Project: Escala
-
Sub-contractor: SKRA
-
Package: Aluminium Windows
-
Apartment No / Tenancy No / Area/ Grid reference: FT03 Façade South-East-Corner
-
Date:
Sub- Escala FT03 Bracket Treatment Contractor
-
1. Confirm bracket number
-
2. Enable someone to record the DFT of bracket paint
-
Paint thickness readings
> 300 Mic= Procedure A
Between 250 & 300 Mic = Procedure B
< 250 Microns = Procedure C
Visual Evidence protective coating is abraded
Procedure D or Procedure E -
Paint thickness (4 locations of each bracket) (if bracket is being retained)
-
1.
-
2.
-
3.
-
4.
-
Is the protective coating abraded (if the bracket is being retained)?
-
Which protective coating procedure is required (A,B,C,D or E)?
-
Required protective coating procedure completed (refer to relevant procedures ITP)?
-
Detail type? (1-12) List required treatment actions below, with respective completion sign-off (TBC upon MAB / Arup sign-off)
-
Photos record attached?
-
I have carried out all necessary inspections and verify that the above items/activities conform to the contract specification/documents
-
Subcontractor Rep Name: (Print)
-
(Signed)
-
Date:
-
Verified by LUSB: (Print)
-
(Signed)
-
Date: