to 10%

  • Asset has failed or failure is imminent. Asset condition is having a detrimental effect on performance.
    Asset exhibiting extreme signs of one or more of the following: physical damage, failure of insulation/exposed live parts, signs of excessive heat damage, deterioration, discolouration, wear and tear, corrosion and/or noise/vibration.
    Urgent action necessary. Asset is unserviceable, replacement required.

MBG00 Murray Bridge General Area

  • MBG00LGT001 External Lighting Startup Year: 1999 Condition: 2 Criticality: 3

  • MBG00LGT002 Internal Lighting Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG00LGT003 Emergency Lighting Start-up Year: 1999 Condition: 2 Criticality: 5

MBG31 Plant Inlet

  • MBG31AIT003 Analyser - R/W Turbidity Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG31AIT004 Analyser - Raw Water pH Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG31FIT001 Flow Meter - Raw Water Start-up Year: 1999 Condition: 3 Criticality: 4

  • MBG31FSL002 Analyser - R/ W Low Flow Swi Start-up Year: 1999 Condition: 2 Criticality: 3

MBG32 PAC Contact Tank

  • MBG32LSH001 PAC Tank 1High Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG32LSH002 PAC Tank 2 High Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG32LSL001 PAC Tank 1Low Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG32LSL002 PAC Tank 2 Low Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

MBG 41 Mixing

  • MBG41LSH002 Rapid Mix High Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG41LSL001 Rapid Mix Low Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG41VFD001 Rapix Mixer VFD 1 Start-up Year: 2014 Condition: 2 Criticality: 4

  • MBG41VFD002 Rapix Mixer VFD 2 Start-up Year: 2014 Condition: 2 Criticality: 4

MBG42 Flocculation

  • MBG42AIT001 Analyser - pH Flocc Tank Start-up Year: 1999 Condition: 1 Criticality: 3

MBG43 Sedimentation

  • MBG43AIT006 Analyser -Cla. Water Turbidity Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG43FSL005 C/Water Turb No Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG43LSL003 Clarifier 1 Low Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG43LSL004 Clarifier 2 Low Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • Sludge Sucker's VSDs 1 and 2 are planned to be replaced in 2022 due to End of Life

  • MBG43VSD001 Sludge Sucker 1 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG43VSD002 Sludge Sucker 2 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG43ZS001 Travel Proximity Sw Clarifier #1 East Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG43ZS002 Travel Proximity Sw Clarifier #1 West Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG43ZS003 Travel Proximity Sw Clarifier #2 East Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG43ZS004 Travel Proximity Sw Clarifier #2 West Start-up Year: 1999 Condition: 3 Criticality: 3

MBG44 Filtration

  • MBG44AE010 Filter Water Common Turbidity Sensor Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG44AE011 Filter 1 Turbidity Analyser Sensor Start-up Year: 2017 Condition: 2 Criticality: 4

  • MBG44AE012 Filter 2 Turbidity Analyser Sensor Start-up Year: 2017 Condition: 2 Criticality: 4

  • MBG44AE013 Filter 3 Turbidity Analyser Sensor Start-up Year: 2017 Condition: 2 Criticality: 4

  • MBG44AE014 Filter 4 Turbidity Analyser Sensor Start-up Year: 2017 Condition: 2 Criticality: 4

  • Filter Water Common Turb Transmitter was planned to be replaced in 2021 due to its End of Life.

  • MBG44AIT010 Filter Water Common Turb Transmitter Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG44AIT011 Filter 1 & 2 Turb Analyser Transmitter Start-up Year: 2017 Condition: 2 Criticality: 4

  • MBG44AIT012 Filter 3 & 4 Turb Analyser Transmitter Start-up Year: 2017 Condition: 2 Criticality: 4

  • MBG44AIT015 Analyser - Post Lime pH Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG44DPT005 Filter 1 Differential pressure Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG44DPT006 Filter 2 Differential pressure Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG44DPT007 Filter 3 Differential pressure Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG44DPT008 Filter 4 Differential pressure Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG44FIT001 Flow Meter - F/W Filters 1&2 Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG44FIT002 Flow Meter - F/W Filters 3&4 Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG44FSL009 F/Water Turb.- No Flow Swi. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG44FSL011 Filter 1 Turb No Flow Switch Start-up Year: 2017 Condition: 2 Criticality: 3

  • MBG44FSL012 Filter 2 Turb No Flow Switch Start-up Year: 2017 Condition: 2 Criticality: 3

