Title Page

  • Document No.

  • Conducted on

  • Prepared by

  • Location

Audit Checklist

  • Tick any NON-COMPLIANT or INCOMPLETE items

  • Mains at DB.

  • power circuits at DB.

  • light circuit at DB.

  • AC circuits at DB

  • All circuits taped and labelled at DB.

  • All wall point set outs checked to architecturals and electrical plans.

  • All actives and switch wires at switches and taped.

  • All light points roughed in.

  • Fans roughed in with sdi where required.

  • Smokies roughed in

  • All gpos roughed in.

  • AC circuits brought out at isolater location

  • Continuous earth to frame where wall points are located.

  • Light points marked on floor or plan where required.

  • Fan, smokies and balcony lights nogged where required.

  • X1 coax to each tv point, with its own cat5.

  • data to each phone or data point.

  • Segregation from data and plumbing pipes maintained.

  • Nbn extended down to final location.

  • Datas brought out with nbn.

  • All other unit mains extended through riser.

  • All fire rating complete and registered.

  • Cables kept up to concrete where acoustic rating will be present.

  • Cables bushed where necessary.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.