LANDSCAPING
-
All Erosion BMPs removed
-
All plant material is alive
-
Drainage swales in place and draining water, no standing water
-
Irrigation working properly, test all zones, check coverage of all heads
-
Landscaping Beds are free of debris and are tight
-
Main sewer tap cleanout has concrete ring with lid installed
-
Minimum 6" clearance from top of slab to grade
-
No bare/dead spots in sod
-
No construction debris on neighboring lots
-
Pine straw in place, no bare spots
-
Review all selections and options for completion and accuracy
-
Sewer cleanouts are 4‐6" above grade if in a bed. Flush if in grass
-
Stoops and Patios have sufficient fall away from house
-
Sufficient fall away from house on all sides
-
Tags/Labels removed from plans
-
Temporary power pole has been removed
-
Termite Stations are in place
-
Water meter installed and set flush with grade, box/lid undamaged
-
Yard is rolled and doesn't have excessive ruts
EXTERIOR
-
All flatwork is pressure washed
-
All penetrations are caulked/sealed
-
All porch columns installed, plumb, painted, trim is level
-
All siding has 1" clearance off roof deck
-
All slide guards have been removed
-
All soffit and fascia are secure/undamaged
-
All window screens are in place and free of rips or loose screen
-
Attic/Dormer windows are locked
-
Attic/dormer windows have been painted black on inside, no framing visible from outside
-
Check roofing plan for crickets. Crickets should extend 2‐3" beyond outside corner
-
Confirm elevation on plan matches house (shutters, vents, brackets, etc)
-
Exhaust vent covers are on and flapper doors in place.
-
Exterior Door thresholds secure and painted
-
Exterior lighting installed, all bulbs working
-
Flashing installed over all doors, windows, and siding blocks
-
Gas piping is grounded
-
GFCI outlets are in place and function properly, test all.
-
Gutters secure and pitched correctly
-
Hardie homes are free of over cuts around windows/doors/blocking
-
Hose bibs secure, sealed to house, backflow preventers installed with set screw sheared off
-
House address numbers are installed on house and are level.
-
HVAC condensation line drains away form house, should terminate 2‐3" above grade
-
HVAC secondary drain is located above a window.
-
HVAC Units are level, secured to pad, pad is above grade
-
If eaves are fire rated, power vents are installed
-
Kickout flashing visible at all rake walls and protrudes beyond siding
-
Line set for HVAC is insulated with no rips
-
Mailbox installed, level, painted, secure
-
No damage or paint on porch shingles. Inspect from second story window
-
No debris/paint on roofs. Check for ladder damage at lower roofs
-
Pipe boots are in place. Nail holes and penetration are sealed.
-
Review all selections and options for completion and accuracy
-
Ridge vents in place and have shingle cap installed
-
Siding is secure and free of excessive bows.
-
Solid soffit in rakes and within 3 feet of any exhaust vent
-
Splash blocks in place at all down spouts
-
Spot check Hardie homes for installation of seam flashing
-
Vented soffit installed in eaves.
-
Vents are painted black.
-
Water heater operates properly. Set temperature to 120°F
-
Weather stripping in place.
GARAGE
-
# of Low volt feeds in panel are accounted for on exterior/interior of home (no covered outlets)
-
All circuits in kitchen should be GFCI and ARC Fault protected (purple)
-
All low volt wires have been terminated in panel
-
Amperage on A/C breaker should match amperage on exterior disconnect
-
Check all light switches for functionality. Light first. Fan second
-
Check for tripped breakers.
-
Electrical Low volt whip has been trimmed out and face plate installed
-
Electrical panel is labeled and legible.
-
Electrical panel is secure, all screws in place, no empty knockouts
-
Emergency contact label is in place
-
Energy sticker is in place
-
Floors have been pressure washed, control joints free of debris
-
Low volt panel cover installed and secure. Door opens/latches properly
-
Low volt panel is labeled.
-
No daylighting at garage doors
-
Opener bulbs are installed.
