Information

  • Gas Main Installation Quality Control Review Sheet (Form 3815)

    *Reviews are to be completed on all main projects (service only projects are excluded)

  • Document No.

  • Conducted on

  • Prepared by

Project Description

  • Project Description:

  • SAP Order Number:

  • Date of Review:

  • Crew Foreman:

  • Company:

Design

  • Installed per Design?

  • Field modifications approved by design engineer?

Work Site

  • Restoration (landscaping, grade, etc.) acceptable?

  • Installation within ROW boundaries?

  • ROW left in reasonable manner?

Installation Per Standards

Materials Used as Specified:

  • Pipe/Fittings (52-A, 53-A, 53-B)

  • Line Markers, Locate Stations (55-F)

  • Key Valves (61-B to 61-E)

  • Test Stations (55-F)

Joining Method(s):

  • Procedure(s) Used per Construction Standards:

  • Welding (53-P)

  • Fusion (52-P)

  • Mechanical (52-P)

Tapping/Stopping (53-K, 3130):

  • Verify coupons were retrieved and Internal Inspection Form completed (Form 3170)

Tracer Wire (52L):

  • Taps Solder to Main Wire

  • Western Union Splice

  • DBY Splice Kits

  • Burial depths and separation met per Construction Standards (55-B):

  • Riser and meter set installed per Construction Standards (59-A):

Backfilling

  • Backfill Used (55-E):

  • Adequate Compaction (55-E):

Special Crossings

  • If applicable, verify all standards and/or requirements are met (road/rail/transmission):

  • Reviewed By

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.