Information
-
Conducted on
-
Prepared by
-
Location
Section 1 - Site Setup and Storage
-
1.1 -Are materials and equipment stacked/stored in a safe manner? No risk of falling materials.
-
1.2 - Have suitable welfare facilities been provided on site for the current and foreseen workforce.
-
1.3 - Are walkways and pedestrian routes maintained in a safe condition?
-
1.4 - Is site accommodation, access and egress and signage appropriate?
-
1.5 - Are all significant risks and impacts identified and controlled?
-
1.6 - Does the site compound have a secure perimeter and Is fencing appropriate for size of the compound?
-
1.7 - Are welfare facilities / Storage Facilities maintained to a suitable standard?
-
1.8 - Is all signage professionally manufactured?
-
1.9 - Has site security been considered and control measures implemented?
-
1.10 - Has the site compound and/or set up been properly organised?
-
1.11- Are there designated secure areas for skips?
-
1.12 - Is there an external site information board displayed and an internal project board?
Section 2 - Public Protection and Community Relations
-
2.1 - Are all significant hazards in areas where the public have access controlled? E.G Access to work Areas and site perimeter.
-
2.2 - Are all risks and impacts identified and controlled?
-
2.3 - Is temporary floor protection adequately managed?
-
2.4 - Is adequate warning signage provided for the public?
-
2.5 - Where existing lighting is obscured/disconnected/removed have alternatives been provided?
-
2.6 - Is segregation of public carried out using suitable pedestrian barriers with tapping rail where applicable?
-
2.7 - Are emissions from processes adequately controlled (noise / dust / fumes)?
Section 3 – Administration and Management (Health and Safety)
-
3.1 - Is the Construction Phase SHE Plan available and regularly reviewed and updated if required?
-
3.2 - Are all works in progress covered by a suitable and sufficient Risk Assessment and Method Statement and evidence that these have been briefed to the workforce?
-
3.3 - Does the site have suitable First Aid cover and complete first aid supplies relevant to works on site with the contents in date?
-
3.4 - Is statutory information displayed on the project board (F10, HSE poster, insurance, policies, nearest hospital and eye clinic)?
-
3.5 - Have all previous Corrective Actions been closed out from previous visits? (GO Visits, Health Checks)
-
3.6 - Have permits to work been used correctly where required and are they recorded on the permit log?
-
3.7 - Have statutory inspections been carried out as required and are they filed, including SHE weekly inspections?
-
3.8 - Is there a process for signing in/out?
-
3.9 - Is there evidence that all people have been inducted on site using the Induction PowerPoint Presentation and site-specific project board?
-
3.10 - Have all relevant bulletins and TBT been briefed?
-
3.11 - Are records of all competences being maintained? E.g. CSCS, Gas Safe
-
3.12 - Are site wide risk assessments completed and required risk assessments in place?
-
3.13 - Does the Site Manager(s) have the necessary competences for operations being undertaken on site?
-
3.14 - Is there a site specific aspects and impacts assessment available?
-
3.15 - Are copies of appropriate licences held on site? E.g. water, waste, ecological, heritage.
-
3.16 - Are records of incidents and complaints maintained? Visits by regulatory agencies recorded and communicated to the SHE Team?
-
3.17 - Is there evidence of Near Misses being reported on site?
-
3.18 - Is there evidence of CM audits being undertaken and communicated to site teams?
Section 4 – Workplace and Housekeeping
-
4.1 - Is the potential of falls from height controlled?
-
4.2 - Are falling objects adequately controlled?
-
4.3 - Are work areas and walkways free from major hazards?
-
4.4 - Are All significant risks controlled?
-
4.5 - Is housekeeping to an adequate standard? Is site free from litter, mud etc.
-
4.6 - Is the interface between different trades managed so as to prevent exposure to risks from others?
-
4.7 - Is the level of lighting adequate for the operation being undertaken inc. Task lighting?
-
4.8 - Have suitable work benches been provided for use of power tools?
-
4.9 - Is site drainage kept free from blockage?
-
4.10 - Is cable management adequate?
Section 5 – Scaffolding
-
5.1 - Is the scaffold free from significant defects? (including ties, tubes and fittings, foundations and boards)?
-
5.2 - Are incomplete sections of scaffold signed?