-
Opener owners/manual and remotes are in kitchen drawer
-
Overhead doors are operational
-
Paint label is in place
-
Review all selections and options for completion and accuracy
-
Safety sensors are aligned and no excessive/loose wiring
-
Switch plates are secure, level, screws aligned
-
Water shut off operates, escutcheons installed, line insulated, shut off tag in place
-
Windows are clean, operable, no scratches
FOYER
-
All Door hardware operates/locks smoothly
-
All hinge pins and screws are in place
-
All light bulbs working
-
Base board is free of bowing
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Door bell button is secure/level/lights up
-
Door bell transformer is in conspicuous location
-
Door Chime functions on push and release
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Front door has good paint finish. No chips or scratches
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
POWDER
-
All Cabinet trim in place
-
All Door hardware operates/locks smoothly
-
All hinge pins and screws are in place
-
All light bulbs working
-
All pipes for pedestal have escutcheons installed
-
Base board is free of bowing
-
Cabinet doors and hardware are level and secure
-
Cabinets are free of defects
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Confirm exhaust fan works. Turn fan on, locate vent on exterior.
-
Countertops are free of defects
-
Countertops sealed to wall and to cabinets
-
Doors do not rub frame or floor, reveal is consistent
-
Fill sink with water, release drain, check for leaks
-
Flooring is free of defects. No squeaks
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
Hot/Cold water are not reversed on sinks
-
HVAC registers are square, not over tightened, free of insulation
-
Light, mirror, and sink centered on each other
-
Mirrors installed, level, secure
-
Pedestal base is secure
-
Review all selections and options for completion and accuracy
-
Sink drain functions properly and drains well when open
-
Sink overflows work sufficiently
-
Switch plates are secure, level, screws aligned
-
Toilet flushes and refills properly without sticking open
-
Toilet is sealed to floor with gap at rear
-
Toilet seat secure with no scratches
-
Toilet supply has escutcheon installed and is flush to wall
-
Toilets are secure and level
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
Checklist
LIVING ROOM
-
# of Low volt feeds in panel are accounted for on exterior/interior of home (no covered outlets)
-
All Door hardware operates/locks smoothly
-
All hinge pins and screws are in place
-
All light bulbs working
-
Base board is free of bowing
-
Ceiling Fan is balanced well. Check pull chains for proper operation
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Fireplace operates, space above and below has been cleaned
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
HVAC returns have clean filters installed
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Thermostats installed, level, no paint overspray
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
KITCHEN
-
All appliance clocks are set and synced
-
All Door hardware operates/locks smoothly
-
All hinge pins and screws are in place
-
All light bulbs working
-
All paperwork is organized in a folder in one drawer. Only keep owner’s manuals not
-
installation guides. Remove all plastic
-
Anti Tip Device installed on slide in ranges
-
Base board is free of bowing
-
Cabinet doors and hardware are level and secure
-
Cabinets are free of defects
-
Chandeliers are strait and approximately 60" AFF
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Cooktop is installed, sealed to countertop and secured to cabinets, check operation
-
Countertop has grout caulk between top and tile backsplash
-
Dishwasher drain has back flow loop in place
-
Dishwasher is secure, check operation
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Garbage disposal is free of debris, check operation
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Over or oven/micros installed, flush to cabinets/countertops, check operation
-
Review all selections and options for completion and accuracy
-
Sink is sealed to countertop
-
Sink stopper is on site and in drawer
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Soap dispenser installed has a tube in place
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
DINING/BREAKFAST
-
All Door hardware operates/locks smoothly
-
All hinge pins and screws are in place
-
All light bulbs working
-
Base board is free of bowing
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
MUDROOM
-
All Door hardware operates/locks smoothly
-
All hinge pins and screws are in place
-
All light bulbs working
-
Base board is free of bowing
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Review all selections and options for completion and accuracy
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
LAUNDRY ROOM
-
All Cabinet trim in place
-
All Door hardware operates/locks smoothly
-
All hinge pins and screws are in place
-
All light bulbs working
-
Base board is free of bowing
-
Cabinet doors and hardware are level and secure
-
Cabinets are free of defects
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Countertops are free of defects
-
Countertops sealed to wall and to cabinets
-
Doors do not rub frame or floor, reveal is consistent
-
Drain Cap on washer box is removed
-
Dryer duct exterior termination verified
-
Dryer vent length of duct sticker is in place
-
Dyer vent trim ring is in place and no paint overspray in/on box
-
Flooring is free of defects. No squeaks
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
Hot/Cold water are not reversed on sinks
-
HVAC registers are square, not over tightened, free of insulation
-
Laundry drain box trim ring is in place and no paint overspray in/on box
-
Review all selections and options for completion and accuracy
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Washer drain pan is positioned correctly, connection is secure, pan not cracked
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
MASTER BEDROOM
-
All light bulbs working
-
Base board is free of bowing
-
Ceiling Fan is balanced well. Check pull chains for proper operation
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
HVAC returns have clean filters installed
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
Checklist
MASTER BATHROOM
-
All light bulbs working
-
Base board is free of bowing
-
Cabinet doors and hardware are level and secure
-
Cabinets are free of defects
-
Check all electrical outlets for functionality
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Confirm exhaust fan works. Turn fan on, locate vent on exterior.