  • MBG44FSL013 Filter 3 Turb No Flow Switch Start-up Year: 2017 Condition: 2 Criticality: 3

  • MBG44FSL014 Filter 4 Turb No Flow Switch Start-up Year: 2017 Condition: 2 Criticality: 3

  • MBG44LIT001 Filter 1 Level Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG44LIT002 Filter 2 Level Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG44LIT003 Filter 3 Level Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG44LIT004 Filter 4 Level Start-up Year: 1999 Condition: 3 Criticality: 3

MBG45 Air Scour System

  • MBG45M001 Air Scour Blower 1 Motor (55kw) Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG45M002 Air Scour Blower 2 Motor (55kw) Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG45PI001 Air Scour Blower Output press. Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG45PI002 Air Scour Blower 2 Output press. Start-up Year: 1999 Condition: 2 Criticality: 2

MBG46 UV Disinfection System

  • MBG46AE001 Channel 1- Bank A - Intensity Meter Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46AE002 Channel 1 - Bank B - Intensity Meter Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46AE003 Channel 2 - Bank A - Intensity Meter Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46AE004 Channel 2 - Bank B - Intensity Meter Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46AIT001 Channel 1 - Transmisisty Meter Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46AIT002 UV Air Pressure Transducer Start-up Year: 2005 Condition: 2 Criticality: 3

  • MBG46ES001 UV Distribution Board - Rowanco Start-up Year: 2005 Condition: 2 Criticality: 5

  • MBG46ES002 UV Distribution Board - Wedeco Start-up Year: 2005 Condition: 2 Criticality: 5

  • MBG46FE001 UV Air Flow Element Start-up Year: 2005 Condition: 2 Criticality: 3

  • MBG46LE001 Channel 1 - LSH - Ultrasonic Unit Start-up Year: 2005 Condition: 1 Criticality: 4

  • MBG46LE002 Channel 2 - LSH - Ultrasonic Unit Start-up Year: 2005 Condition: 1 Criticality: 4

  • MBG46ME001 #1 A/C Unit - Split System Start-up Year: 2005 Condition: 2 Criticality: 3

  • MBG46ME002 #2 A/C Unit - Split System Start-up Year: 2005 Condition: 2 Criticality: 3

  • MBG46MIS001 UV Lamp Wiper Reactor #1 Start-up Year: 2005 Condition: 4 Criticality: 2

  • MBG46MIS002 UV Lamp Wiper Reactor #2 Start-up Year: 2005 Condition: 4 Criticality: 2

  • MBG46MIS003 UV Lamp Wiper Reactor #3 Start-up Year: 2005 Condition: 4 Criticality: 2

  • MBG46MIS004 UV Lamp Wiper Reactor #4 Start-up Year: 2005 Condition: 4 Criticality: 2

  • MBG46MISC005 UV HIM Module Start-up Year: 2005 Condition: 2 Criticality: 3

  • MBG46PLC001 UV PLC Start-up Year: 2005 Condition: 2 Criticality: 5

  • MBG46UV001 Channel 1 - Bank A UV Unit Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46UV002 Channel 1 - Bank B UV Unit Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46UV003 Channel 2 - Bank A UV Unit Start-up Year: 2005 Condition: 2 Criticality: 4

  • MBG46UV004 Channel 2 - Bank B UV Unit Start-up Year: 2005 Condition: 2 Criticality: 4

MBG50 Chemical Dosing, Storage

  • MBG50ES001 Switchboard - Dosing Start-up Year: 1999 Condition: 3 Criticality: 5

  • MBG50LSH001 General Area Bund High Level Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG50LSH002 Truck Unloading Bund 1 Level switch Start-up Year: 2012 Condition: 3 Criticality: 3

  • MBG50LSH003 Truck Unloading Bund 2 Level switch Start-up Year: 1999 Condition: MISSING Criticality: MISSING

MBG51 Alum Dosing

  • MBG51CO001 Calibration Column Start-up Year: 1999 Condition: 2 Criticality: 3

  • Flow Meter - Alum was planned to be replaced in 2022 due to its End of Life.

  • MBG51FIT004 Flow Meter - Alum Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG51FSL005 Alum - Low Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG51LIT001 Alum Tank 1 Level Transm. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG51LIT002 Alum Tank 2 Level Transm. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG51LSH003 Alum Bund Sump High Start-up Year: 1999 Condition: 2 Criticality: 3

  • Alum Pumps 1 & 2 were planned to be replaced in 2022 due to their condition.