-
5.3 - Is any area where there is a risk from falling objects closed off?
-
5.4 - Are the design drawings and calculations available for 'design' scaffolds?
-
5.5 - Have scaffolds been erected in accordance with TG20:13 or the design?
-
5.6 - Are scaffolders working to SG4:15? E.g. advanced guardrail and correct fall arrest.
-
5.7 - Is the scaffold handover certificate available, are details correct and is scaffold being used in line with the handover certificate?
-
5.8 - Are test results available for drilled in fixings and calibration certificates available?
-
5.9 - Have inspections been carried out as required?
-
5.10 - Are other significant risks and impacts controlled?
-
5.11 - Is housekeeping during scaffold erection and dismantling managed?
-
5.12 - Has the competency of scaffolders been checked? - copies of CISRS cards must be on site. E.g. design scaffolds supervised by advanced scaffolders.
-
5.13 - If a gin wheel is in use are LOLER certificates available?
-
5.14 - Are all ladders fixed in position and of correct orientation?
-
5.15 - Are brick guards fixed where required?
-
5.16 - Is debris netting and/or monoflex in place where required, and fixed correctly?
-
5.17 - Are all minor risks and impacts controlled?
-
5.18 - Is there evidence that scaffolds are made safe at the end of each working day?
Section 6 - Mobile Towers and Other Access Equipment
-
6.1 - Has the most appropriate form of access equipment been chosen?
-
6.2 - Have overhead obstructions been considered?
-
6.3 - Is all equipment in good order?
-
6.4 - Are scaffold towers erected in accordance with manufacturer’s instructions and are guardrails, toe board in place, are wheels locked. Is bracing required?
-
6.5 - Is the scaffold tower or other equipment sat on a level and stable foundation?
-
6.6 - Are ladders of the correct type / grade and is the use of ladders adequately controlled?
-
6.7 - Are incomplete scaffold towers marked as incomplete?
-
6.8 - Are All significant risks controlled?
-
6.9 - Is equipment being stored correctly when not in use?
-
6.10 - Are those erecting and/or responsible for mobile towers competent ENGIE or PASMA trained?
-
6.11 - Are copies of inspections for all access equipment available?
Section 7 – Powered Access Equipment
-
7.1 - Are certificates of ‘thorough examination’ available on site, and current?
-
7.2 - Are all moving parts and controls for operating guarded?
-
7.3 - Is the equipment in good condition and fit for purpose?
-
7.4 - Is the equipment appropriate for the task?
-
7.5 - Are there overhead services, obstructions? Has an exclusion zone been set up around the equipment?
-
7.6 - Are the operators of scissor and boom type MEWPS clipped in or is there a risk assessment in place to substantiate otherwise?
-
7.7 - Are counterweights for cradles locked in place?
-
7.8 - Is the equipment isolated and the keys removed when left unattended?
-
7.9 - Are all significant risks controlled?
-
7.10 - Is there evidence that pre-use daily and weekly checks on MEWPS, cradles etc. are being carried out?
-
7.11 - Are test results available for drilled in fixings?
-
7.12 - Is there a detailed operators manual available on site?
-
7.13 - Does the equipment have its SWL indicated?
-
7.14 - Are cradle moves being undertaken by competent persons (where required)?
-
7.15 - Are those operating MEWPS, plant etc. competent – IPAF?
-
7.16 - Has safe access into/out of the equipment been considered?
-
7.17 - Is there an appropriate emergency plan in place?
-
7.18 - Have copies of operator’s training/competence been copied into the site file?
-
7.19 - Evidence of familiarity checks for operator?
Section 8 – Temporary Works
-
8.1 - Are detailed designs and drawings available for any temporary works?
-
8.2 - Has a competent person checked the temporary works after construction/erection?
-
8.3 - Has the temporary works been modified/amended since erection without being rechecked?
-
8.4 - Are the works in good order? E.g. Not showing signs of distress and/or excessive deflection.
-
8.5 - Are all significant risks controlled?
-
8.6 - Has a competent person been nominated as the 'temporary works co-ordinator'?
-
8.7 - Is there evidence of regular checks on the temporary works?
-
8.8 - Is a design check appraisal available?
-
8.9 - Have copies of operator’s training/competence been copied into the site file?
