PROJECT DETAILS
-
Client
-
Project.
-
-
Job Number
EQUIPMENT DETAILES
-
Plant Area
-
Plant Area 2
-
Equipment No
-
Contractor
-
Manufacturer
-
Model
-
Order No
-
Serial No
-
ITP Reference
-
Inspection Engineer (Inspected By)
PRE-INSPECTION REQUIREMENTS
-
1. Place Electrical Permit of Isolation on Linear Screen and Mechanically Isolate all feed lines to screen.
2. Complete and issue FRI XXX, stating direction test of motor checked and correct.
INSPECTION TASKs
-
Inspect gearbox oil level and ensure if is as per manufacture's specification regarding oil level and contents.
-
Inspect around the feed box and ensure that there is no contact between the steelwork and the polyester filter cloth.
-
Photograph of screen clerance.
-
Inspect skirting around feed box and ensure that it is secure.
-
Inspect spray pipes top and bottom and ensure that they are secure.
-
Inspect all pulley bearings for grease and security.
-
Inspect idler rollers for security.
-
Non-Conforming items identified & Segregated
-
Inspect all guards for security.
-
Inspect general area around the linear screen for safe access and any other hazards that are ther.
-
Details of non-completed.
REMARKS AND OBSERVATION
-
Remarks
-
Sketches / Drawings
-
Photo of findings.
INSPECTION STAGE
-
Inspection Status
-
Inspection Engineer Signature
-
Witnessed By
-
Signed On