Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Exterior Storefront
Exterior Storefront
-
Keypad/Lock
-
Do you have the location of the key if the Superintendent will not be onsite? Where?
-
Does the store have a Knox Box?
-
Signage
-
Is the signage complete? (Blade/Halo/Vinyls/Awning) <br>If exterior location, is address applicable?
-
Glazing
-
Is the glazing system installed? (Water Tight Seams - Foyer/Sidewalk Slope Away from Entrance)
-
Doors
-
Are the doors complete? (Hardware/Kickplates/Hold Opens/Closers/Check Locks/Weather Stripping/Floor Sweep)
-
Are all functions of the doors working properly?
-
Are the pull handles on all doors?
-
Trim
-
Is the trim at the storefront complete and correct?
-
Finish
-
Is the finish completed to our standards?
-
Lights
-
Are all the lights installed? (Goosenecks/Sconces)
-
Other
-
How is the overall quality of the Exterior Storefront?
-
Additional notes for section
Interior Storefront
-
Displays
-
Are the displays complete and installed?
-
Doors
-
Are the doors complete?
-
Are all functions of the doors working properly?
-
Are the pull handles on all doors?
-
Trim
-
Is the trim complete?
-
Finish
-
Is the finish completed to our standards?
-
Other
-
How is the overall quality of the Interior Storefront?
-
Additional notes for section
Ceiling
-
Lights
-
Are all the track lights installed and correct? (Height/Working)
-
Are the lights directed towards the merchandise? (Criss/Cross Pattern)
-
Are the tracks attached to the drywall/direct to the grid? (Do not hang from tiles)
-
Finish
-
Is the finish completed to our standards?
-
Acoustical Tile/Hard Lid
-
Is the ceiling complete and installed correctly?
-
Other
-
How is the overall quality of the Ceiling?
-
Additional notes for section
Walls
-
Finish
-
Is the finish completed to our standards?
-
Baseboards
-
Have the baseboards been installed?
-
Are the nail holes filled in on baseboards?
-
Other
-
How is the overall quality of the Walls?
-
Additional notes for section
Flooring
-
Wood/VC Plank
-
Has the Wood/VC Plank been installed? (Transition Strips)
-
Finish
-
Is the finish completed to our standards?
-
Other
-
How is the overall quality of the Flooring?
-
Additional notes for section
Cabinets/Fixtures
-
Fixture Layout
-
Provide a Photo of the Most Recent Layout
-
Are the fixtures laid out per plan? If no, is there a particular reason why not and explain?
-
Are the tables laid out per plan? If no, is there a particular reason why not and explain?
-
Shelving
-
Are the mounted shelves sturdy? (Be sure to hang on Shelves)
-
Are the brackets installed correctly?
-
Are the screw heads painted black?
-
Are the metal end caps installed doubled up on all appropriate rods?
-
3FO
-
Is the 3FO mounted securely? (Top and Bottom Shelves)
-
Is there enough separation for the 3FO?
-
4WS
-
Are the shelves installed at 24", 40", 56" and 72" and sturdy?
-
Armoire
-
Are the glass shelves installed in the armoire?
-
Has the cork been removed from the glass shelves?
-
Is the armoire secured to the wall?
-
Are the LED bulbs installed and power hooked up?
-
Are the door/drawers operational?
-
Glass Cabinets
-
Are the glass shelves installed in the glass cabinets?
-
Has the cork been removed from the glass shelves?
-
Are the glass cabinets secured to the wall?
-
Are the LED bulbs installed and power hooked up?
-
Are the door/drawers operational?
-
Cash Wrap
-
Are the cash wraps secured to the floor with 36" separation?
-
Is the glass installed in the center with rubber bumpers?
-
Are the data jacks at the front of the cash wrap? (Towards the inside of the opening.)
-
Have the stub outs been concealed from view of sales area?
-
Have the stereo and speakers been installed and working properly?
-
Are the door/drawers operational?
-
Is the picture fram grid attached above the back CW? (Screwed in at bottom corners)
-
Other
-
How is the overall quality of the Cabinets/Fixtures?
-
Additional notes for section
Dressing Rooms
-
Hardware
-
Is the hardware installed correctly per the most recent fixture manual?
-
Sconces
-
Are the sconces installed and centered above the mirrors?
-
Can Lights
-
Are the can lights installed?
-
Mirrors
-
Are the mirrors caulked?
-
Was the trim installed around the caulking of the mirrors?
-
Purse Hook Panels
-
Are the panels installed at 2', 4' , and 6' to the center of the panels?
-
Were the purse hooks installed outside of the dressing room?
-
Crown/Trim
-
Is everything installed correctly?
-
Baseboards
-
Are all seams caulked?
-
Other
-
How is the overall quality of the Dressing Rooms?
-
Additional notes for section
Stock Room
-
Frosted Door
-
Is the stock room door installed? (Frosted/Plastic Completely Removed)
-
Combo Lock/Passage Handle
-
Is the temporary handle installed? If no, why? (i.e. Code does not allow keypad locks)
-
Rear Door
-
Is there a rear door? If so, is there a doorbell?
-
If so, is there a doorbell?
-
Has the door been weather sealed and sweeps installed?
-
Is the panic push bar operational?
-
Has the peephole been installed?
-
Shelving
-
Is the shelving installed and sturdy? (Plywood Backer)
-
Walls
-
Are the wall finishes completed to our standards?
-
Ceiling
-
Is the ceiling finished to our standard? If no, explain.
-
Floor
-
Is the floor finished to our standards?
-
Water Fountain/Water Cooler
-
If there is a water fountain, is it installed and working properly?