-
8.10 - Are copies of qualifications for 'temporary works co-ordinator' maintained within the site file?
Section 9 – Mobile Plant
-
9.1 - Does the operator hold a CPCS Card or equivalent and is it of the correct type?
-
9.2 - Is the plant in good order and suitable for the purpose for which it is provided or used?
-
9.3 - Is the plant maintained so that it remains mechanically sound and are there records available?
-
9.4 - Is the plant stable in use? Is there a safe way to get into and out of the cab and any other parts of the vehicle that need regular access?
-
9.5 - Is the plant being operated in a safe manner? i.e. is the area segregated, hazard light on and banked if required by RA.
-
9.6 - Are vehicle lights, reversing lights, a horn and other warning devices such as rotating beacons or reversing alarms fitted?
-
9.7 - Is the plant fitted with Roll Over Protection System (ROPS) where necessary?
-
9.8 - Are dangerous vehicle parts, such as power take –off, chain drives, exposed hot exhaust pipes appropriately guarded?
-
9.9 - Is the vehicle suitable for any loads carried?
-
9.10 - Is there a Manufacturers Operation Manual available to the Mobile Plant Operator?
-
9.11 - Has security been considered and is the unauthorised use of plant prevented?
-
9.12 - Are all significant hazards controlled?
-
9.13 - Are seat belts fitted and used correctly?
-
9.14 - Are mirrors and or closed circuit TV (CCTV) systems fitted and fit for purpose?
-
9.15 - If used on the road is the vehicle registered etc and operator has a current UK Driving Licence?
-
9.16 - Is equipment Manufacturers tag on machine? E.g Plate containing serial number etc
-
9.17 - Is any towing/quick hitch in good order and spares available? – correct pin?
-
9.18 - Are daily and weekly checks being carried out and recorded?
-
9.19 - Is equipment that may be used for lifting marked with a SWL?
-
9.20 - Is equipment that may be used for lifting thoroughly examined/tested and in date?
Section 10 – General Work Equipment
-
10.1 - Are all safety devices in place and operational?
-
10.2 - Is the equipment being used for the purpose that it was designed?
-
10.3 - Are there specific assessments for noise, dust and vibration with adequate controls in place?
-
10.4 - Are operatives competent to use the equipment?
-
10.5 - Are tools and equipment in good condition?
-
10.6 - Is there evidence that defective equipment is removed from use?
-
10.7 - Are All significant risks controlled?
-
10.8 - Are whip checks fitted to airlines?
-
10.9 - Are test certificates available for specialist equipment?
-
10.10 - If there is a requirement for an exclusion zone has this been established?
-
10.11 - Are maintenance / inspection records available for the equipment?
-
10.12 - Are copies of the training records available in the site file? E.g Abrasive wheels
Section 11 – Lifting
-
11.1 - Are all lifting operations reviewed by a competent person and is there a Lifting Plan available for Cranes /Forklifts etc?
-
11.2 - Are lifting operations adequately supervised and carried out in a safe manner?
-
11.3 - Are test and examination certificates available for all equipment and accessories being used and in date?
-
11.4 - Is all equipment in good visual order?
-
11.5 - Are those involved with planning and executing the lift competent as specified by the lifting plan risk assessment?
-
11.6 - Is the lift area secure? e.g. No lifting over live work areas, pedestrian management or whilst zoning is taking place.
-
11.7 - Are licenses required? e.g. Oversailing work near railway lines, over public walkways, over schools, etc.
-
11.8 - Are sufficient and appropriate insurance cover arranged for all liabilities, agreed and documented between all parties, before any lifting operations commence?
-
11.9 - Is the Safe Working Load (SWL) clearly indicated on all cranes and lifting appliances?
-
11.10 - Are only contract lifts used on site?
-
11.11 - Are all significant risks controlled?
-
11.12 - Are loads stable and secure with no projections and in accordance with the lifting plan?
-
11.13 - Is the lifting plan being followed?
-
11.14 - Are competent slinger / signaller / banksman being used and is there an effective system of communication between the operator and the slinger / signaller / banksman?
-
11.15 - If applicable – Is there a risk assessment in place for an excavator being operated as a crane/hoist and gin wheels?
-
11.16 - Has the correct lifting equipment been selected, used and stored in a safe manner? i.e. using a hoist rather than a gin wheel.
