  • Project: Escala

  • Sub-contractor: SKRA

  • Package: Aluminium Windows

  • Apartment No / Tenancy No / Area/ Grid reference: FT03 Façade South-East-Corner

  • Date:

Sub- Escala FT03 Bracket Treatment Contractor

  • 1. Confirm bracket number

  • 2. Enable someone to record the DFT of bracket paint

  • Paint thickness readings
    > 300 Mic= Procedure A
    Between 250 & 300 Mic = Procedure B
    < 250 Microns = Procedure C
    Visual Evidence protective coating is abraded
    Procedure D or Procedure E

  • Paint thickness (4 locations of each bracket) (if bracket is being retained)

  • 1.

  • 2.

  • 3.

  • 4.

  • Is the protective coating abraded (if the bracket is being retained)?

  • Which protective coating procedure is required (A,B,C,D or E)?

  • Required protective coating procedure completed (refer to relevant procedures ITP)?

  • Detail type? (1-12) List required treatment actions below, with respective completion sign-off (TBC upon MAB / Arup sign-off)

  • Photos record attached?

  • I have carried out all necessary inspections and verify that the above items/activities conform to the contract specification/documents

  • Subcontractor Rep Name: (Print)

  • (Signed)

  • Date:

  • Verified by LUSB: (Print)

  • (Signed)

  • Date:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.