HAMBRO® JOISTS/GIRDERS - Pre-pouring verification

  • This checklist is provided as a reference tool only to help with installation oh the Hambro® System. Construction drawings (E1J, E2J, etc) ED-D500. CC-D500 and installation manual remain the principal documentation for your project and installation of the Hambro® system should always be done according to those respected documents.

1. Orientation of joists/girders

  • Tag side on the joists/girders should be located on the same side of the bay than on the Hambro® layout drawing.

2. Joists spacing

  • Spacing should be identical to the Hambro® layout drawing. Particular attention should be taken for joists parallel to an edge of slab/cantilever.

  • If impossible to re-create identical spacing due to site conditions, report any discrepancies for engineering review.

3. Eccentricity of Hambro® joist/girder shoes

  • Portion of the joist/girder shoe not bearing completely on the bearing element ( should never be greater than 1/2"/ shoe)

  • Hambro® girder shoe full bearing in both directions, unless noted otherwise on layout drawing.

4. Rollbars (RB)

  • Rollbars vertically locked in place?

  • Note: Watch for handles and brackets of the first rollbars near a bearing element. Make sure they are facing the correct direction for easier stripping after the pour.

5. Shoe & FH/MH fastening

  • All shoes, including girder shoes and FH/MH should be securely fastened to bearing element as per Hambro® IFC drawings.

  • Note: Hambro® joists bearing on concrete/masonry wall do not require to be fastened, unless noted on the Hambro® IFC drawing

6. Header beams

  • Location of header beam as per Hambro® IFC drawing.

  • Header beam is welded/bolted in place, as per Hambro® IFC drawing.

7. Joists elevation

  • All joists leveled, as per requested elevation on Hambro® IFC drawing.

8. Joists rotation/sweep

  • Joists perfectly vertical before pour?

  • Acceptable Sweep of 1/20'-0"

9. Damaged Hambro® joists

  • All damages to the Hambro® joist/girder, of any nature, should be documented and reported

  • Pictures of damages

  • Joist mark(s) and description of damages

10. Temporary bridging

  • Temporary bridging installed as per Hambro® drawing ED-D500

  • Hambro® joists close to edge of slab are laterally supported

11. Plumbing sleeves/wood block-outs

  • Clearance of plumbing sleeves and wood block- outs minimum 6" clear from the center of the Hambro® joists.

  • Note: if the clearance is non-compliant, report immediately this situation for engineering review. Reinforcement may be required.

12. Slab thickness

  • Thickness as per Hambro® IFC drawings?

  • Has a drill inspection been performed?

13. Plywood, wire mesh, rebar etc.

  • Size of wire mesh and quantity of layers, as per Hambro® drawings.

  • Overlap of wire mesh.

  • Wire mesh ties properly at overlap.

  • All additional reinforcing steel (rebar) in place.

  • General aspect of plywood

  • Structural steel connections ( bolts, weld, etc.)

Additional comments

  • Pictures

Signatures

  • Inspected by

  • Reviewed by

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.