-
11.17 - Is there a “Permit to Lift” in place for all operations involving conventional or mobile cranes?
-
11.18 - Are lifting operations recorded in the Construction Phase SHE Plan?
-
11.19 - Are height restrictors fixed to cranes / excavators that limit the height to which the job will reach and the limit to which a machine can slew?
-
11.20 - Are copies of all certificates and training details maintained in the site file?
-
11.21 - Is there evidence of adequate information, instruction, training and supervision available to all operatives involved in lifting operations?
-
11.22 - Is there evidence that the lifting plan is reviewed in meetings for future adaptions to the plan?
Section 12 – COSHH
-
12.1 - Have all substances which may be hazardous to health been identified, assessed, and use controlled and MSDS available?
-
12.2 - Are all significant risks controlled?
-
12.3 - Are hazardous materials being stored in accordance with MSDSs and COSHH assessments and recorded on register?
-
12.4 - Has COSHH information been briefed out to those affected? - Record required.
-
12.5 - Are control measures identified in COSHH assessment being operated?
-
12.6 - Are the necessary first aid measures in place?
-
12.7 - Is the COSHH storage identified on the site plan with appropriate signage displayed?
-
12.8 - Where substances have WEL/STEL in place is adequate control and surveillance in place?
-
12.9 - Have harmful products been substituted for less harmful products where possibly?
Section 13 – PPE
-
13.1 - Is all PPE identified by Risk and COSHH assessments etc. being provided?
-
13.2 - Is PPE provided of the correct type/grade?
-
13.3 - Is appropriate RPE being utilized and Face fit test certification in place?
-
13.4 - Are All significant risks controlled?
-
13.5 - Is PPE/RPE being used in good order?
-
13.6 - Is PPE/RPE being worn correctly or not at all (multiple failures)?
-
13.7 - Where necessary have operatives been given instruction/training on use of PPE? - Evidence required.
-
13.8 - Does the site have a sufficient supply of replacement PPE?
-
13.9 - Are all but minor misuses of PPE eliminated?
-
13.10 - Signage in place where required?
-
13.11 - Where required, are maintenance records for PPE available?
Section 14 – Manual Handling
-
14.1 - Have all manual handling operations been identified, assessed and managed and control measures briefed out?
-
14.2 - Where mechanical aids been identified within RAMS are they being used?
-
14.3 - Has manual handling training been provided where required? E.g. Manual Handling training (High risk) TBT to cover everything else.
-
14.4 - Are weight of items known?
Section 15 – Noise and Vibration
-
15.1 - Have areas where noise is likely to exceed the Lower Exposure Action Level 80 dB (A) been identified?
-
15.2 - Have hearing protection zones been established for areas where noise exceeds 80 dB (A)?
-
15.3 - Where required has a S61 consent been obtained and is there evidence of monitoring and compliance in accordance with it?
-
15.4 - Have work practices where hand-arm vibration is likely to exceed the daily exposure limit value [5 m/s² A (8)] been identified?
-
15.5 - Have work practices where whole-body vibration is likely to exceed the daily exposure limit value [1.15 m/s² A (8)] been identified?
-
15.6 - Are All significant risks controlled?
-
15.7 - Has noise above 80 dB (A) been controlled at source where possible?
-
15.8 - Have others who may be affected by the noise been considered and consulted?
-
15.9 - Does the site or task have working hour restrictions and are these complied with?
-
15.10 - Is there adequate signage for hearing protection zones 85dB (A) and above?
-
15.11 - Has information on hearing protection zones been briefed out? - Evidence required.
-
15.12 - Has hearing protection been assessed to ensure compliance with other PPE?
-
15.13 - Has a risk assessment been carried out for vibrating equipment which includes a soundly based estimate of the employees’ exposure to vibration?
-
15.14 - Have all ENGIE Regeneration employees and site operatives been made aware of the risks and control measures in place for Noise and Vibration?
-
15.15 - Are hearing protection zones identified on the site plan?
Section 16 – Fire Prevention
-
16.1 - Are all potential sources of ignition, including waste and fuel identified, stored and controlled adequately??
-
16.2 - Is the site operating a 'Hot Works' permit system and are the controls detailed within the permit being complied with?
