Document No.
-
Audit Title: HB-SUPP-ITP040 Altrove Stage 6 (SANA) 25277 - UNIT Number, DATE & TIME
-
Unit Number Only
-
Conducted on
-
Prepared by
-
Personnel
-
Is brickwork in accordance with elevation plans and plan measurement?
-
Is brick colour consistent?
-
Are bed joints and perpend 10mm in thickness?
-
Has the brickwork been neatly jointed?
-
Are all brick panels straight and plumb?
-
Has the brickwork been left clean and brushed down?
-
Are all brick sills installed as per plan?
-
Do all sills fall away from window with min 3° fall?
-
Are all perpends in alignment from base to top?
-
Are weep holes spaced between every 4th perpend?
-
Are balcony flashing and overflow spitters installed?
-
Do gal lintels/structural steel have 150mm end bearing on brickwork?
-
Are all continuous head flashing installed over the length of lintels?
-
Is horizontally continuous leading flashing installed in maximum 1500mm lengths and joints lapped with a min of 200mm?
-
Has sill flashing been installed tight and positioned one (1) course below bottom of brick sill?
-
Are brick cavities installed at 40mm?
-
Are brick cavities and brick flashing cleaned?
-
Are brick ties positioned every 5th course and no greater than 600mm centres both vertically and horizontally?
-
Has all excess bricks and mortar been removed from scaffold and placed in waste enclosure?
-
Has all mortar been removed from perimeter of slab edge including concrete surfaces?
-
Has house been cleaned of all trade associated waste and placed in waste enclosure?
-
Has house been freed of all food waste, wrapping and placed in the waste enclosure?
-
Add signature