  • MBG51P001 Alum Pump 1 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG51P002 Alum Pump 2 Start-up Year: 1999 Condition: 3 Criticality: 3

  • Alum Pump 1 & 2 VSDs were planned to be replaced in 2022 due to End of Life.

  • MBG51VSD001 Alum Pump 1 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG51VSD002 Alum Pump 2 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

MBG52 Coagulant Aid Dosing

  • MBG52CO002 Calibration Column Volumetric Start-up Year: 2012 Condition: 2 Criticality: 3

  • MBG52CO003 Carry Water Rotameter Start-up Year: 2012 Condition: 3 Criticality: 4

  • Flow Meter - Coag Dosing was planned to be replaced in 2023 due to its End of Life.

  • MBG52FIT003 Flow Meter - Coag Dosing Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG52FSL004 Coag L/ Flow Swi-.Dosing Point Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG52FSL005 Coag L/ Flow Swi.Carry Water Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG52LIT001 Coag Storage Tank Level Trans Start-up Year: 1999 Condition: 1 Criticality: 4

  • MBG52P001 Coag Dosing Pump 1 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG52P002 Coag Dosing Pump 2 Start-up Year: 1999 Condition: 3 Criticality: 3

  • Coag Dosing Pump 1 & 2 VSDs were planned to be replaced in 2022 due to its End of Life.

  • MBG52VSD001 Coag Dosing Pump 1 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG52VSD002 Coag Dosing Pump 2 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

MBG53 Fluoride Dosing

  • MBG53CO001 Fluoride Calibration column Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG53FIT007 Flow Meter - Fluoride Start-up Year: 1999 Condition: 3 Criticality: 3

  • Flu. Trans Pump Low Flow was planned to be replaced in 2023 due to its End of Life.

  • MBG53FSL003 Flu. Trans Pump Low Flow Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG53FSL008 Flu. Dosing Point Low Flow Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG53LIT001 Fluoride Storage Tank Level Start-up Year: 1999 Condition: 1 Criticality: 4

  • Fluoride Day Tank Level was planned to be replaced in 2021 due to its End of Life

  • MBG53LIT004 Fluoride Day Tank Level Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG53LSH009 Fluoride Bund - High Level Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG53LSH010 Fluoride Tank Bund - H/ Level Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG53P001 Fluoride transfer pump Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG53P003 Fluoride Dosing Pump 1 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG53P004 Fluoride Dosing Pump 2 Start-up Year: 2000 Condition: 3 Criticality: 3

MBG54 Lime Dosing

  • MBG54FSL007 Mix Tank 1 Low Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG54FSL008 Mix Tank 2 Low Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG54FSL014 Pre Lime Pump 1 L/ Flow Swi. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG54FSL015 Pre Lime Pump 2 L/Flow Swi. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG54FSL016 Post Lime Pump 1 L/Flow Swi. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG54FSL017 Post Lime Pump 2 L/Flow Swi. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG54JB001 Lime switchboard Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG54LE005 Mixing Tank 1 Level sensor Start-up Year: 2019 Condition: 1 Criticality: 3

  • MBG54LE006 Mixing Tank 2 Level sensor Start-up Year: 2019 Condition: 1 Criticality: 3

  • MBG54LIT005 Lime Mixing Tank 1 trans. Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG54LIT006 Lime Mixing Tank 2 trans. Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG54LSH018 Lime Sump High Level Start-up Year: 1999 Condition: 5 Criticality: 3

  • MBG54P001 Pre Lime Dosing Pump 1 Start-up Year: 2020 Condition: 1 Criticality: 3

  • MBG54P002 Pre Lime Dosing Pump 2 Start-up Year: 2020 Condition: 1 Criticality: 3

  • MBG54P003 Post Lime Dosing Pump 1 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG54P004 Post Lime Dosing Pump 2 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG54PSH009 Pre Lime Pump 1 Press Switch Start-up Year: 1999 Condition: 3 Criticality: 4

  • MBG54PSH010 Pre Lime Pump 2 Press Switch Start-up Year: 1999 Condition: 3 Criticality: 4

  • MBG54PSH011 Post Lime Pump 1 Press Switch Start-up Year: 1999 Condition: 3 Criticality: 4

  • MBG54PSH012 Post Lime Pump 2 Press Switch Start-up Year: 1999 Condition: 3 Criticality: 4

  • Pre Lime Pump 1 & 2 VSDs were planned to be replaced by 2022 due to its condition and End of Life, respectively.

