Exterior Storefront

Key Turn Over

  • Do you have the location of the key?

  • Does the store have a Knox Box? Code?

Signage

  • Is the signage installed? (Halo, Blade, Vinyls, Awning)<br><br>If exterior location, is address applicable?

Glazing

  • Is the glazing system installed? (Water Tight)

Doors

  • Are the doors complete? (Hardware/Kickplates,Hold Opens/Closers/Check Locks/Weather Stripping/Floor Sweep.

  • Are all functions of the door working properly?

  • Are the pull handles on all doors?

Trim

  • IS the trim at the storefront complete and correct?

Finish

  • Is the finish completed to our standards?

Lights

  • Are all the lights installed? (Goose neck/Sconces)

  • How is the overall Exterior Storefront?

  • Additional notes for section

Interior Storefront

Doors

  • Are the doors complete?

  • Are all functions of the doors working properly?

  • Are the pulls handles on all doors?

Trim

  • Is the trim complete?

Finish

  • Is the finish complete to our standards?

  • How is the overall quality of the Interior Storefront?

  • Additional notes for section

Ceiling

Lights

  • Are a;; the track lights installed correctly?

  • Are the lights directed towards the merchandise? (Crisscross pattern)

  • Are the tracks attached to the drywall/direct to the grid? (Do not hang from tiles)

Finish

  • Is the finish completed to our standards?

Acoustical Tile/Hard Lid

  • IS the ceiling completed and installed correctly?

  • How is the overall quality of the Ceiling?

  • Additional notes for section

Walls

Finish

  • Are the walls complete?

Baseboards

  • Have the baseboards been installed?

  • Are the nail holes filled in on baseboards?

  • How is the overall quality of the Walls?

  • Additional notes for section

Flooring

Wood/VC Plank

  • Has the Wood/VC Plank been installed? (Transition Strips)

Finish

  • Is the finish completed to our standards?

  • How is the overall quality of the Flooring?

  • Additional notes for section

Fixtures

Fixture Layout

  • Provide a photo of the most recent Layout

  • Are the fixtures laid out per plan? If no, is there a particular reason why not and explain?

  • Are the tables laid out per plan? If no, is there a particular reason why not and explain?

Shelving

  • Are the mounted shelves sturdy?

  • Are the bracket installed correctly?

  • Are the screw heads painted?

  • Are the metal end caps installed double up on all appropriate rods?

3FO/3FOHB

  • Is the 3FO mounted securely? (Top and Bottom Shelves)

  • Is there enough separation for the 3FO?

4WS

  • Are the shelves installed at 24", 40", 56", and 72" and sturdy?

Armoire

  • Are the glass shelves installed in the armoire?

  • Has the cork been removed from the glass shelves?

  • Is the armoire secured to the wall?

  • Are the LED bulbs installed and power hooked up?

  • Are the door/drawers operational?

Glass Cabinets

  • Are the glass shelves installed in the glass cabinets?

  • Has the cork been removed from the glass shelves?

  • Are the glass cabinets secured to the wall?

  • Are the LED bulbs installed and power hooked up?

  • Are the door/drawer operational?

Cash Wrap

  • Are the cash wrap secured to the floor with 36" separation?

  • Is the glass installed in the center with rubber bumpers?

  • Are the data jacks at the front of the cash wrap? (Toward the inside of the opening)

  • Have the stub outs been concealed from view of the sales area?

  • Have the stereo and speakers been installed and working?

  • Are the door/drawers operational?

  • Is the picture frame grid attached above the back CW and screws at the bottom corners?

  • How is the overall quality of the Fixtures/Cabinets?

  • Additional notes for section

Dressing Rooms

Hardware

  • Is the hardware installed correctly per the most recent fixture manual?

Sconces

  • Are the sconces installed and center above the mirrors?

Can Lights

  • Are the can lights installed above each dressing room?

Mirrors

  • Has the trim been installed around the mirrors?

  • Are all seams caulked on all four sides? (Trim and Mirror)

Dressing Room Bars/Hooks

  • Are dressing room bars installed correctly?

  • Were the purse hooks installed outside of the dressing room?

Crown/Trim

  • Is the crown installed correctly?

  • Is the trim installed around all dressing room panels? Are all seams caulked?

  • How is the overall quality of the Dressing Rooms?

  • Additional notes for section

Stock Room

Stockroom Door

  • Is the stock room door installed and frosted?

