Title Page
-
Site inspected
-
Inspected on
-
Inspected by
-
Location
Control section
-
Controlled by
-
Signature
Approve section
-
Approved by
-
Signature
Checklist
-
Trenches checked for location, elevation and dimensions
-
Cable size, type, spacing and bend radius in accordance with drawings
-
Stub-up dimensions and cable protection pipes installed in accordance with drawings
-
Perform insulation resistance test on cable prior to backfilling trench
-
Pipe size, elevation and bend radius in accordance with drawings
-
Verify if cable is free of visual damage
-
Trench backfilled with fine sand to depth of 200mm above largest cable
-
depth
-
Warning Tape installed
-
Trench backfilled to correct elevation and required compaction performed