  • MBG54VSD001 Pre Lime Pump 1 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • MBG54VSD002 Pre Lime Pump 2 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • Post Lime Pump 1 & 2 VSDs were planned to be replaced by 2022 due to its condition and End of Life, respectively.

  • MBG54VSD003 Post Lime Pump 1 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • MBG54VSD004 Post Lime Pump 2 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • Lime Screw Feeder 1 & 2 VSDs were planned to be replaced by 2022 due to its condition and End of Life, respectively.

  • MBG54VSD005 Lime Screw Feeder 1 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • MBG54VSD006 Lime Screw Feeder 2 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

MBG56 Caustic Dosing

  • MBG56COL001 Volumetric Column Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG56FSL003 Caustic Dosing L/ Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG56FSL004 Caustic Dose Point L/ Flow Swi Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG56LIT001 Caustic Storage Tank Level Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG56LSH002 Caustic Sump High Level Switch Start-up Year: 1999 Condition: 5 Criticality: 4

  • Caustic Pump 1 & Pump 2 were planned to be replaced by 2022 due to their End of Life.

  • MBG56P001 Caustic Pump 1 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG56P002 Caustic Pump 2 Start-up Year: 1999 Condition: 2 Criticality: 3

  • Caustic Pump 1 VSD & Pump 2 VSD were planned to be replaced by 2022 due to its condition and End of Life, respectively.

  • MBG56VSD001 Caustic Pump 1 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • MBG56VSD002 Caustic Pump 2 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

MBG57 Flocculation Aid

  • MBG57C001 Carry Water Flow Rotameter Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57C002 Volumetric Column Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57C003 Batching Water Rotameter Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57C004 Dosing point calibration column 2 Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57C005 Dosing point calibration column 1 Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57FIT007 Flow Meter - Flocculation Aid Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57FSL003 Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57FSL007 Floc Aid L/F Sw-Dose point Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57FSL008 Floc Aid L/F Swi - Carry water Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG57LE004 Level Indicator Stock tank Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG57LE005 Ageing tank level probe Start-up Year: 1999 Condition: 3 Criticality: 3

  • Floc Aid Dose Pump 1 & Pump 2 were planned to be replaced in 2022 due their End of Life.

  • MBG57P001 Floc Aid Dose Pump 1 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG57P002 Floc Aid Dose Pump 2 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG57SWB001 Flocc Aid Switch Board Start-up Year: 1999 Condition: 2 Criticality: 5

  • Floc Aid Dose Pump 1 VSD & Pump 2 VSD were planned to be replaced in 2022 due to its Condition and End of Life, respectively.

  • MBG57VSD001 Floc Aid Dose Pump 1 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG57VSD002 Floc Aid Dose Pump 2 VSD Start-up Year: 1999 Condition: 3 Criticality: 3

  • Variable Speed Drive Volumetric Feeder was planned to be replaced in 2022 due to its End of Life.

  • MBG57VSD003 Variable Speed Drive Volumetric Feeder Start-up Year: 1999 Condition: 3 Criticality: 4

MBG58 Chlorine Dosing

  • Chlorine Gas Leak Detector was planned to be replaced in 2022 due to its condition.

  • MBG58AIT001 Chlorine Gas Leak Detector Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG58DIS001 Chlorine Distribution Board #2 Start-up Year: 1999 Condition: 2 Criticality: 5

  • Chlorine Dose F/ Switch for Trim and for F/W outlet was planned to be replaced in 2024 due to its condition.

  • MBG58FSL007 Chlorine Dose F/ Switch -Trim Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG58FSL008 Chlorine Dose F/Sw -F/W Outlet Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG58ME001 Chlorine Change-Over Control Panel Start-up Year: 1999 Condition: 2 Criticality: 5

  • Signal Conditioning Unit #1, #2, and #3 were planned to be replaced in 2023 due to its End of Life.

  • MBG58MIS002 Signal Conditioning Unit #1 Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG58MIS003 Signal Conditioning Unit #2 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG58MIS004 Signal Conditioning Unit #3 Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG58MIS007 Chlorine Shutdown - ratchet arms Start-up Year: 2015 Condition: 2 Criticality: 4

  • Booster Pump 1, 2, and 3 were planned to be replaced in 2021 due to its End of Life.

