Title Page
-
Altrove Stage 6 25277 - Schofields (Slab and Date)
-
Document No.
-
Slab Preparation Inspection (Slab Only)
-
Trades Associated With Report
- Brownies Plumbing
- Status Concrete
-
Conducted on
-
Add location
-
Prepared by
Inspection Items
-
Has the pier inspections past?
-
Has internal drainage been installed as per Hydraulics Plan?
-
Has under slab membrane been installed?
-
Have pest control collars been fitted to internal drainage?
-
Has formwork inspection been passed by the surveyor?
-
Has steel inspection passed?
-
If brick veneer, is the depth of the rebate a minimum of 160mm?
-
If Hebel , is the depth of the rebate 75mm?
-
Are the edge boards installed straight and plumb?
-
Has hot water, air-conditioner and watertank pads been installed as per plan?
-
Has D.E.B stepped a minimum of two courses with a minimum of 1 m between steps?
-
Is the D.E.B as per elevations plan?
-
Add signature