Photo required.
Safety devices.
-
Check electrical interlock switches are securely attached and alligned
-
Check interlock Guards function correctly
-
Check the gate catches lock out the gate
-
Check fitting security,operation and adjustment,including the safety features ,guards and indication light by the safety switch
-
Is the emergency stop facility effective
-
Power up and and check the operational controls .Operate each function and reset
Mechanical.
-
Check machine anchor bolts.
-
Check for oil leaks / repair as required.
-
Check for oil levels, top up as required.
-
Check for damage to beam and tooling clamps.
-
Check shadow line.
-
Check couplings for wear / Damage.
-
Check condition of tooling.
Control panel and electrics.
-
Check control panel for damage.
-
Isolate power
-
Check condition of cables to all drive motors.
-
Check condition of limit switches
Final operation check.
-
is the area well illuminated
-
Check all operations.<br><br><br>