Required Evolution Remodel Items
Building Painting

Paint Evolution color scheme - Heartthrob SW 6866. Mocha SW 6067. Sand trap SW 6066. Before painting building please contact your Development Manager.

Repaint roof caps Mocha SW 6067.

Remove red LED light strips on parapet wall. Patch and paint wall penetrations. May require a new stucco coat to cover patched areas.

Entry tower elements at main entry to the restaurant

Add entry tower at building entry vestibule. Tie back to the parapet or mansard roof for structural support. Lower tower Brevity Brown SW 6068. Big tower French Roast SW 6069.

Install flat entry awning with up flood light and down light (if straight entry).

Install Breakfast/Lunch/Dinner panel.

Exterior lighting

Paint light post if they were painted red or green previously.

Replace lights under soffit

Replace light bulbs over mansard roof

Remove any existing lights not needed.

Roof

Replace existing mansard roof material (shingle, tile or metal) with new sand-colored standing seam roof. (mansard building). Contact Development Manager for color match.

Replace gutter around mansard roof.

Parking Lot/Sidewalk

Patch damaged areas of parking lot

Seal parking lot

Stripe parking lot

Paint wheel stops/curbs

Power wash the sidewalks around the building.

Paint sidewalks if previously painted.

Exterior Signage

Install 7’ diameter round Huddle House logo sign on tower.

Replace old Huddle House block letter channel letter signs with new script logo. Allowable size to be determined by sign vendor. Signs on the mansard roof should be mounted on a raceway painted the same color as the metal roof color.

Replace pylon sign faces with new script logo faces.

Replace light bulbs in pylon sign

Paint existing sign pole and sign cabinets black.

Install reader board

Install new awnings over windows

Install feature panels with lights or awnings on the side of the building (optional)

Trash enclosure

Paint outside and inside of dumpster enclosure mocha SW6067

Repair dumpster enclosure gates

Entry Vestibule

Walls - Install new Marlite Laredo Oak wainscot and Marlite spec chair rail. Stain formula. 1/2 Sher-wood deep cherry base S64 R52 and 1/2 Minwax ebony 2718

Walls- install Artizan FRP #194 Cody Marlite paneling above chair rail.

Ceiling - Install new taupe ceiling tiles. Armstrong Haze Cirrus - HumiGuard Plus

Ceiling- Replace ceiling grid with Armstrong haze ceiling grid

Ceiling - Paint ceiling grid. Contact DM for spec.

Doors- Fix entry doors to work properly.

Doors- Replace door handles and push bars.

Lighting - Remove 2x4 fluorescent fixtures and replace with recessed can fixtures.

Dining Room

Dining Room Walls- Install new Marlite Laredo Oak wainscot 3ft high
and Marlite spec chair rail.

Dining Room Walls- Install Oak window sills. Stain formula. 1/2 Sher-wood deep cherry base S64 R52 and 1/2 Minwax ebony 2718

Dining Room Walls - Install gold/brown Marlite wall covering above chair rail

Dining Room Walls- Drywall existing soffit and paint Fine wine SW 6307

Dining Room Ceiling - Install new taupe ceiling tiles in the dining area. Armstrong Haze Cirrus- HumiGuard Plus

Dining Room Ceiling - Replace with new Armstrong Haze ceiling grid.

Dining room ceiling - Paint existing grid. Contact DM for spec

Dining room ceiling - Paint speakers to match ceiling.

Dining room ceiling - install new HVAC diffusers.

How many HVAC diffusers are needed?

Dining Room Lighting - Replace pendant lights over all booths along exterior walls. Cree lighting F2

How many booth pendants are needed?

Dining Room Lighting - Remove 2x4 fluorescent fixtures in dining room and replace with recessed can fixtures. Lighting should be place with 6ft between fixtures. 3 can lights should be placed over bar and a can light should be place above each interior seat. Cree lighting Type B

How many recessed cans are needed? (Typically space 5-6 tiles apart)

Dining Room Lighting- install new exit lights

How many exit lights are needed?

Exit Door and Frame - Paint exit door and frame. Ivoire SW6127 oil based

Dining Room Flooring - Typically will remain as-is. Replace with Evolution spec tile, if needed.

Seating- Select appropriate option

24" seat backs
42"seat backs
48" seat backs
59" seat backs
66" seat backs
71" seat backs

Note any additional seat backs needed.

Replace table tops

24"x24"Table Top
24"x27"Table Top
24"x30"Table Top
24"X42"Table Top
27"X42"Table Top
30"x42"Table Top
24"x47"Table Top
27"x47"Table Top
30"x47"Table Top
24"x59"Table Top
27"x59"Table Top
30"x59"Table Top
Angled Top 27" wide 42" on right 59" on left
Angled Top 27" wide 59" on right 42"" on left
Angled Top 30" wide 42" on right 59" on left
Angled Top 30" wide 59" on right 42" on left
Angled Top 27" wide 47" on right 59" on left
Angled Top 27" wide 59"on right 47" on left
Angled Top 30" wide 47"on right 59" on left
Angled Top 30" wide 59"on right 47"on left

Note additional Table Tops

Seating- Repair and Paint rusted booth frames and table bases

Replace bar top

Bar Top length

Build new bar wall and foot rest.

Re-cover bar with Marlite Laredo oak paneling.

Repair foot rest and cover with runner vinyl black stair tread. Located at Home Depot, product number 0000-140-877.

Replace bar wall with 54" knee wall

Replace Bar stool seats

How many bar seats are needed?

Swivel option

Replace bar stool posts

How many bar stool post are needed?

Chairs - Replace all chairs with new stained wood chairs with vinyl padded seat.

Chairs needed

Seating- replace high chairs and booster seats.

