Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Inverter number
-
Inverter number
Ducting
-
Installed
-
Secure
-
Sharp edges removed
-
Duct sealed
Inverter
-
Location correct
-
Numbering as per drawing
-
Labelling correct
-
Mounting secure
-
Termination box closed and sealed
String cables
-
Permanent labels fitted
-
Cables dressed and secured
-
LV Cable
-
Clamps secure
-
Permanent labels fitted
-
Cable correct length
-
Sheer bolts removed at lug
-
Heatshrink fitted
-
Correct phasing
-
M12 Lug bolts torqued to 25-30Nm
Spoil backfilling
-
Spoil level with adjacent ground
-
Confirm no overspill to roadway
-
No soft spots
-
No lying water
EXTERNAL EARTH BONDING
-
Clamp secure
-
Weld acceptable
-
Crimp secure
-
M10 Lug bolt torqued to 15Nm
PV TABLE
-
Number label fitted
-
Cable ties trimmed, no sharp edges
-
No sharp edges or swarf on steelwork
-
Edge protection installed and secure
-
Edge protection installed and secure