Title Page
-
Conducted on
-
Prepared by
-
Location
High Rise Post Audit
-
Name of engineer being Audited
-
Address details
-
Building Owner
-
LDZ
-
Description of building owner
- I&C Organisation
- Local Authority
- Housing Association
- Private Landlord & Tenants
- Individually owned/Private
- Unknown
-
Type of building use
-
Estimated year of construction
-
Number of storeys
-
Number of flats per storey
-
Total number of flats
-
Have previous corrosion records been identified
General
-
Is there a cellar basement or underground garage
-
Has the engineer obtained an asbestos report
-
Building construction type
-
Meter positions and configurations
-
Diagram displaying current riser network available
Supply Pipe Details
-
Is the supply pipe entry point correctly identified?
-
Has the supply pipe material been captured correctly
-
Has the supply pipe diameter been identified correctly
-
Is there cathodic protection present and what is its condition ?
-
Is surveyed supply pipe distinguishable as Gas Pipework?
-
EP : Entry point has adequate access for inspection maintenance and Repair
-
EP: Entry point does not compromise building fire resistance
-
EP: Entry point does not compromise safe egress in an emergency
-
Insulation joint installed correctly
PIV Details
-
Has the pipeline isolation valve (PIV ) been located
-
PIV location correct
-
PIV location correctly referencing supply
-
Has DR4 process been raised
IIV Detail
-
Is an inlet isolation valve (IIV) Present and locatable
-
Has the location of the IIV been captured correctly?<br>
-
Is the IIV accessible for maintenance?
-
IIV, Has the IIV Been clearly identified as a gas valve
-
IIV , Is the IIV Accessible to members of the public ?
-
IIV ; If IIV is not located internally is it in a locked compartment at point where the pipeline enters the building
-
IIV : If IIV is located in a locked compartment is there advice where the keys may be found
-
IIV : Have permanent identification and gas escape notices been posted on or near the IIV
-
Has the handle been removed from the IIV
Riser Details
-
Number of external Risers
-
Number of internal Risers
-
EFV Installed on Riser
-
RIV: Has aRIV/ BIV been fitted to the maintenance and isolation of individual Risers
-
Riser Pipe Length
-
Has the Riser Pipe diameter been captured correctly
-
Has the Riser Pipe material been captured correctly
-
Has the Base of the Riser been checked
-
Is there evidence of any external building modifications that could affect the safety of the network pipe work
-
Is the Riser referenced to correct supply pipe
-
Has the percentage of the Riser visible been captured correctly
-
Can the base of the Riser be checked
-
Has corrosion be been identified on the Riser
-
Has the Riser location been correctly identified
-
Is the number of visible repairs correct
-
If so are they still fit for purpose
-
Is the Riser supported every 3mtr for horizontal
-
Is the Riser supported 2.5 mtr for vertical
-
After leakage has the engineer found and recorded locations
-
Has the leak been repaired and captured