-
Other
-
How is the overall quality of the Stock Room?
-
Additional notes for section
Rest Room
-
Hardware
-
Have all the Restroom hardware been installed? (Mirror/ADA Hardware/Toilet Paper Holder/Paper Towel Holder)
-
Toilet
-
Is the toilet installed and functioning properly?
-
Has the toilet been snaked? (Floor Drain)
-
Is the supply line a steel braided line?
-
Sink
-
Is there hot water?
-
Has the sink been snaked? (Floor Drain)
-
Mopsink
-
If there is a mop sink is it working properly?
-
Restroom Door
-
Is the RR door working and hardware?
-
Walls
-
Are the wall finishes completed to our standards?
-
Ceiling
-
Is the ceiling finished to our standard? If no, explain.
-
Floor
-
Is the floor finished to our standards?
-
Other
-
How is the overall quality of the Rest Room?
-
Additional notes for section
Electrical/Mechanical
-
Lights
-
Are all the lights installed and directed towards the merchandise?
-
Receptacle Covers
-
Are all the covers at the electrical sockets?
-
CrossCom/Cat 5
-
Has CrossCom been onsite and installed the network cables/jacks?
-
Label Electrical Panel
-
Has the electrical panel been labeled?
-
Fascia/Lighting Timer
-
Is the fascia/lighting timer installed and properly set? (1 Hr. before and after the Mall/Center Operating Hours)
-
Thermostat
-
A/C set point 72* during operating hours and 76* during non-operating hours. Set to operating hours 1 hour before store open and 1 hour after close.
-
Heating set point 70* during operating hours and 67* during non-operating hours. Set to operating hours 1 hour before store open and 1 hour after close.
-
Setback override 1 hour at 2 degrees max. Fan set to Auto.
-
Is the thermostat installed and functioning properly? (Set Points set on EnTouch Controls)
-
HVAC
-
Is the HVAC installed and functioning properly? (Merch Week Filter Change)
-
Other
-
How is the overall quality of the Mechanical/Electrical?
-
Additional notes for section
Other/Misc.
-
Final Clean
-
Does the store still need to be final cleaned? (This should be completed prior to Merch Week.)
-
Security Globes
-
Are all 3 security globes installed? (2 Sales/1 Stock)
-
Fire Extinguishers
-
Is/Are the fire extinguisher (s) mounted?
-
Are the Fire Extinguishers tagged for the current year?
-
Misc. Items
-
Have all items been addressed on the above punch list? If no, explain what section is missing.
-
Are the access panels properly located? (Sign/HVAC/Misc)
-
Other
-
Did the store receive everything on the fixture truck? If no, what is missing and when should it arrive?
-
Did anything arrive damaged? (Take Photo)
-
How is the overall quality of the Other/Misc.?
-
Additional notes for section
New Store Specific Information
-
Barricade
-
Has the barricade/window blocks been removed?
-
If no, when will this occur?
-
C of O/Mall Walk Through
-
Does the store have the C of O?
-
If no, when will is the C of O expected?
-
Has the Mall Management walked the space, and approved the work?
-
If no, when will this occur?
-
If Mall Management has walked the space, did the GC complete their punch items? If no, what remains?
-
Has the Mall removed all kiosks from our storefront? (All should be 15'+ away from our store.)
-
Has the Mall added us to the Directories? (Should at least say "Coming Soon")
-
Muzak/Mood Media
-
Has Muzak/Mood Media been installed?
-
Tyco/ADT
-
If Tyco/ADT is applicable, have they installed the system?
-
Lock Smith
-
Has All State Locksmith changed out the locks?
-
If no, when will this occur?
-
Phone Provider
-
Have the phone lines been run? Do we have dial tone at both cashwrap and manager's desk?
-
If no, when will this occur?
-
Megapath
-
Has Megapath delivered the equipment?
-
Has Megapath installed the delivered equipment?
Contact Information
-
francesca's® Construction Contact
-
Who is the Construction Contact for this location? Main Office - (832) 494 - ****
-
General Contractor
-
Who is the General Contractor for this location?
- Lauer - Phil Linneman - (636) 928 - 9784
- RCS - Barry Urbas - (651) 704 - 1707
- Retail - Kyle Kimberlain - (262) 886 - 9800
- Retail - Steve Peterson - (262) 886 - 9800
- StoreCrafters - Joe Silvaggi - (585) 865 - 5350 x106
- Timberwolff - Antonio Carbajal - (909) 919 - 0637
- Vintage - Tyler Amey - (864) 252 - 5099
- TORCOM - Tony Torano - (262) 748 - 7846
- Other
- Lakeview - Amy Powell - (262) 857 - 3336 x252
-
Who is the GC for this location if not listed above? (Company Name, PM Name and Phone Number)
-
Who is the GC Superintendent name and number?
-
Architect
-
Who is the Architect for this location?
-
Who is the Architect for this location if not listed above? (Company Name, PM Name and Phone Number)
-
Sign Vendor
-
Who is the Sign Vendor for this location?
- Anchor - John Van Fossen - (843) 576 - 3253
- Philadelphia - Adrian Corda - (856) 829 - 1460
- North American - Susan Ollan - (888) 660 - 1874
- Wurz - Bob Wurz - (856) 461 - 4397
- AGI - Jon Wolvin - (757) 255 - 8485
- ICON - Ryan Shaw - (847) 631 - 3195
-
Who is the Sign Vendor for this location if not listed above? (Company Name, PM Name and Phone Number)
-
Attendee to Punch for francesca's®
-
Attendee to Punch for General Contractor