Information

  • Project

  • Conducted on

  • Prepared by

Fall Protection

Fall Protection

  • Fall protection when at 6' or above

  • Rebar - protected and reinforced steel rebar caps

  • Perimeter guardrail in place (42", 21" & toeboards)

  • Perimeter guardrails - using cables - must be >= 1/4" & flagged every 6'

  • Scissor lift gate closed or chain attached

  • Boom lift operators wearing PFA & tied-off

  • Roofers, masons or steel erectors using proper fall protection

  • Hole covers secured and labeled

  • Stairways free of materials and debris

Scaffolds

Scaffolds

  • More 4:1 - tied to structure

  • Scaffold grade planks (no 2x4s, etc)

  • Planks - minimum 12" overlap or fastened down

  • Tight floors (no more than 1" between planks)

  • Toprails, midrails & toeboards in place

  • Baseplates and mudsills in place

  • Access - ladders being used

  • Mobile - casters are locked when in use

Electrical

Electrical

  • GFCI's in use

  • Extension cords okay

  • Power tools with proper grounds (unless double insulated)

  • Faceplates on all energized outlets and switches

  • Covers on panel boxes or rooms labeled and locked

  • Breakers labeled and missing breakers covered

Personal Protective Equipment

Personal Protective Equipment

  • Wearing hard hats at all times

  • Wearing safety glasses (when necessary)

  • Wearing construction boots at all times

  • Wearing full body harness (when necessary)

  • Wearing hearing protection (when necessary)

  • Wearing gloves (when necessary)

  • Wearing respirator (when necessary)

Ladders

Ladders

  • Step ladders - opened fully when used

  • Step ladders - can't stand on the 2nd to last step up or top

  • Extension ladders - properly sloped (4:1), extend 3' at top & tied at top

  • Metal ladders not used near power lines

  • Ladder corrals - built at top (around ladder)

Heavy Equipment & Vehicles

Heavy Equipment & Vehicles

  • Audible (noise arrestors) work - backing up

  • No unsafe hauling of people or materials

Excavations

Excavations

  • Utilities located & marked

  • 4' or more - ladder must be within 25' of each worker

  • 4' or more - ladder must extend 3' above ground

  • 5' or more - must slope, shore or use trench box

  • If sloped - is it correct (A 3/4:1, B 1:1, C 1 1/2:1)

  • If using trench box - >18" above grade & <2' from bottom

  • Adjacent structures - protect & support (if needed)

  • All materials stored 2' or more from edge

  • If left open over night - barricaded properly

Hand & Power Tools

Hand & Power Tools

  • Right tool for the right job

  • Prompt repair of split or cracked wooden handles

  • Power tools must have proper grounds

  • Power tools - all mechanical safeguards in place

Emergency Procedures

Emergency Procedures

  • Emergency numbers posted at phone

  • Nearest emergency facility (maps & directions)

  • First-aid kit okay

Barricades, Signs & Signals

Barricades, Signs & Signals

  • Elevator shafts barricaded (all levels)

  • OSHA & state postings in trailer

  • Job signs up (no trespassing, danger, do not enter)

Stairs & Walkways

Stairs & Walkways

  • Steps & floorboards okay

  • Metal pan stairs are filled in or barricaded off

  • 4 or more risers or 30" or more = handrail

  • 19+" in a break in elevation = need to have something

  • Clear of dirt, oil, ice, snow, mud, trash, etc.

Welding & Cutting

Welding & Cutting

  • Torch, hoses & gauges okay

  • Cylinders in use are secured and upright

  • Cylinders in storage (secured upright & separated by 20' or barrier)

  • Extinguisher and/or water hose a available

Fire Protection & Prevention

Fire Protection & Prevention

  • Fire extinguishers

  • Flammables stored away from buildings

  • Containers are clearly identified with warning signs

  • No smoking, burning, etc. around flammables

  • Flammable - no more than 25 gallons per room

Crane, Derrick, Hoist & Elevator

Crane, Derrick, Hoist & Elevator

  • Crane has annual inspection - within 1 year

  • Qualified operators

  • Power lines cleared, deactivated or sleeved

  • Horn works

  • Outriggers , tracks, cribbing is on solid ground

  • Spring-loaded safety latch on crane hook

  • Rigging okay (slings, checkers, chains, shackles)

  • Workers kept clear

  • Swing radius barricaded

Powder Actuated Tools

Powder Actuated Tools

  • Qualified operators

  • Hearing protection & safety glasses in use

  • Tools & loads are protected from unauthorized use

  • No leaving of tools & loads unattended

  • Signs posted in work areas to warn others

Hazard Communication

Hazard Communication

  • MSDS in trailer

  • All containers marked & labeled

Housekeeping

Housekeeping

  • Passageways & aisles - clean & clear

  • Materials stored away from edges - neatly piled

  • Nails are removed or bent down

  • Dumpsters & trashcans are provided daily

Other Safety Violations

Other Safety Violations

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.