Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Job Number
-
Job Name
-
Report Prepared By:
-
Select date
-
Floor:
-
Area:
-
Room/Corridor
Sump Pumps
-
Sump Pits are clean and free of debris prior to setting?
-
Picture of sump pit prior to installation
-
Is entry to the pit required to install pumps?
-
Has a work plan been developed?
-
Has the safety department been notified of the confined space entry?
-
Guide rails are installed and material is per submittal?
-
Floats are installed at correct elevation and per detail?
-
Coordination with electrician is complete, float and power cables are of sufficient length?
-
Picture of power and float cables
-
All O&M manuals that came with the pumps have been given to the PM to compile the turn over package?
-
Manufacturers Rep has been onsite to assist with start up of pumps?
-
Name of Manufacturers Representative:
-
Date or Dates Rep was on site:
-
Electrical/Control panel location has been coordinated and complies with electrical clearances required?
-
Photo of Installed Panel
-
Pit Lid matches frame and gasket and all bolts are installed?
-
Picture of installed pit lid
Water Softener
-
Anchorage complies with details?
-
All Clearances required for maintenance or service have been addressed and adhered to?
-
Photo of clear service area
-
Flex connectors installed on connection to softener if required?
-
Softening media installed if required?
-
Manufacturers Rep has confirmed installation is correct and assisted in start up?
-
Name of Manufacturers Rep
-
Date or Dates Manufacturers Rep was on site
-
Drains off equipment are run to floor sink and drain properly?
-
Water softener installed on housekeeping pad if required?
-
Photos of completed installation
Expansion Tank
-
Anchorage complies with approved details
-
Piping is installed to tank with union and valves as required?
-
Piping is connected to cold water system per detail?
-
Pre Charge Pressure of the tank has been confirmed?
-
All O&M Manuals that came with the tank have been given to the PM for the turn over package?
-
Tank is on housekeeping pad if required?
-
Picture of completed installation
Domestic Water Heaters
-
Piping to heaters complies with approved detail?
-
All valves, gauges, reliefs thermometers are installed per detail?
-
All Clearances for maintenance have been adhered to?
-
Coordination with Electrical, Control, and Mechanical (steam) has been completed and clearances met?
-
Anchorage of heaters is per approved detail?
-
Housekeeping pad is installed if required?
-
Flex connectors installed at equipment if required?
-
Relief valves are run to floor sink?
-
Manufacturers Rep has approved the installation and has assisted in start up?
-
Name of Manufacturers Rep:
-
Date or Dates Manufacturers Rep was on site
-
Start up Documentation and compliance is complete and given to the PM?
-
Insulation of equipment is complete if required?
-
Picture of the completed installation
Circulating Pumps
-
Circulating pumps installed per contract details?
-
Pumps are properly supported?
-
Picture of pump support
-
Flex connectors installed if required?
-
Aqua stat, timer and control panel installed?
-
Timer and control panel are accessible and required clearances met?
-
All O&M paperwork with with pumps has been given to the PM for the turn over package?
-
Oil for bearings and seals has been installed if sent with pumps?
-
Picture of completed installation
Thermostatic Mixing Valve
-
Mixing Valve has been installed per the manufacturers instructions?
-
Mixing Valve is supported properly?
-
Picture of mixing valve support
-
Mixing Valve is accessible?
-
O&M Manual has been given to the PM for the turnover package?
-
Picture of completed installation
Notes, Impacts, or Comments
-
Notes, Impacts or Comments
-
Signature of report preparer: