Title Page
-
Document No.
-
Conducted on
-
Prepared by
-
Location
Audit Checklist
-
Tick any NON-COMPLIANT or INCOMPLETE items
-
Mains at DB.
-
power circuits at DB.
-
light circuit at DB.
-
AC circuits at DB
-
All circuits taped and labelled at DB.
-
All wall point set outs checked to architecturals and electrical plans.
-
All actives and switch wires at switches and taped.
-
All light points roughed in.
-
Fans roughed in with sdi where required.
-
Smokies roughed in
-
All gpos roughed in.
-
AC circuits brought out at isolater location
-
Continuous earth to frame where wall points are located.
-
Light points marked on floor or plan where required.
-
Fan, smokies and balcony lights nogged where required.
-
X1 coax to each tv point, with its own cat5.
-
data to each phone or data point.
-
Segregation from data and plumbing pipes maintained.
-
Nbn extended down to final location.
-
Datas brought out with nbn.
-
All other unit mains extended through riser.
-
All fire rating complete and registered.
-
Cables kept up to concrete where acoustic rating will be present.
-
Cables bushed where necessary.