Title Page

  • Business Name

  • Location
  • Date of Inspection

  • Inspector

Plans / Drawings

  • Verify approved plans / drawings are on-site or are available to the contractor.

Visual Inspection

Riser and Riser Room

  • Backflow prevention device size, type, and flow direction verified.

  • Main drain is proper size, piped outside, or to floor drain.

  • A means to forward flow the backflow prevention device is installed.

  • Verify components are stacked on the riser as shown on the plans.

  • If required, an accelerator is installed.

  • Metal or rigid plastic hydraulic design information sign is attached.

  • General information sign posted with appropriate information.

  • General information sign should include: name; location; flow test data; presence of high-pile/rack storage; presence of flammable/combustible liquids; max storage height planned; presence of hazmat; aisle width planned; presence of other special storage; commodity classification; location of aux/low-point drains; encapsulation status; main drain flow test data; presence of solid shelving; location of dry/anti-freeze systems.

  • Main drain labeled.

  • Spare sprinklers provided (6 if < 300 heads; 12 if 300 – 1,000 heads; 24 if >1,000 heads).

  • Replacement wrench is provided.

  • Multiple risers are numbered and consistent with alarm addressing.

  • Riser room has label and an approved locking key box or OS&T/PIV is provided.

  • Room has hard wired heat, light, and emergency light.

Piping and Hangers

  • Proper type of piping, layout, and size.

  • Branch lines have one hanger per section of pipe.

  • Mains and cross mains have hanger between branch lines and at ends.

  • Max distance between end of line & hanger (48” for 1-1/4”; 60” for 1-1/2” and greater).

  • Risers have supports at lowest level, alternate level, and at top.

  • Verify installation of inspector’s test valve (remote area).

  • Inspectors test connection clearly labeled and accessible.

  • All low-point drains are clearly labeled and accessible.

  • Sign at each control valve with description of area served.

Sprinkler Heads

  • Sprinkler heads are not obstructed.

  • Type, temperature, and spacing of sprinkler heads match approved plans.

  • Heads are minimum of 4” from wall/vertical obstruction.

  • Heads are separated by a minimum of 6’.

  • Heads are 1” - 12” below ceiling; Sidewalls are 4” - 6” from ceiling.

  • Heads installed under fixed objects/overhangs greater than 4’ wide.

  • Verify ceiling pockets and skylights are properly protected.

  • Verify sprinkler heads are free from paint, coverings, etc.

  • Verify escutcheons are installed where required.

  • ESFR upright deflectors are a minimum of 7” above top of the pipe.

  • ESFR heads are a minimum of 1’ away from the joist/truss.

  • ESFR heads are a minimum of 3’ above top of the storage level.

Fire Department Connection (FDC)

  • FDC is visible and accessible from the fire lane.

  • Connections 18” - 48” above finished grade with Knox Cap.

  • A locking Knox Cap is provided for each FDC connection.

  • 4' wide all-weather pathway to FDC.

  • Signage is provided indicating the area, building, or address served.

  • 2-1/2” Siamese or 5” Storz connection provided (depending on fire department response area).

  • Check valve behind connection and ball drip; verify flow direction.

Hydrostatic Test

  • Confirm underground fire line has been finalized.

  • Starting pressure is minimum of 200 PSI.

  • Pressure pumps disconnected after initial pressurization.

  • Test lasted a minimum of 2 hours; resulting in no pressure loss.

  • Relieved pressure on system and gauges returned to zero PSI.

Pneumatic Test

  • Starting pressure is minimum of 40 PSI.

  • Air compressor disconnected after initial pressurization.

  • Test lasted a minimum of 24 hours; resulting in less than 1.5 PSI pressure loss.

  • Relieved pressure on system and gauges returned to zero PSI.

Operational Test

  • Backflow prevention assembly forward flow tested.

  • Test of valve conducted, without Quick Opening Device (QOD).

  • Test of valve conducted, with Quick Opening Device (if >750-gallon capacity).

  • Record time from complete opening of inspector’s test to water flow at inspector’s test.

  • Water delivery <60 sec or <500-gal or <750-gal w/QOD.

  • Waterflow switch activates between 45 and 90 seconds (non-silenceable).

  • Control valves operated under normal system pressure.

  • Pressure reducing valves tested under full flow and no-flow conditions.

  • Main drain test completed; static and residual pressures recorded.

  • Air compressor fills the system within 30 minutes.

  • Confirm proper high and low air pressure is set for air compressor.

  • Exposure protection systems tested (only if no risk of water damage to building).

  • Automatic inspection and testing devices/equipment operationally tested.

  • Deluge and pre-action systems operate automatically when triggered.

  • Both manual- and remote-control systems on deluge/pre-action systems are operational.

Documentation

  • As-built plans provided if applicable.

  • Aboveground contractor's material and test certificate provided.

  • https://www.tdi.texas.gov/forms/sfmfireindustry/sf041sprabovgrn.pdf

Inspection Status

  • Inspection Status

  • Next Inspection

  • Fire Alarm Contractor

  • Phone #

  • Email Address

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.