  • MBG58P001 Booster Pump 1 Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG58P002 Booster Pump 2 Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG58P003 Booster Pump 3 Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG58P004 F/W Chlorine Buffer Pump Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG58P005 T/W Chlorine Buffer Pump Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG58PI005 Under Pressure Alarm Gauge #1 Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG58PI006 Under Pressure Alarm Gauge #2 Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG58SWB001 Chlorine Switch Board Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG58ZF33 Chlorine Low Flow Switch #1 Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG58ZF34 Chlorine Low Flow Switch #2 Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG58ZF35 Chlorine Low Flow Switch #3 Start-up Year: 1999 Condition: 2 Criticality: 3

MBG59 PAC Dosing

  • MBG59C001 Balancing Tank Filling Rotameter Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG59C002 PAC pump 2 carry water rotameter Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG59C003 PAC pump 1 carry water rotameter Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG59FSL015 Pump #2 Carry Water Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG59FSL016 Pump #1 Carry Water Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG59LIT010 PAC Mix Tank 1 Level trans. Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG59LIT011 PAC Mix Tank 2 Level trans. Start-up Year: 1999 Condition: 1 Criticality: 3

  • MBG59LSH003 PAC Bulk Silo High Level Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG59LSH020 PAC Bund High Level Start-up Year: 1999 Condition: 5 Criticality: 4

  • MBG59P001 PAC Dosing Pump 1 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG59P002 PAC Dosing Pump 2 Start-up Year: 1999 Condition: 3 Criticality: 3

  • MBG59PSH017 PAC Dosing Pump 1 High press. Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG59PSH018 PAC Dosing Pump 2 High press. Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG59TSH004 PAC Silo High Tempruture Swi. Start-up Year: 1999 Condition: 2 Criticality: 3

  • PAC Dosing Pump 1 VSD & Pump 2 VSD were planned to be replaced due to its condition and End of Life, respectively.

  • MBG59VSD003 PAC Dosing Pump 1 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • MBG59VSD004 PAC Dosing Pump 2 VSD Start-up Year: 1999 Condition: 4 Criticality: 3

  • MBG59ZS001 PAC Hopper Door Open Start-up Year: 1999 Condition: 2 Criticality: 3

MBG62 Backwashing

  • MBG62FIT001 Flow Meter - Backwash Start-up Year: 1999 Condition: 2 Criticality: 4

MBG63 Treated Water Pumping

  • MBG63ACU001 T/W Switch Room Air conditioner Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG63AIT004 Analyser - F/W Fluoride Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG63AIT005 Analyser - F/Water Chlorine Start-up Year: 1999 Condition: 2 Criticality: 3

  • Analyser - F/W pH was planned to be replaced in 2021 due to its End of Life.

  • MBG63AIT006 Analyser - F/W pH Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG63AIT013 Analyser - T/W Turbidity Start-up Year: 1999 Condition: 1 Criticality: 4

  • MBG63AIT014 Analyser - T/W Fluoride Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG63AIT015 Analyser - T/Water Chlorine Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG63AIT016 Analyser - T/W pH Start-up Year: 1999 Condition: 1 Criticality: 4

  • MBG63ES001 Switchboard - Treated Water Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG63FIT010 Flow Meter - Treated Water Start-up Year: 1999 Condition: 1 Criticality: 4

  • MBG63FS001 T/W Pump 1 No Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG63FS002 T/W Pump 2 No Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG63FS003 T/W Pump 3 No Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG63FSL002 F/ Water Sample Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG63FSL017 T/ Water Sample Flow Switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG63M001 T/W Pump 1 Motor (355KW) Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG63M002 T/W Pump 2 Motor (375KW) Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG63M003 T/W Pump 3 Motor (355KW) Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG63MCC001 T/W Pump 1 Switch Gear Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG63MCC002 T/W Pump 2 Switch Gear Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG63MCC003 T/W Pump 3 Switch Gear Start-up Year: 1999 Condition: 2 Criticality: 2

MBG64 Service Water System

  • MBG64FIT001 Flow Meter - Service Water Start-up Year: 1999 Condition: 2 Criticality: 4

MBG71 Control Building

  • MBG71ACU001 Switch Room Airconditioner Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG71ACU002 Lab Airconditioner Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG71AD001 Auto Dialler - Alarm Start-up Year: 2006 Condition: 2 Criticality: 4