Replace broken floor tile

Restroom Vestibule

Install Marlite Laredo Oak wainscot 3ft high and install Marlite spec chair rail.

Install Marlite Artizan FRP # 194 Cody wall cover above chair rail

Paint drywall ceiling white.

Doors- paint door frame. Ivoire SW6127 Oil based

Doors- re-finish doors. Stain formula. 1/2 Sher-wood deep cherry base S64 R52 and 1/2 Minwax ebony 2718

Lighting - Replace existing lighting.

Restrooms

Walls - Which finish?

Paint ceiling white

Lighting- Replace existing lighting

Flooring - Typically will remain as-is. Replace with Evolution spec tile, if needed.

Doors - Paint door frames Ivoire SW6127 oil based

Doors- re-finish doors. Stain formula. 1/2 Sher-wood deep cherry base S64 R52 and 1/2 Minwax ebony 2718

Doors- replace door hardware

Install new toilets

Install new wall mounted sinks

Install new urinal

Install new toilet paper and paper towel dispensers

Install new grab bars

Install new partitions.

Install baby changing stations?

Cook line

Demo back bar equipment.

Demo equipment curb and re-tile to match existing floor tile.

Install stainless steel on back bar wall

Add drywall be cooking equipment and ins white FRP 32" high.

Install new white outlets with stainless steel covers on back bar wall

Install additional electrical outlets for new equipment

Replace ceiling tile with white vinyl clad tiles.

Replace ceiling grid.

Paint existing ceiling grid

Replace 2x4 fluorescent lights with 2x4 LED fixtures (Cree A fixture)

How many 2x4 lights are needed?

Re-lamp existing 2x4 lights

Cover equipment drawers and doors with Stainless Steel if they have wood grain finish

Paint door frame to BOH Ivoire SW6127 oil based.

BOH

Replace 3 comp sink faucets

Replace prep sink faucets

Replace mop sink faucets

Replace 2x4 fluorescent lights with 2x4 LED fixtures (Cree A fixture)

How many 2x4 lights are needed?

Re-lamp existing 2x4 lights

Install FRP on walls

Replace ceiling grid

Paint existing ceiling grid

Replace ceiling tile

Replace HVAC grills

Repair broken tile floor

Paint block walls

Decor

Install "Huddle In" and "Huddle Back" round logos on vestibule door?

Install frosted "smiley face" graphics on right and left side of vestibule?

Valance - Select appropriate option.

Input approximate valance dimensions.

Install "Welcome" message, if suitable location is available.

Install G20 Wall art (I never met a potato) 92.5"W X 53"H

Install G21 wall art ( Life itself is a proper binge) 66"W X 49.5"H

Install G22 wall art (Man does not live on coffee alone ) 32"W x 37.5H

Install G23a wall art. "I am an explorer of food"

Install G23b wall art "Bacon is my favorite food group"

Install G23c wall art "Forget love I'd rather fall in Chocolate"

Install G23d wall art "All Happiness breakfast"

Install restroom door graphics (football player & cheerleader)?

Install restroom wall decor (one per restroom)?

Install Huddle House history graphic and plaque?

Equipment Requirements
Cook line equipment

Install Heated holding cabinet to HH current spec.

Type of Heated Holding Cabinet Needed

Install new toasters to meet current HH specifications

How many toasters needed?

Install toaster stand to meet current HH specifications

Install new waffle baker to meet current HH specifications

How many waffle bakers needed?

Install waffle baker stand to meet current HH specifications

Install convection oven to meet current HH specifications

Install 2 new microwave to meet HH meet current HH specifications

How many microwaves needed?

Install double microwave shelf to meet current HH specifications

Install APW steam wells to meet current HH specifications

How many APW needed?

Install 6ft of grill space to meet current HH spec

Which grill in needed?

Install Hood Extension.

Install eye burners meet current HH specifications

How many eye burners needed?

Install 2-Vat fryer with half-size fryer baskets meet current HH specifications

Install 2 Egg Mixers

How many egg mixers needed?

Install double mixer bracket

Install cooking timer to meet current HH spec

Install equipment for milk shake program

Have all existing equipment cleaned before re opening

Have all equipment calibrated before re opening

Have all refrigeration serviced and door gaskets replaced as needed before re opening

What Gas Type is at the location

Note any additional equipment needed

Drink Equipment

Install 2 coffee brewers- from Royal Cup

Install tea brewer- from Royal Cup

Have Soda, tea, and coffee equipment serviced or replace by appropriate vender

Back of House Equipment

Replace slicer

Replace dicer

Order Personal Protection Equipment and Cut gloves

Install bulk soap and sanitizing system for 3 comp sink

Order working temperature kit ( digital hand held thermometer, hi/lo temp probe, surface probe and separate hi/lo temp digital thermometer.

Replace any dry storage or walk-in wire shelving that is rusted or in poor condition

Alley behind Cook Line

Replace old insulation

Repair any unsafe wiring

Fix lighting

Clean alley of trash and debris

Additional Requirements

Install Roll-A-Shade window blinds (available with Huddle House logo)?

How many window blinds needed?

Update POS to be PCI compliant

Install high speed cable or broadband internet. (Dial up will not be accepted)

Install high speed credit card processing

Incorporate non-smoking through out restaurant

Install music system

Update small wares to HH spec

Participate and Display VOC/POP

Remove crane game

New entrance mats for vestibule

Install TV's and brackets (Typically 2)?

New uniforms required

Clean hood

Extra repair maintenance items

Signatures
Huddle House Representative
Time and Date of Completed Scope of Work
Please note that this checklist is a hypothetical example and provides basic information only. It is not intended to take the place of, among other things, workplace, health and safety advice; medical advice, diagnosis, or treatment; or other applicable laws. You should also seek your own professional advice to determine if the use of such checklist is permissible in your workplace or jurisdiction.