Quality Assurance<br>Report

  • Address

  • External auditor

  • Auditors number/reference/type

  • BK reference number

  • Site

  • Property location
  • Customer name

  • Date of audit

  • QA auditor

  • Contractor
  • Installers name

  • Measure name/type

  • Work/handover date

Quality Assurance<br>Report

Loft

  • Loft - No insulation on loft hatch

  • Loft - No Photographic evidence

  • Loft - Electric Cable is covered by installation

  • Loft - No draught proofing installed

  • Loft - Ventilation not sufficient

  • Loft - Loft Insulation does not meet minimum building regulations

  • Loft - Downlights are not covered in the loft space

  • Loft - Documents

Solar

  • Solar - Solar PV Schematic not present

  • Solar - The exterior run of cable down the side elevation is not secured to the wall

  • Solar - Installer Missing Documents

  • Solar - Missing Photographic evidence

  • Solar - Post install Missing Documentation

  • Solar - Walkboard by inverter not present

  • Solar - Issue with panels install

CWI

  • CWI - Injection holes/penetrations have not been sealed

  • CWI - No background ventilation present

  • CWI - Missing documents

  • CWI - Combustion appliances

  • CWI - Approval for U-Values is missing

  • CWI - Drill pattern

Ventilation

  • Ventilation - Background ventilation

  • Ventilation - No evidence that the extractor fans fitted correctly

  • Ventilation - MEV's not present

  • Ventilation - Trickle vents not present

  • Ventilation - Undercuts not present

  • Ventilation - Does not match Vents strategy

  • Ventilation - Missing Photo evidence

  • Ventilation - Missing documentation

  • Ventilation - Minor works certificate required for ventilation installation

ESH

  • ESH - Electrical Cables not clipped away from pipework

  • ESH - Missing photographic evidence

  • ESH - Missing paperwork

Boiler

  • Boiler - Boiler flue location

  • Boiler - Damage caused by installers

  • Boiler - System not working

  • Boiler - Not installed to up to date regulation standard

  • Boiler - Issue with Radbots and TRV's installed

  • Boiler - Missing Paperwork

  • Boiler - Missing Photographic evidence

  • Boiler - Issue with radiators

  • Boiler - pressure drops out

ASHP

  • ASHP - System regularly dropping in pressure

  • ASHP - System trips out daily

  • ASHP - not installed to manufacturers instructions and other guidance

  • ASHP - Does not match the strategy

  • ASHP - Discharge pipe not terminated in accordance with Building Regulations

RIR

  • RIR - No dataplate photo supplied

IWI

  • IWI - Do any faults specific to the measure installed present an immediate risk to the occupier or the property?

  • IWI - Do you believe that there are any other safety related issues with the installation?

  • IWI - Have all avoidable thermal bridges/heat loss areas which could have been insulated, been insulated?

  • IWI - Has 100% of the measure been installed where possible?

  • IWI - Is the measure installed as specified in the appropriate product certificate and/or system designer's instructions?

  • IWI - Is the insulation sealed around all adjoining boards, walls, ceilings and floors?

  • IWI - Is the insulation continued 400mm along all party and solid partition walls where required by the system design?

  • IWI - Have all services (e.g. light switches, sockets, radiators) been removed, insulated behind and re-positioned inside the heat<br>loss area?

  • IWI - Has the system been sealed fully at edges, corners and junctions to prevent the ingress of moisture?

  • IWI - If wet room(s) have been omitted do they have a safe heating system that can achieve a minimum of 18 degrees C ?

  • IWI - If wet room(s) have been omitted, has CONTINUOUS extract ventilation been installed?

  • IWI - Is the external condition of the property suitable for IWI to be installed?

  • IWI - Does the provision of ventilation in the property meet the requirements of the relevant version of<br>PAS?

  • IWI - Is background ventilation present in each habitable room (e.g. trickle vents / room ventilators)?

  • IWI - Is the ventilation in all habitable rooms controllable?

  • IWI - Are background ventilators at least 1700mm above floor level, to reduce cold draughts, but still easy for the occupant to reach?

  • IWI - Are mechanical extract ventilators intermittent or continuous?

  • IWI - Do background ventilators have a minimum equivalent area of 4000mm2 and are not present in wet rooms?

EWI

  • EWI - Roof overhand not installed correctly

  • EWI - Installation of EWI carried out to an acceptable standard

  • EWI - The system has not been sealed and is watertight

  • EWI - Movement/Construction Joints

  • EWI - Building features re-instated

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.