  • MBG71AREALIGHT Area Lighting Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG71CCY001 Process Computor Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG71CCY002 Process Controllers Laptop Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG71CCY005 IT Network Router Start-up Year: 2015 Condition: 2 Criticality: 4

  • MBG71CCY006 IT Network Switch Start-up Year: 2015 Condition: 2 Criticality: 4

  • MBG71CCY007 SCADA Historian Server Start-up Year: 2013 Condition: 2 Criticality: 3

  • MBG71CIB001 Process Computor Monitor Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG71CR001 Process Comp. Colour Printer Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG71CU001 PLC-Main Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG71CU002 PLC-Backup Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG71CU004 SCADAphone dialler and EDAC Backup diall Start-up Year: 2010 Condition: 2 Criticality: 5

  • MBG71DIS001 Control Building Distribution Board Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG71DIS002 Laboratory Distribution Board Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG71ES001 Switchboard -Main Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG71ES002 Switchboard -Essential Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG71ES004 UPS Switch Board Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG71EXTLD001 Extension Leads Start-up Year: 1999 Condition: 2 Criticality: 2

  • MBG71FIRALM001 Fire Alarm System - Panel Start-up Year: 1999 Condition: 1 Criticality: 5

  • MBG71FIRALM002 Fire Alarm System - Site Smoke Detectors Start-up Year: 1999 Condition: 1 Criticality: 5

  • MBG71GEN001 Standby Generator Start-up Year: 1999 Condition: 2 Criticality: 4

  • Treated Water Autosampler was planned to be replaced in 2021 due to its End of Life.

  • MBG71MIS001 Treated Water Autosampler Start-up Year: 1999 Condition: 2 Criticality: 4

  • Scada Historian was planned to be replaced in 2021 due to its End of Life. Why was it missing from the Asset Register?

  • MBG71PC001 SCADA Historian (Not in original asset list) Start-up Year: MISSING Condition: MISSING Criticality: MISSING

  • MBG71PC002 SCADA Server MBGS1 Start-up Year: 2016 Condition: 2 Criticality: 4

  • MBG71SECLM001 Security Alarm Panel Start-up Year: 1999 Condition: 1 Criticality: 4

  • MBG71SWB001 PLC Switch Board Start-up Year: 1999 Condition: 2 Criticality: 5

  • MBG71UPS001 UPS Start-up Year: 1999 Condition: 3 Criticality: 4

MBG72 Chlorine Building

  • MBG72ES001 Switchboard - Chlorine Start-up Year: 1999 Condition: 2 Criticality: 5

MBG80 Treated Water Storage

  • Treated Water Stor. Tank Level was planned to be replaced in 2023 due to its End of Life.

  • MBG80LIT001 Treated Water Stor. Tank Level Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG80LSH008 T/W Storage Tank Level High Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG80LSH009 T/W Storage Tank Level Low Start-up Year: 1999 Condition: 2 Criticality: 3

MBG91 Supernatant Pumping

  • MBG91FIT005 Flow Meter - Supernatant Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG91LIT003 Supernatant Sump Level Trans. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG91LSLL004 Supernatant Sump Low/Low Start-up Year: 1999 Condition: 2 Criticality: 3

  • Supernatant Pump 1 VSD & Pump 2 VSD were planned to be replaced in 2022 due to its condition and End of Life, respectively.

  • MBG91VSD001 Supernatant Pump 1 VSD Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG91VSD002 Supernatant Pump 2 VSD Start-up Year: 1999 Condition: 2 Criticality: 3

MBG94 Dirty Water Pumping

  • MBG94JB001 Dirty Water Junction Box Start-up Year: 1999 Condition: 2 Criticality: 4

  • MBG94LIT003 Dirty Water Pit Level trans. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG94LSHH005 Dirty Water Pit High/High Lev. Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG94LSLL004 Dirty Water Pit Low/Low Level Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG94ZS001 Dirty Water Pump 1 No Flow switch Start-up Year: 1999 Condition: 2 Criticality: 3

  • MBG94ZS002 Dirty Water Pump 2 No Flow switch Start-up Year: 1999 Condition: 2 Criticality: 3

MBG95 Sludge Lagoons

  • MBG95MISC007 Lagoon Dewatering Power supply Start-up Year: 1999 Condition: 2 Criticality: 2

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.