Title Page
-
Conducted on
-
Prepared by
-
Location
-
Number of stories:
-
Registration Number:
-
Job Number:
1: General Tasks
-
1.1 Verify embedded fall-arresting systems have been inspected as it relates to use for concrete installation. Shop drawings. Contractor maintenance log.
-
1.2 Maintain a concrete safety log book which lists activities that shall be conducted in coordination with the site safety manager or coordinator
-
1.3 Adequate lighting
-
1.4 Adequate ventilation
-
1.5 Housekeeping
-
1.6 Pre-Storm planning, high winds
-
1.7 Concrete washout water, collection, containment, disposal
-
1.8 Underpinning sequence/detail drawings on site
2: Site Safety Provisions
-
2.1 Monitor that required fall protection systems in place
-
2.2 Monitor workers using required fall protection systems
-
2.3 Monitor hoisting and rigging operations performedin a safe manner
-
2.4 Extra shores or other material and equipment are available in the event of an emergency
-
2.5 Building materials properly piled and tied or contained
-
2.6 Emergency egress maintained
-
2.7 Escape hatches
-
2.8 Handrails, mid-rails and kickboards in place and secure
-
2.9 Formwork erection and stripping signage clearly displayed
-
2.10 Rebar ends capped to prevent impaling.
3: Installation of Formwork
-
3.1 Verify formwork drawings are available. Including shores, re-shores, foundations
-
3.2 Verify formwork drawings are signed and sealed when required by Code
-
3.3 Verify existing structure adjacent to concrete placement has been inspected and evaluated by a registered design professional prior to use as a form. Design drawings prepared
-
3.4 Verify formwork inspected by a competent person and shores are installed as per shop drawings
-
3.5 Verify visual observations of formwork were conducted by formwork designer at the minimum intervals
-
3.6 Verify any formwork discrepancies have been resolved
-
3.7 Unsafe conditions; notify contractor; contact DOB if required
-
3.8 Monitor the required guardrail systems are in place on the forming and placement floors
-
3.9 Ramps, runways and platforms comply with 3315. Designed by qualified person when buggies used
-
3.10 Inspection of concrete formwork by Concrete Safety Manager
4: Placement of Reinforcement
-
4.1 Verify required shop drawings are available on site
-
4.2 Monitor that the workers performing reinforcement bending, cutting, welding and reinforcement placement operations on the working deck are working in a safe manner
-
4.3 Verify reinforcement placement operations are performed in a safe manner
-
4.4 Verify concrete special inspector inspected and signed-off on final reinforcement placement
5: Placement of Concrete
-
5.1 Verify concrete special inspector is present for concrete placement.
-
5.2 Verify DOB licensed concrete testing lab is present to sample and test.
-
5.3 Pumping operations.
-
5.4 Verify pump operator and placement crew have participated in a pre-planning meeting for pumping operations. Verify pre-planning meeting for concrete pump operations occur at initial start-up of concrete pumping operations.
-
5.4.1 For concrete pumping operations which involve lubricating grout (e.g. concrete pumped though a placement boom).
-
5.4.1.2 Verify the contractor supplied sufficient grout discharge boxes on-site to receive 100% of the volume of the lubricating grout actually placed in the boom (and hoses, etc.), regardless of the volume indicated on delivery ticket(s).
-
5.4.1.3 Verify the contractor provided the special inspector of the concrete pour with sufficient notice
-
5.4.1.4 Confirm the special inspector is on site to perform the required special inspections
-
5.4.1.5 Confirm that the special inspector has observed the concrete exiting the hose and that he has identified it as concrete exhibiting a uniform matrix of aggregate before commencement of placement of the structure
-
5.5 Verify pump equipment has been inspected
-
5.6 Verify hoses and connections have been inspected
-
5.7 Monitor pumping operations performed in a safe manner
-
5.8 Monitor concrete buckets, hoppers, chutes and buggies are inspected, cleaned and in proper working order
-
5.9 Monitor concrete placement is performed in a safe manner
-
5.10 Monitor power buggies operated in a safe manner
-
5.11 Monitor formwork is inspected during concrete placement for potential problems
-
5.12 Verify the designated signalmen are in place when a crane is being used for lifting
-
5.13 Cold weather requirements
-
5.14 Hot weather requirements
-
5.15 Verify rate of placement not exceeded per drawings
6: Stripping Operations
-
6.1 Monitor that the horizontal netting conforms to Code before commencing stripping operations
-
6.2 Verify formwork removal procedure
-
6.3 Monitor that in-place concrete strength has been evaluated and accepted in accordance with removal schedule
-
6.4 Verify structural members have acquired sufficient strength to safely support their own weight and external loads
-
6.5 Monitor stripping operations are performed in a safe manner
-
6.6 Debris contained and removed at reasonable intervals
-
6.7 Stripping not performed more than three stories below the story being formed
-
6.8 Special considerations for pre-stressed members
7: Reshoring Operations
-
7.1 Verify reshoring plan is available
-
7.2 Monitor re-shores within 10 feet of building edge are secured, banded and tied to the structure
-
7.3 Monitor wedges are not used for reshores within 10 feetof building edge
-
7.4 Monitor appropriate number of floors have been reshored.
-
7.5 Verify reshores were inspected by competent person designated by the contractor
-
7.6 Verify visual observations of formwork were conducted by formwork designer at the minimum intervals
-
7.7 Stresses. Ensure shores not located improperly causing stress reversals or inducing tension at unreinforced portion of structural member(s)
-
7.8 Reshores perpendicular to surface they are supporting
-
7.9 Reshores braced and plumb
-
7.9.1 Were any re-shores removed from the building that were reinforcing structural member(s) throughout the day
8: Material Handling
-
8.1 Monitor safe handling of shores, reshores, formwork and reinforcement
-
8.2 Monitor proper storage of shores, reshores, formwork and reinforcement on working floors
-
8.3 Monitor floors not overloaded by excessive storage
-
8.4 Monitor fall protection methods employed at edges left exposed for hoisting are in place
Miscellaneous
-
PSI:
-
Pour Location:
-
Total Yards Poured:
-
Weather Conditions:
-
Manpower on site:
-
Has the Pre-Lift Load insection been Verified?
-
Has the Daily Pre-Shift Meetings been completed in accordance with 3301.12.1?
-
Has the Covid-19 Pretask Plan/JHA/Daily Sign In check sheet been reviewed and signed with all workers?
-
Any additional issues
-
Comments:
Signature
-
Concrete Safety Manager