HVAC - Pre-Install
-
WAIT ROOM TSTAT
-
What type of Thermostat is in the waiting room?
-
What has the stage settings been programmed to?
-
Second Stage Only
-
Please take photo of wait room tstat wiring.
-
SHOWROOM TSTAT
-
What type of Thermostat is in the Show room?
-
What has the stage settings been programmed to?
-
Second Stage Only
-
Please take photo of show room tstat wiring.
-
Are there any HVAC problems prior to starting work?
-
If YES above. Has facilities been notified?
-
Any special notes or problems with HVAC system?
Compressors Pre-Install
-
COMPRESSOR 1
-
Is there any physical damage to compressor 1? If yes please attach photo and describe.
-
If YES above. Has facilities been contacted about the problem?
-
Does compressor 1 cycle when pressure is released?
-
COMPRESSOR 2
-
Is there any physical damage to compressor 2? If yes please attach photo and describe.
-
If YES above. Has facilities been contacted about the problem?
-
Does compressor 2 cycle when pressure is released?
Lighting Information
-
Does the store have new lights?
-
If "no" above please complete addition lighting survey form.
HVAC Post Installation
-
WAIT ROOM TSTAT
-
What model thermostat is installed?
-
Has wait room thermostats been programmed to reflect the system type listed above? Please Select program type.
-
What has the stage settings been programmed to?
-
Has the scheduler been set to off in system programming and have you adjusted status display settings?
-
Has EEC control been set to 0?
-
Second Stage Only
-
SHOWROOM TSTAT
-
What model thermostat is installed?
-
Has showroom thermostats been programmed to reflect the system type listed above? Please Select program type.
-
What has the stage settings been programmed to?
-
Has the scheduler been set to off in system programming and have you adjusted status display settings?
-
Has EEC control been set to 0?
-
Second Stage Only
-
Any special notes or problems with HVAC system?
Control Panel
-
Is the control panel securely mounted and grounded?
-
Please provide a photo of panel installation.
-
Is the data connections complete and active?
-
Does the store have MPLS installed?
-
If YES above. Has the data been connected to port 43 of the network switch and labeled EMS?
-
Please provide a photo of data connection.
Compressor Post Installation
-
Has compressor 1 been tested and operating correctly?
-
Please provide a photo of the electrical connections for compressor 1.
-
Has compressor 2 been tested and operating correctly?
-
Please provide a photo of the electrical connections for compressor 2.
Relay Configuration
-
Is the Showroom relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Is the Service Area 1 relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Is the Service Area 2 relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Is the Exterior relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Is the Storage 1 relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Is the Storage 2 relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Is the EH Fan relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Is the EH Fan 2 relay installed and tested? If yes please indicate circuit and panel numbers and if connected to a contactor.
-
Please list any additional relays installed and indicate panel numbers and if connected to a contactor. Please list any special notes about the relays or electrical panels.
-
Please provide multiple photos of installed relays and electrical panels.
System Testing and Operation Review
-
Has the date and time been set on the panel?
-
Has the open flag been set correctly?
-
Have all the opening & closing times and set points been programmed?
-
Have you trained the manager on normal override with red button to be used during or after hours if a relay does not turn on including compressors or late nights?
-
Have you trained the manager on manual override and showed them where the documentation is listed in the event the red button does not turn on a device.
-
Have you explained to the manager not to use the disconnects for shutting down compressors anymore?
-
Have you left the manager with our FAQ sheet and contact information?
Sign Off
-
Managers Signature
-
Tech signature