Title Page
-
Client
-
Site address
-
EICR Contractor
-
EICR Contractor Engineer
-
Date the works to be audited were completed
-
Works that were completed, to be audited
-
Audit Date
-
Audit conducted by
Remedial/Installation work and Certification accuracy.
-
Are details of the work carried out entered on the certification correctly? (EIC or MWC) To include the selection new, alteration or addition on any EIC.
-
Do the Supply Characteristics and Earthing Arrangements match what is recorded on the certification submitted? (incl. Distributors Facilty/Earth Electrode)
-
Does the main earth conductor size and main protective bonding conductor sizes match what is recorded on the certification submitted?
-
Does the main protective bonding conductor/s connection or continuity test reflect what is recorded on the certification produced? (note services applicable)
-
Was the main earthing conductor/main earthing conductor to the DB/Consumer Unit upgraded as part of remedial work - if so done correctly?
-
Where the main protective bonding conductor/s upgraded/installed as part of the work? If so have they been installed correctly and conductor continuity tests noted ? (list any issues, with photo)
-
Does the Ze and PFC and/or Zdb and Ipf (higher of PEFC or PSSC) match what is recorded on the certification submitted?
-
Maximum demand noted/calculated correctly?
-
Schedule of Inspections on any EIC submitted completed correctly relating to work carried out? (N/A for MWC)
-
Has any replacement Distribution Board or Consumer Unit been installed as per BS 7671:2018+A2:2022 including SPD and, if required, AFDD's? (Include photos)
-
Have any replacement OCPD's been selected and installed correctly?
-
If applicable, have any accessories been replaced correctly? (include photos)
-
If applicable, have any replacement downlights been selected and installed correctly? (i.e fire rated, enclosed connections etc. Include photos)
-
If applicable, Have any bathroom accessories been selected and installed correctly? (i.e Surface mounted IP rated lights. Include photos)
-
If applicable, has any new or replacement wiring been selected and installed correctly? (List circuits affected and details incl presence of fire rated cable supports where required. Include photos)
-
Has all the EICR C1/C2/FI identified required remedial works been completed to BS 7671:2018+A2:2022?
-
If applicable, has all the EICR C3 identified recommended remedial works been completed to BS 7671:2018+A2:2022?
-
Has any further defective parts of the installation been found that can be confirmed as missed from the initial EICR? (List details with photos)
-
On completion of the initial EICR, or after the Distribution Board/Consumer Unit has been replaced, has a BS 7671 compliant Periodic Inspection Test notice been placed at the origin of the installation or at teach DB/Consumer Unit and correctly completed? (Include photos as applicable)
Sample test results and circuit details accuracy. (Mark as N/A tests not part of this audit)
-
Does the Distribution Board or Consumer Unit circuit schedule match the details recorded on the certification submitted?
-
Do all OCPD devices and RCD's (incl RCBO's) have the correct BS EN details, rating and type noted correctly on the certification submitted?
-
Does the Type of Wiring code and Cable Installation Reference Methods match what is recorded on the certification submitted?
-
Do the number of points on a circuit/s match those recorded on the certification submitted? (note which circuit/s sampled)
-
Do the Lighting Circuit/s R1+R2 or R2 sample tests match those recorded on the certification submitted? (note which circuit/s checked, certificate test result and photos)
-
Does the Cooker and/or Hob circuit R1+R2 or R2 sample tests match those recorded on the certification submitted? (Include certificate test result and photo)
-
Do the Shower circuit R1+R2 or R2 sample tests match those recorded on the certification submitted? (if more than one electric shower note which circuit was checked, certificate test result and include photos)
-
Do the Immersion and/or Central Heating circuit R1+R2 or R2 sample tests match those recorded on the certification submitted? (note which circuit checked, certificate test result and photos)
-
Do the Fire detection circuit R1+R2 or R2 sample tests match those recorded on the certification submitted? (note certificate test result and photos)
-
Do the Ring Circuit/s 'end to end' conductor continuity sample tests match those recorded on the certification submitted? (note which circuit/s checked, certificate test result and photos)
-
Do the Ring Circuit/s R1+R2 sample tests match those recorded on the report submitted? (to reflect Figure of 8 test) (Note which circuit/s checked, certificate test result and photos)
-
Do any Radial circuits for socket-outlets R1+R2 sample tests match those recorded on the certification submitted? (note which circuits checked, certificate test result and photos)
-
Do the Insulation resistance sample tests match those recorded on the certification submitted? (note either individual circuits or whole installation/group of circuits as applicable and photos)
-
Do the Zs sample tests match those recorded on the certification submitted? (note which circuits were checked, certificate test result and photos)
-
Does any RCD (incl RCBO) sample tests match those recorded on the certification submitted? (x1 instrument trip test and test button operation, certificate test result and photos)
-
Has any Surge Protection Device fitted been recorded correctly on the certification submitted?
-
Has any AFDD manual test button operation been noted and matching what is recorded on the certification submitted? (if applicable)
-
Do any other circuit/s sample tests match those recorded on the certification submitted? (state circuit/s and tests performed, certificate test result and photos
-
If occupant is present, did the engineer wear PPE and use dust sheets/clean up after work completed? (if debris still evident, please supply photo)
Audit conclusion
-
Is any further action required? (to re-attend site for any reason due to outstanding works from remedial works/EICR or issues that have arisen since)
Additional comments
-
undefined
Signatures
-
Auditor