Information

  • Overhead Installation Quality Control Review Sheet (Form 3816)

    *Reviews are to be completed on all primary projects (service only projects are excluded)

  • Document No.

  • Conducted on

  • Prepared by

Project Description

  • Project Description:

  • SAP Order Number:

  • Date of Review:

  • Crew Foreman:

  • Company:

Design

  • Installed per Design?

  • Field modifications approved by design engineer?

Work Site

  • Installation within ROW boundaries?

  • Restoration (landscaping, grade, r/w, etc.) acceptable?

  • Scrap, salvage, spent poles addressed?

Pole Installation (Minimum - 10% of poles must be reviewed)

  • Size and class per staking sheet?

  • Fill properly tamped?

  • Grounds installed per staking sheet?

  • Guy type installed per staking sheet?

  • Dead ends and angles with rake?

  • Correct clearance and insulator placement?

  • Poles set at proper depth?

  • Ground molding installed?

  • Anchor distance per staking sheet?

  • Guy guards installed?

  • Tagging transferred to new pole?

Framing

  • Tangents per staking sheet and standards?

  • Dead ends per staking sheet and standards?

  • Raptor and animal protection per staking sheet?

  • Neutral offset brackets per staking sheet?

  • Angles per staking sheet and standards?

  • Taps per staking sheet and standards?

  • Climbing space maintained?

Field Equipment

  • Correct Transformer KVA per staking sheet?

  • Lightning arrestor location per standards?

  • Required ground molding installed?

  • Specified fusing and tagging installed?

  • Animal guards installed per standards?

  • Grounds installed per staking sheet?

  • Transformer bolt end insulator installed?

  • Specified phase(s) tapped?

  • Other equipment (air brakes, reclosures, cap banks, etc.) installed per design and standards?

Primary Conductor

  • Do you want to add a primary conductor review?

  • Primary Conductor Review
  • Location of review (reference pole ID or #):

  • Span length as per design?

  • Joint use clearance as per standards?

  • Conductor height ground clearance as per design?

  • Conductor height above ground at pole attachment as per design?

  • Correct Sag height per design?

  • Vertical clearances as per NESC?

  • Horizontal clearances as per NESC?

Special Crossings

  • If applicable, verify all standards and/or requirements are met (road/rail/transmission):

  • Reviewed By

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.