Combo Lock/Passage Handle

  • Has the door handle been installed? If no, why? (i.e. Locksmith install or Code does not allow)

Rear Door

  • Is there a rear door?

  • Has the door bell been installed? Can you hear on sales floor?

  • Has the door been weather sealed and sweeps installed?

  • Is the panic bar operational? Or, is Locksmith installing?

  • Has the peephole been installed?

Shelving

  • Is the shelving installed and sturdy? (Plywood Backer)

Walls

  • Are the walls finishes completed to our standard?

Ceiling

  • Is the ceiling finished to our standard?

Floor

  • Is the floor finished to our standard?

Water Fountain/Water Cooler

  • If there is a water fountain, is it installed and working properly?

  • How is the overall quality of the Stockroom?

  • Additional notes for section

Restroom

Hardware

  • Has all the Restroom hardware been installed? (Mirror/ADA Hardware/Toilet Paper Holder/Paper Towel Holder)

Toilet

  • Is the toilet installed and functioning properly?

  • Has the toilet been snaked? (Floor Drain)

  • Is the supply line a steel braided line?

Sink

  • Is the hot water working?

  • Has the sink been snaked? (Floor Drain)

Mop Sink

  • If there is a mop sink, is it working properly?

Restroom Door

  • Is the RR door hardware installed and working?

Walls

  • Are the walls finishes completed to our standards?

Ceiling

  • Is the ceiling finished to our standard?

Floor

  • Is the floor finished to our standard?

  • How is the overall quality of the Rest Room?

  • Additional notes for section

Electrical/Mechanical

Lighting

  • Are all the lights installed and directed towards the merchandise?

Receptacle Covers

  • Are all the cover plates at the electrical sockets?

CAT 6 Cabling

  • Has all 4 cables been installed at Cash Wrap and two cables installed at Manager's Desk?

  • Are all cables terminated?

Electrical Panel

  • Has the electrical panel been labeled? (Typed)

Display Lighting and Signage Timer

  • Is the timer installed and properly set? (1 Hr. before and after the Mall/Center Operating Hours)

Thermostat

Set Points Operating Hours: Cooling 72* / Heating 70* Non-Operating Hours: Cooling 76* / Heating 67* Set to operate hours 1 hour before store open and 1 hour after close

  • Is the thermostat installed and functioning properly? (Set Points set on EnTouch Controls)

HVAC

  • Is the HVAC installed and functioning properly? (Merch Week Filter Change)

  • How is the overall quality of the Mechanical/Electrical?

  • Additional notes for section

Other/Misc.

Final Clean

  • Has the store been final cleaned?

Security Globes

  • Are all 3 security globes installed? (2 Sales/1 Stock)

Fire Extinguisher

  • Are the fire extinguisher (s) mounted?

  • Are the fire extinguishers tagged for the current year?

Misc. Items

  • Have all items been address on the above punch list? If no, explain what section missing.

  • Are the access panels properly located?

Other

  • Did the store receive everything on the fixture truck? If no, what is missing and when should it arrive?

  • Did anything arrive damaged?

  • How is the overall quality of the Other/Misc.?

  • Additional notes for section

Closeout Information

Barriacde

  • Has the barricade/window graphics been removed?

  • If, no when will this occur?

C of O/Mall Walk through

  • Does the store have the Certificate of Occupancy? (CofO)

  • If no, when is the C of O expected?

  • Has Mall Management walked the space and approved the work?

  • If Mall Management has walked the space, did the GC complete their punch list items?

  • If no, when will this occur?

  • Has the Mall removed all kiosks from our storefront? (All should be 15'+ away from store)

  • Has the Mall added us to the Directories? (Coming Soon)

Mood Media

  • Has the Mood Media player been installed?

Tyco/Security System

  • If Tyco is applicable, has the system been installed?

Phone Provider

  • Have the phone lines been run? Do we have dial tone at both cashwrap and manager's desk?

Fortinet/Router

  • Has the Router been delivered and installed?

Contact Information

Francesca's Construction Manager

  • Who is the CM for this location?

General Contractor

  • Who is the General Contractor from this location?

Architect

  • Who is the Architect for this location?

Sign Vendor

  • Who is the Sign Vendor for this location?

  • Attendee to Punch for Francesca's

  • Attendee to Punch for General Contractor

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.