-
Countertops are free of defects
-
Countertops sealed to wall and to cabinets
-
Doors do not rub frame or floor, reveal is consistent
-
Fill sink with water, release drain, check for leaks
-
Flooring is free of defects. No squeaks
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
Hot/Cold water are not reversed on sinks
-
Hot/Cold water on shower not reversed
-
HVAC registers are square, not over tightened, free of insulation
-
Light, mirror, and sink centered on each other
-
Mirrors installed, level, secure
-
Review all selections and options for completion and accuracy
-
Shower door installed, functional, and free of defects
-
Shower door is sealed to wall and curb and has silicone for first 3" beyond door
-
Shower finishes free of defects
-
Shower valve is flush to wall and sealed around edge
-
Sink drain functions properly and drains well when open
-
Sink overflows work sufficiently
-
Switch plates are secure, level, screws aligned
-
Test tub drains and overflow.
-
Thermostats installed, level, no paint overspray
-
Toilet flushes and refills properly without sticking open
-
Toilet is sealed to floor with gap at rear
-
Toilet seat secure with no scratches
-
Toilet supply has escutcheon installed and is flush to wall
-
Toilets are secure and level
-
Tops of door casings are caulked and painted
-
Tubs free of rust, dents, scratches
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
BEDROOM #2
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Jumper ducts are in place and both ends are accounted for (not covered up)
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
BATHROOM #2
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Confirm exhaust fan works. Turn fan on, locate vent on exterior.
-
Countertops are free of defects
-
Countertops sealed to wall and to cabinets
-
Doors do not rub frame or floor, reveal is consistent
-
Fill sink with water, release drain, check for leaks
-
Flooring is free of defects. No squeaks
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
Hot/Cold water are not reversed on sinks
-
Hot/Cold water on shower not reversed
-
HVAC registers are square, not over tightened, free of insulation
-
Light, mirror, and sink centered on each other
-
Mirrors installed, level, secure
-
Review all selections and options for completion and accuracy
-
Shower finishes free of defects
-
Shower valve is flush to wall and sealed around edge
-
Sink drain functions properly and drains well when open
-
Sink overflows work sufficiently
-
Switch plates are secure, level, screws aligned
-
Test tub drains and overflow.
-
Toilet flushes and refills properly without sticking open
-
Toilet is sealed to floor with gap at rear
-
Toilet seat secure with no scratches
-
Toilet supply has escutcheon installed and is flush to wall
-
Toilets are secure and level
-
Tops of door casings are caulked and painted
-
Tubs free of rust, dents, scratches
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
BEDROOM #3
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Jumper ducts are in place and both ends are accounted for (not covered up)
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
BATHROOM #3
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Confirm exhaust fan works. Turn fan on, locate vent on exterior.
-
Countertops are free of defects
-
Countertops sealed to wall and to cabinets
-
Doors do not rub frame or floor, reveal is consistent
-
Fill sink with water, release drain, check for leaks
-
Flooring is free of defects. No squeaks
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
Hot/Cold water are not reversed on sinks
-
Hot/Cold water on shower not reversed
-
HVAC registers are square, not over tightened, free of insulation
-
Light, mirror, and sink centered on each other
-
Mirrors installed, level, secure
-
Review all selections and options for completion and accuracy
-
Shower finishes free of defects
-
Shower valve is flush to wall and sealed around edge
-
Sink drain functions properly and drains well when open
-
Sink overflows work sufficiently
-
Switch plates are secure, level, screws aligned
-
Test tub drains and overflow.
-
Toilet flushes and refills properly without sticking open
-
Toilet is sealed to floor with gap at rear
-
Toilet seat secure with no scratches
-
Toilet supply has escutcheon installed and is flush to wall
-
Toilets are secure and level
-
Tops of door casings are caulked and painted
-
Tubs free of rust, dents, scratches
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
Checklist
BEDROOM #4
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Jumper ducts are in place and both ends are accounted for (not covered up)
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
BATHROOM #4
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Confirm exhaust fan works. Turn fan on, locate vent on exterior.
