Integrated Project Management Plan (IPMP).

  • Has a IPMP been completed for the project/work (check date issued).

  • Have all staff and sub-contractors received a site specific induction and white/blue cards sighted (check a few).

  • Are Safe Work Method Statements available for all high risk activities.

  • Are emergency telephone numbers available/displayed.

  • Are incident/NCR forms available? (Check to see if any completed for HSEQ, and have been added to the FIXIT Diary with appropriate actions taken to close out)?

  • Has Foreman/Supervisor completed Hazard Identification Checklist for job site?

  • Have Weekly Inspections, Daily Pre-starts/Toolbox Talks been completed.

  • Have Construction Drawings been issued for the project? (Check that drawings are current).

Site Access.

  • Is site secured with fencing and signage displayed at entrances restricting access? (Where required)

  • Is site signage displayed at the entrance to the project (Project signage, QBSA number, Unauthorised entry signs)?

  • Are footpaths clean and clear, Vehicle crossovers have no pedestrian trip hazards?<br>

Environmental Controls.

  • Rain events have the potential to destabilise excavations, undermine scaffolding supports or supports for precast elements etc. (Inspect the effect of rain or water events on site)

  • Are erosion and sediment control devices in place prior to excavation works commencing on site?

  • Are storm water/kerb inlet pits fitted with protection (where required)?

Amenities / Work Areas.

  • Is site office clean and tidy (no trip/slip hazards) and does regular waste removal occur?<br>

  • Is there adequate supply of drinking water, hand washing facilities and toilets available?<br>

  • Are work areas tidy and staff using good stacking and storage practices?

  • Are vehicles and plant not directly involved in construction activities, parked clear of work area and public thoroughfares?

First Aid.

  • First-aid equipment is available with all items in date?

  • First-aid Officer's names clearly displayed?<br>

Housekeeping.

  • Site access ways clear of material and waste?<br>

  • Site personnel are cleaning up after each days activities?<br>

  • Trip hazards are all removed progressively?<br>

  • No build up of waste on site?<br>

  • Protrusions are protected (Reo capped and sharp objects guarded)?

Personal Protective Equipment (PPE).

  • PPE is maintained and in good condition (boots not falling apart, shirts not faded/torn, helmets in date 3 years) and being worn correctly?

  • Use of PPE is appropriate to tasking (Goggles for over head drilling, face shields/dust masks for grinding/cutting concrete)?<br>

Electrical Equipment / Power Tools.

  • A handover certificate exists for all temp boards and site shed?<br>

  • Temp boards are in good repair and RCD tested each month?<br>

  • Electric leads are not exposed to mechanical damage (Suspended where required or exposed to potential damage), not run on the floor in access ways?

  • Checked test tags are within test dates (3 months)?<br>

  • Are Generators protected by RCD's a have they been tested to ensure correct operation?

  • Are all leads plugged into RCD's (no double adapters or piggy back plugs)?

  • Are portable power tools in good condition with all guards in place and stored out of the weather?

Trenching and Excavation.

  • Overhead services clear of excavation zone, is electrical spotter required (works is 3m exclusion zone)?

  • All services located (prior to excavation) with copy of locations included in project folder?<br>

  • Benching at not more than 1.5m steps (1m steps preferred) and 1 in 1?

  • Trenches/excavations left unattended are barricaded?<br>

  • Access ladders in trenches at 9m intervals where depth is greater than 1m?<br>

Working at Heights.

  • Ladder access provided and secured?

  • Workers using harnesses have been trained for their use and have a fallen worker retrieval procedure?<br>

  • Exclusion zones are maintained below workers and signs placed (if required) to state "Workers Above"?<br>

  • Access systems are suitable for taking tools and materials up to the working platform?

  • Controls are in place to prevent falling objects?

Ladders.

  • Are Ladders in good condition and rated greater than 120kg (not domestic)?

  • Access ladders extend 1m past point of access and are secured?<br>

  • Persons using ladders maintain 3 points of contact, are not over reaching, pulling or pushing potentially over turning the ladder?<br>

  • Ladders are set up on firm flat ground with solid footing, no loose material or debris at base?

Scaffold.

  • Drawings held on site for erected scaffold?

  • Erected scaffolds have been certified by competent person and re-certified every 30 days?<br>

  • Scaffold decks clear of debris and trip hazards?

  • Are gaps in working platform boards <25mm with a total of all accumulative gaps not exceeding 50mm?

  • Are lap boards secure against uplift?

  • Are top and middle rails fitted, are kick boards in place, are containment screen fitted/required?

Plant and Equipment.

  • Have daily Pre-Start checks been completed and recorded?<br>

  • Operators hold certification and or have completed a VOC where required?<br>

  • Safety pins used on excavator/backhoe quick hitch attachments?<br>

  • Warning lights and reversing beepers operating and all anti-slip surfaces in good condition?

Scissor / Boom Lifts.

  • Operators have High Risk Work Licence for 11m+ and yellow card for scissor lifts or similar for under 11m?

  • Every operator has completed a Pre-Start check and signed the log book?<br>

  • There are no penetrations or drop off edges unprotected in EWP operating areas?<br>

  • Overhead power precautions detailed in the SWMS or daily prestart if present?<br>

  • Floor area of plant (basket) clear to prevents trips and falls?<br>

  • Operators manual held with the plant for easy access?

  • Plant is not operating with identified defects on the checklist?

Penetrations.

  • All penetrations have been covered with a suitable cover that is secured against dislodgment. Penetration covers are clearly marked “Warning hole below” or words to a similar effect?

  • Penetrations are barricaded where securing has been released for access?

Edge Protection.

  • Mesh guards fitted and secured?<br>

  • Toe-boards or mesh guard (where fitted) in close contact with the floor or platform level?

  • Check for sturdiness and secured components, including supporting structure?<br>

  • Edge barricades back 1.8m from edges (Formwork live edge protection etc)?

Hazardous Manual Tasks.

  • Workers avoiding twisting and lifting (Particularly over chest height)?

Hazardous Chemicals.

  • Material Safety Data Sheets (MSDS) register is readily available for all MSDS brought to site and MSDS are current (5 years from issue date)?<br>

  • Has a “Risk Assessment” been completed for each Hazardous/Dangerous goods on site?<br>

  • Are all chemical containers, including decanted containers, labeled appropriately?

  • Emergency spill response equipment (yellow bin/spill kit) is on site and full inventory is available?

Crane Activities - Including Excavators used for Crane Work.

  • Overhead services clear of lift zone, is electrical spotter required (works in 3m exclusion zone)?

  • Excavators/Backhoes used in crane mode have anti-burst devices fitted, an “SWL” marked on the dipper arm and an “appropriate” load chart in the operator’s cabin?

  • Is all lifting gear tagged, current, stored appropriately and in good condition (hooks fitted with safety latches)?

  • Are lift plans available for lifts of a complex nature?

  • Is the crane Fit for Purpose (suitable for the proposed lift)?

Material Storage.

  • No materials stacked in front of water coolers, power boards, fire extinguishers or fire exits?<br><br>

  • Access ways are kept clear?<br>

  • Clear access to storage location?

  • Are storage locations designated and advised to all PCBU's?

Non-Conformances

Recommendations.

Sign off - fgf personnel

  • Note: Present audit findings to Project Team and sign off.

  • Additional comments by personnel conducting audit.

  • Name and Site Role of fgf personnel conducting audit.

Sign off - Project Manager or Site Foreman.

  • Name, position and signature of PM or SM

  • PM or SM comments

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.