SST010
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Information Required
-
SST010 - Electrical Systems Permit to Work (V1)
-
Section A
-
Authority is hereby granted for to carry out the following works
-
Reference:
-
As the electrical system is DEAD/ISOLATED* from all live conductors and is connected to EARTH, works may be carried out from :
-
Date/Time:
-
Until
-
Date/Time
-
The Apparatus is effectively connected to earth at the following point(s)
-
Section B
-
Caution notices are posted at:
-
Safety locks have been fitted at:
-
Safety keys are held by:
-
The following special precautions must be followed during the works.
-
Attach drawing as appropriate to this, identity the area / location of the works.
-
Section C
-
Authorised by:
-
Received by:
-
Works covered by this permit have been suspended/completed*and all tools, equipment & operatives have been removed.
-
The electrical system is / is not* safe to make live
-
Returned. (date and time)
-
Return Confirmed (Site Manager)