Workplace Safety and Security Audit
Contractual SHEQ Requirements
-
Are Site Operating Guides finalised and agreed?
-
Have all sub-contractors received and signed the Site Operating Guide?
-
Have all Site Risk assessment been prepared, reviewed and approved?
-
Has all required Safety Training been completed, for both ENGIE and subcontractor staff?
-
Has the Health and Safety Inspection schedule (Safety Audit, Management Safety Visit, Joint Safety Walk schedule) been agreed?
-
Has the Health and Safety Incident, Hight Potential Incident and Near Miss reporting process been agreed?
-
Has an escalation process for operational, environmental and safety incidents been agreed?
-
Is the Safety , health, Environment, and Quality monthly status report available?
-
is a Site Induction and Customer Permit to Work Process in place and in use?
-
Are Risk Assessment and Method Statements in place for all high-risk activities with Potential for Significant Injury and Fatality (pSIF)?
-
Any additional comments:
ENGIE One Safety Culture
-
All staff and sub-contractors are familiar with, and apply the ENGIE Life Saving Rules
-
All staff and sub-contractors are familiar with, and apply the Faurecia Safety Essentials
-
All staff and sub-contractors conduct a Last Minute Risk Assessment before starting or resuming work
-
All Staff and sub-contractors are familiar with the ENGIE Sop the Work Authority
-
Any additional comments:
Work Activity being performed (During works)
-
Are there any technicians performing work at the time of the audit?
-
Are the Technicians/Engineers working in a way that complies with regulations, site procedures and their own risk assessment and work procedure?
-
Are the Technicians/Engineers using the correct safety equipment throughout the work activity?
-
Did the Technicians/Engineers maintain a generally clean and tidy workspace while performing the works?
-
Any additional comments:
Sub-Contractor Management
-
Are all sub-contractors identified?
-
Is the scope of work for eac sub-contractor documented and agreed?
-
Are formal agreements in place between ENGIE and the sub-contractors?
-
Are sub-contractors monitored to ensure effective and safe service delivery?
-
Are sub-contractor non-conformances reported and corrective action plans in place?
-
Are all sub-contractor assessments complete including H&S assessments, public/employers liability insurance certificates, etc.?
-
Any addtional comments:
Corrective Action Items
-
For all flagged responses has a corrective action plan been created?