Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Region

  • Contractor/s

  • Job Description

  • Date

  • Time

1. Site Risk Management

  • Is a relevant SWMS available and a Site Risk Assessment (JSA) completed for the work?

  • Has the JSA been signed and dated daily and the SWMS identified?

  • Overall, is the JSA adequate for the worksite?

2. Personnel Protective Equipment

  • Is approved PPE clothing worn and is wrist to ankle coverage maintained?

  • Is approved safety footwear worn?

  • Is other appropriate PPE utilised and in good condition? (e.g. hard hats, hearing and eye protection)?

3. Traffic and Pedestrian Management

  • Has the appropriate Traffic and Pedestrian Management Plan been identified, and does it meet all requirements?

  • Does the actual traffic/pedestrian layout reflect the Traffic/Pedestrian Management Plan?

  • Is pedestrian traffic safely controlled through the worksite?

  • Are traffic signs and devices legible and undamaged?

4. Forms/Documentation

  • Does the job file contain an Application for EAP / HV Suppression?

  • Does the job file contain switching instructions?

  • Does the job file contain clearance documents?

  • Are all appropriate forms available? (e.g. EAP, SFT, PTW)

  • Are required reference materials available? (Operations Manual, Switchgear Operating Manual, Green Book)

5. Skills and Competency

  • Do all personnel have Passports on site?

  • Is all training and are all authorisations current for the functional role of the Passport holder?

  • Are all personnel licensed/registered for their functional role?

  • Are apprentices adequately supervised?

6. Vehicles/Plant

  • Are all plant operators licensed as required?

  • Are logbooks available for all plant on site and have they been maintained appropriately?

  • Are EWPs within the electrical test due date?

  • Are EWPs within the weight test due date?

  • Have pre-start checklists been completed?

  • Are all vehicles on site registered?

  • Are all vehicles/plant within their service range?

  • What is the general condition of the vehicles/plant (cleanliness)?

  • Is all equipment carried on vehicles adequately secured?

  • Is there appropriate identification on contractor vehicles?

7. First Aid

  • Is there an intact First Aid kit?

  • Is the kits location marked on the vehicle?

  • Do the contents appear to be complete, in good condition and within expiry dates

8. Tools and Equipment: Testing and Condition

  • Are all electrical tools and PETE items within their test date range?

  • Is all electrical test and measurement equipment in test date?

  • Has any test equipment been modified? (e.g. probes extended)

  • Are gloves and sleeves in test date?

  • Are HV operating gloves, sleeves and mats in test date?

  • Are HV mats and covers in test date?

  • Are HV sticks in test date?

  • Are the gas bottles within expiry date and stored appropriately?

9. Environment and Hazardous Goods

  • Are environmental risks identified and controlled in the JSA?

  • Are there any control measures to manage spills and leaks? (e.g. spill kit)

  • Is Bushfire mitigation equipment available? (e.g. knapsack, rakes permit)

10. Working at Heights

  • Is the correct fall prevention equipment used?

  • Are harnesses, pole belts, lanyards and any other fall prevention equipment in test date?

  • Are Rescue Kits available, in test and in position?

  • Are ladders in use in an adequate condition?

  • Are ladders in use setup correctly?

11. Worksite/Work Practices

  • Have the required communications been made with Network Control prior to and during switching operations?

  • Has the station master auto reclose been suppressed (where available)?

  • Are Safe Approach Distances maintained?

  • Is the site tidy with no obvious tripping or other hazards?

  • Adequate cover utilised? (e.g. mats, LV covers, HV covers, etc.)

  • Plant and equipment appropriately set up? (e.g. trucks earthed / bonded, outriggers in use, etc.)

  • Are all isolation points tagged and locked, where applicable?

  • Are appropriate operational Earths/Bonders attached in correct locations and in an adequate condition?

  • Was the condition of switchgear inspected before & after operation?

  • Has safe to earth test been performed (modiewark)?

  • Are adequate operational and work party earths/bonders in place

  • Has the Operator discussed with the Recipient in Charge the access required for work to be done?

  • Does the Access Permit cover the required access to safely carry out the work?

  • Has the Access Authority been filled out correctly?

  • Has the Operator adequately explained to the RIC & Work Party the minimum requirements? (e.g. Apparatus covered, Isolation points, Earths, Nearest Live Apparatus)

  • Has the Work Party been asked the four questions required at issue.

  • Has the Access Authority issue details been advised to the Control Room?

  • Has the switching and the Access Authority issue been recorded in the station?

  • Has the Operator checked the network fit for service prior to restoring supply?

  • Comments

  • Overall Audit Rating

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.