-
Countertops are free of defects
-
Countertops sealed to wall and to cabinets
-
Doors do not rub frame or floor, reveal is consistent
-
Fill sink with water, release drain, check for leaks
-
Flooring is free of defects. No squeaks
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
Hot/Cold water are not reversed on sinks
-
Hot/Cold water on shower not reversed
-
HVAC registers are square, not over tightened, free of insulation
-
Light, mirror, and sink centered on each other
-
Mirrors installed, level, secure
-
Review all selections and options for completion and accuracy
-
Shower finishes free of defects
-
Shower valve is flush to wall and sealed around edge
-
Sink drain functions properly and drains well when open
-
Sink overflows work sufficiently
-
Switch plates are secure, level, screws aligned
-
Test tub drains and overflow.
-
Toilet flushes and refills properly without sticking open
-
Toilet is sealed to floor with gap at rear
-
Toilet seat secure with no scratches
-
Toilet supply has escutcheon installed and is flush to wall
-
Toilets are secure and level
-
Tops of door casings are caulked and painted
-
Tubs free of rust, dents, scratches
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
BEDROOM #5
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Doors do not rub frame or floor, reveal is consistent
-
Flooring is free of defects. No squeaks
-
Hinge/base bump installed on all doors
-
HVAC registers are square, not over tightened, free of insulation
-
Jumper ducts are in place and both ends are accounted for (not covered up)
-
Review all selections and options for completion and accuracy
-
Smoke Detector in place. Activated. Dust cover removed. Test for operation
-
Switch plates are secure, level, screws aligned
-
Tops of door casings are caulked and painted
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
BATHROOM #5
-
Check all light switches for functionality
-
Check all light switches for functionality. Light first. Fan second
-
Check plan for tempered window locations
-
Compare number of supply vents in room to manual J
-
Confirm exhaust fan works. Turn fan on, locate vent on exterior.
-
Countertops are free of defects
-
Countertops sealed to wall and to cabinets
-
Doors do not rub frame or floor, reveal is consistent
-
Fill sink with water, release drain, check for leaks
-
Flooring is free of defects. No squeaks
-
GFCI outlets are in place and function properly, test all.
-
Hinge/base bump installed on all doors
-
Hot/Cold water are not reversed on sinks
-
Hot/Cold water on shower not reversed
-
HVAC registers are square, not over tightened, free of insulation
-
Light, mirror, and sink centered on each other
-
Mirrors installed, level, secure
-
Review all selections and options for completion and accuracy
-
Shower finishes free of defects
-
Shower valve is flush to wall and sealed around edge
-
Sink drain functions properly and drains well when open
-
Sink overflows work sufficiently
-
Switch plates are secure, level, screws aligned
-
Test tub drains and overflow.
-
Toilet flushes and refills properly without sticking open
-
Toilet is sealed to floor with gap at rear
-
Toilet seat secure with no scratches
-
Toilet supply has escutcheon installed and is flush to wall
-
Toilets are secure and level
-
Tops of door casings are caulked and painted
-
Tubs free of rust, dents, scratches
-
Window/door trim level, flush, good paint coverage, caulked well
-
Windows are clean, operable, no scratches
-
Wire shelving is level, secure, all screws in place, no scratches
ATTIC
-
A/C unit is strapped to platform
-
All hinge pins and screws are in place
-
All mastic/tape is in good condition
-
Attic access is cleaned off
-
Ceiling accesses are energy rated with weather stripping installed
-
Check all light switches for functionality. Light first. Fan second
-
Doors do not rub frame or floor, reveal is consistent
-
For gas furnaces, caps are removed from condensation line
-
HVAC registers are square, not over tightened, free of insulation
-
Insulation does not block soffit ventilation
-
Insulation Ruler is in place and depth of blow insulation meets code
-
Keyless light installed and switch located near access
-
Line set for HVAC is insulated with no rips
-
No unprotected wiring
-
Overflow pan under A/C unit is clear of debris and drain line is not clogged
-
Review all selections and options for completion and accuracy
-
Sufficient gap at ridge vents
-
Switch plates are secure, level, screws aligned
-
Temporary bracing has been removed from trusses
-
Tops of door casings are caulked and painted
-
Wall accesses have weather stripping installed
-
Window/door trim level, flush, good paint coverage, caulked well
SIGN-OFF
-
Checked by