-
16.3 - Has the site developed a written fire plan, drawn fire plan and an associated risk assessment for all work areas and is it sufficient for the work place?
-
16.4 - Are all significant risks controlled?
-
16.5 - Is there suitable means of escape and are they kept clear?
-
16.6 - Are fire extinguishers suitable for the types of fire likely to be encountered?
-
16.7 - Is there suitable means of warning and an interlinked fire alarm where required?
-
16.8 - Are fire points established and maintained?
-
16.9 - Are fire extinguishers serviceable and maintenance records available?
-
16.10 - Is there evidence that the fire plan is briefed out and/or included in the induction?
-
16.11 - Is there a nominated and trained Fire Marshal(s)?
-
16.12 - Where relevant, emergency arrangements give consideration to other occupiers/users?
-
16.13 - Fire Drill held in accordance with the site fire plan?
-
16.14 - Is the drawn fire plan displayed on the project board?
Section 17 – Excavations
-
17.1 - Has the RAMS for excavation works been issued and relevant for Task?
-
17.2 - Has service Drawings been obtained or PAS 128 survey been carried out?
-
17.3 - Has a CAT and Genny been used to establish underground services on site and calibration certificates available?
-
17.4 - Has training / Competency been obtained for Use of Cat and Genny?
-
17.5 - Is there a permit to dig system in place?
-
17.6 -Are excavations properly supported?
-
17.7 - Is the excavation guarded to prevent people, material and plant falling in?
-
17.8 - Have stop blocks been provided for plant?
-
17.9 - Are all significant risks controlled?
-
17.10 - Has a safe means of access/egress been provided for the excavation?
-
17.11 - Is there an emergency procedure in place for excavations?
-
17.12 - Is spoil stored at a safe distance from the sides of the excavation?
-
17-13 - Has undermining of nearby structures been considered?
-
17.14 - If other services have been exposed are they adequately protected and supported?
-
17.15 - Record of inspections for the excavation available on site?
Section 18 – Asbestos Management
-
18.1 - Is there asbestos information available and is it adequate for the works being undertaken?
-
18.2 - Are works in progress covered by a risk assessment and/or plan of work and is the work correctly described and categorised?
-
18.3 - Is non-licensable 'minor' work being undertaken by competent and trained personnel with the required insurances and approved by Regional SHEQ Manager?
-
18.4 - Are licensable asbestos works being undertaken by a licensed company?
-
18.5 - Has the HSE been notified using the ASB5 Notification form?
-
18.6- Is the potential for accidental release of asbestos fibres identified and controlled?
-
18.7 - Are all significant risks identified?
-
18.8 - Has all asbestos information been communicated to relevant personnel?
-
18.9 - Is there evidence that face fit testing has been carried out for the RPE being used with asbestos?
-
18.10 - Are occupational health checks being carried out for Asbestos removal operatives?
-
18.11 - Has a general briefing / toolbox talk on asbestos been carried out?
-
18.12 - Are site managers carrying out Asbestos Checklists?
-
18.13 - Has the Site Manager got access to the Emergency Release asbestos procedure and is it understood?
-
18.14 - Relevant flow charts extracted from the asbestos standards are displayed on the site notice boards?
Section 19 – Gas Safety
-
19.1 - Have gas appliances and flues been surveyed, identified, tested and documented? (smoke testing)
-
19.2 - Have works that impact on gas appliances and flues been identified? (e.g. changes to ventilation during window replacement and working within 1m of a live flue)
-
19.3 - Are all ‘gas works’ undertaken by Gas Safe registered persons? (excludes bayonet fittings)
-
19.4 - Is there a gas flue ‘Permit to Work’ system in use for all works that impact on live gas flues, and is the system correctly implemented?
-
19.5 - Are all significant risks posed by gas identified?
-
19.6 - Is information on GAS SAFE registered persons used on site recorded and easily accessible?
-
19.7 - Has the Site Manager undertaken the ENGIE Gas Safety training?
-
19.8 - Are specific risk assessments and method statements available for works which may impact on gas appliances and flues, and are works undertaken in accordance with the planned method of work?
-
19.9 - Is Stars and Stripes TBT delivered to all personnel?
-
19.10 - Is commissioning paperwork available for all new live appliances?
