Information
-
Location:
-
Activity
- Operation
- Construction
- Rig Work
- Other
-
CHK Rep/Office:
-
Contractor:
-
Auditor:
-
Date/Time:
HAZCOM [EHS-101]
-
MSDS's available and accessible at all times
-
All liquid containers labeled with NFPA or HMIS labels
PPE [EHS-102]
-
FRC utilized
-
Hard hat(s) utilized
-
Appropriate eye protection being utilized
-
Safety toe boots being worn
-
Personal Gas Monitor used
-
Other required PPE items being utilized
Hearing Protection [EHS-104]
-
Proper signage present at high noise areas
-
Proper hearing protection worn by workers
Lockout/Tagout (LOTO) [EHS-105]
-
LOTO required
-
LOTO permit available on-site<br>{105-B}
-
LOTO permit properly managed
-
Locks/Tags properly managed
Hot Work Management [EHS-106]
-
Hot Work required
-
Hot Work permit available on-site<br>{106-A}
-
Hot Work Qualified Individual on-site
-
Hot Work permit properly managed
-
Gas monitors properly used and managed
-
Fire extinguishers available/maintained
Confined Space [EHS-107]
-
Are confined spaces properly posted
-
Confined Space Policy being followed (No confined space entry)
Trenching and Excavation [EHS-108]
-
Trenching and Excavation Checklist required (depth > or = 48")
-
Checklist available on-site<br>{108-A}
-
Checklist properly managed
-
Gas monitors properly used and managed
-
Engineering Best Practices being utilized (sloping/benching/egress)
-
One call being utilized
H2S [EHS-110]
-
Site has an H2S concern (concentration in well stream > or = 10 ppm)
-
Site is properly posted (signs at > or = 10 ppm/windsock at > or = 100 ppm)
-
Workers are wearing monitors that are properly maintained
Chemical, Flammable and Combustible Liquids/Materials [EHS-111]
-
All chemical containers are in good condition
-
All chemicals are properly stored and in secondary containment if required
-
All chemical containers are closed/sealed when not in use
-
All containers are bonded/grounded in liquid transfer
Heat and Cold Stress [EHS-112]
-
All workers taking proper precautions for heat/cold
-
PJSAs state hazards of heat/cold stress and how to mitigate
-
Controls/supplies in place to prevent heat/cold stress
Fire Protection [EHS-113]
-
Fire extinguisher available in company trailer
-
Monthly inspection tag on each fire extinguisher
-
Annual Fire Extinguisher Maintenance Record available
Electrical Safety [EHS-114]
-
Electrical equipment operating at a voltage of greater than 600V labeled as high voltage
-
Work clearance of at least 36 inches maintained in front of electrical equipment
-
Fixed equipment grounded properly
-
Only 3-wired and GFSI extension cords and electrical power cords being used
-
All extension cords and electrical power cords are in good working condition
-
No flexible cord or wire going through windows or doorways
Powered Industrial Trucks (Forklifts) [EHS-115]
-
Forklift operators certified and certificate available
-
Seat belts provided (as per manufacturer)
-
Backup alarm working
-
Auxiliary lighting for use during nighttime operations
-
Horn working
-
Rated lifting capacity posted on the forklift
-
Pre-Use Inspection Checklist available
Hoisting and Lifting Equipment [EHS-116]
-
Workers operating hoisting and lifting equipment properly trained
-
Monthly Hoisting Machinery Inspection Record (Overhead) available
-
Straps and slings have been inspected and are in proper working condition
ATV/UTV [EHS-117]
-
Proper PPE available of being utilized
-
Equipment in good repair
Lifting and Carrying Safety [EHS-118]
-
Proper lifting and carrying techniques being used (i.e., bending at knees, back straight, object close to body, etc.)
Walking-Working Surfaces Policy [EHS-119]
-
Any working surface above 4 feet from the ground must be protected by a work platform with guardrails and toe boards or personal fall arrest system
-
Guardrails must be at least 42 inches above the platform and have intermediate mid- rail and toe board
-
Fall arrest system must have a full body harness, deceleration device and a lifeline.
-
Anchorage used for fall arrest equipment must be capable of supporting at least 5,000 lbs.
-
All walking/working surfaces are clear of debris and tripping hazards and/or tripping hazards have been identified
Ladder Safety [EHS-120]
-
No wooden ladders allowed on site
-
Metal ladders must have a warning label for electrical caution
-
Ends/feet of ladder must be fitted with insulated non-slip material
-
Extension ladders must extend 3 feet past the landing if used to access another working surface and be secured
-
While on a ladder, workers are using 3-point contact procedure
-
Fixed ladders are to be inspected annually and fill out a Fixed Ladder Annual Inspection Checklist
-
Portable ladders are to be inspected monthly and fill out a Portable Ladder Monthly Inspection Checklist
Bloodborne Pathogen Exposure Control [EHS-121]
-
First Aid Kit/Bloodborne Pathogen Kit available on site
-
Bloodborne Pathogens Exposure training complete
Pre-Job Safety Assessment [EHS-122]
-
Pre PJSA safety tour on site conducted
-
Daily safety meeting being conducted
-
Special safety meetings conducted when H2S/SO2 present
-
Safety meetings properly documented
-
Accidents, if any, are discussed during safety meetings
-
PJSA filled out completely and properly
-
Individual contractors conducting Job Safety Analysis (JSA) to identify task-specific hazards
Ground Disturbance Safety [EHS-124]
-
One call is being utilized before any ground disturbance
Waste Management [EHS-202]
-
All vendors are managing their waste appropriately
-
Wastes are segregated in the proper containers
NORM Management [EHS-204]
-
NORM surveys being conducted on a regular basis
General
-
OSHA poster posted (posted at CHK field office)
-
OSHA Log available on location. (Maintained at CHK Corp offices)
-
Injuries and incidents reported and documented immediately
-
STOP program, or equivalent, in use
-
Adequate communication w/other contractors on site
-
Emergency response plan
-
BOP training provided
-
Written safety program
-
All incidents resulting in injuries to employees investigated and documented to prevent recurrence
Housekeeping
-
Walking/Working surfaces clean and clear of debris
-
Equipment on location is neat
-
No trash on the ground
-
Tripping hazards have been identified and addressed
-
Seasonal conditions have been identified and addressed
Production Operations
-
Tank batteries properly labeled in at least two positions per tank
-
H2S monitoring devices available and in use
-
Only H2S qualified personnel permitted
-
Pumper tools are neat and in good working condition
-
First Aid Kit available and stocked ink Pumper's truck
Extras
-
Comments