  • TOW Number

  • FDH Location

  • FSAM Location

  • Conducted on

  • Prepared by (your name)

  • Installation completed by:

  • Customer Address

Preliminary checks

  • DBYD required/conducted

  • Way leave access consent required/obtained

  • Land access consent required/obtained

Pit & conduit installation

  • Conforms to slope and ground level

  • The top rim of the lid is not warped or bent and is labelled as a communications pit

  • Pit not located within a carriageway, driveway, 3m of a pole or 5m of a corner

  • Pit positioned with long side parallel to the adjacent property, boundary or road way

  • The pit does not have exposed edges

  • Correct service drop access pit used (length 650mm x width 280mm x depth 565mm)

  • Pit lid has a lifting tool hole at each end of the lid

  • Pit has a gasket fitted

  • Radial clearance of 300mm from gas pipe over 110mm diameter

  • Radial clearance of 150mm from gas pipe under 110mm diameter

  • Radial clearance of 300mm from high voltage

  • Radial clearance of 100mm from low voltage

  • Radial clearance of 300mm from high pressure water main

  • Radial clearance of 150mm from local water reticulate on

  • Radial clearance of 300mm from mains sewerage

  • Radial clearance of 150mm from local sewerage connection

  • Radial clearance of 100mm. From other telecommunications

  • Conduit installed a minimum of 50mm from the pit floor

  • 25mm separation between conduits

  • Conduit has bushes fitted and finishes square and flush with the pit end wall

  • Conduit depth is 400mm with warning tape at 300mm

  • Conduit shall be white PVC-U 23mm diameter

  • Work area left clean and tidy

Underground Drop Cables

  • Cables connected to the correct Multiport port

  • Correctly labelled

  • Cable slack is coiled neatly

  • Ground reinstatement undertaken

  • Cable or conduit has been suitably fixed to the premises

  • Telstra LIC used

  • Work area left clean and tidy

PCD

  • Installed at the closest practical point on the premise to connect drop

  • Meets power source separation requirement of 1000mm

  • Meets water and gas fitting separation requirements of 250mm

  • Meets distance from corner of wall requirements of 150mm

  • Meets distance from window or balcony requirement of 150mm

  • Mounted vertically with latches on the right hand side

  • PCD height must fulfil all location and accessibility req's from NBN-NO-GDE-0007

  • Drop cable enters only from bottom of the PCD

  • 25mm gap has been left between the lead-in pipe and the PCD (for underground drop)

  • Cables go through the correct grommet type (flat=Left, round=Centre or right)

  • One cable per Entry/Exit point

  • Sufficient space to access the PCD and open the latches and door

  • Stored cable is not excessive (<=3m drop, <5m Premises)

  • Store cable is coiled neatly without exceeding bend radius

  • Work area left clean and tidy

  • Reinstatement

  • PCD

  • Pit

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.