-
19.11 - Have those disconnecting/reconnecting bayonet fittings been trained and records kept? Do they have access to leak detection spray?
-
19.12 - Are the Gas procedures available on site?
-
19.13 - Are flue tags in use?
-
19.14 - Are GAS SAFE registrations verified?
-
19.15 - Does the site paperwork link an individual GAS SAFE registered person back to individual items of work?
Section 20 – Electrical Safety
-
20.1 -Have RAMS been issued and are relevant for Electrical works on site?
-
20.2 - Is the need for 'live' working eliminated?
-
20.3 - Are works in the vicinity of live circuits adequately controlled? (e.g. safe isolation).
-
20.4 - Has the risk from overhead services or live conductors been identified, and are suitable control measures in place?
-
20.5 - Are all conductors properly insulated where required or 'permit to work' in place?
-
20.6 - Are statutory undertaker’s plans available on site (where relevant)?
-
20.7 - Are all significant risks controlled?
-
20.8 - Are test certificates for temporary supplies available?
-
20.9 - Are all site supplies certified with no visual defects?
-
20.10 - Are all electrical appliances (including extension cables) PAT tested and in date?
Section 21 – Traffic Management
-
21.1 - Is there a Traffic Management Plan (written and drawn) in place, implemented and displayed with corresponding risk assessment?
-
21.2 - Is the need for vehicles to reverse either eliminated or managed?
-
21.3 - Are transport and pedestrian routes segregated / protected and signposted?
-
21.4 - Are risks to the public adequately controlled?
-
21.5 - Are all significant risks and impacts controlled?
-
21.6 - Are Internal / external roads maintained in a clean condition?
-
21.7 - Are clearly identified and trained Vehicle Banksmen used for access / egress to site (where appropriate)?
-
21.8 - Are there wheel cleaning facilities available on site where applicable?
-
21.9 - Are deliveries planned to avoid congestion at site?
-
21.10 - Are vehicles maintained in a clean and road worthy condition?
Section 22 – Ecology, Archaeology and Heritage
-
22.1 - Is a bio diversity action plan completed for the site? (where required)
-
22.2 - Have buildings likely to contain protected bats, nesting birds or other species been surveyed by the Client?
-
22.3 - Have Tree Preservation Orders (TPO) or Client protected trees been identified?
-
22.4 - Have listed buildings been identified and planning restrictions communicated?
-
22.5 - Are areas likely to contain archaeological resources been surveyed by the Client?
-
22.6 - Have areas with noxious and / or invasive plants been identified?
-
22.7 - Are all significant impacts controlled?
-
22.8 - Has a mitigation programme for protected species been developed?
Section 23 – Water Resource Management
-
23.1 - Have water discharge points been identified and appropriate license in place?
-
23.2 - Is bulk storage of fuel in accordance with oil storage regs?
-
23.3 - Are all significant impacts controlled?
-
23.4 - Is Oil / fuel drums maintained in bunded areas?
-
23.5 - Is drainage from the office / canteen facilities to mains sewer or septic tank?
-
23.6 - Is concrete wash-out collected in appropriate container (no discharge to ground)?
-
23.7 - Is there a drainage plan on site (where appropriate)?
-
23.8 - Is the drainage system maintained and free from blockages?
-
23.9 - Are bunded areas free from rainwater, litter, oil, fuel etc.?
-
23.10 - Is there evidence of spill clean up training delivered to site personnel, where applicable and spill kit available?
Section 24 – Waste Management & Carbon
-
24.1 - Are Waste Transfer Notes and Consignment Notes held on site for all waste movements and are compliant with correct details?
-
24.2 - Is all waste stored and segregated where possible with physical barriers and signed?
-
24.3 - Are all significant impacts controlled?
-
24.4 - Have all waste streams been identified and suitable storage obtained?
-
24.5 - Have all hazardous waste streams been identified and suitable storage obtained?
-
24.6 - Is there evidence of Internal waste transfer notes and are they completed properly for ENGIE and Subcontractors (where required)?
-
24.7 - Is there a copy of ENGIE/Subcontractors Waste Carriers Licence in relevant ENGIE/Subcontractors vehicles?
-
24.8 - Where possible energy usage (electricity / gas / other site fuel) is monitored and recorded (monthly) on the online recording system.
-
Completed By -
-
Received By -