1.0 Site Entry / Boundaries

  • 1.1 Are project signs displayed and secured at the gate and at appropriate intervals along the fence line?

  • 1.2 Is the site evacuation sign displayed at the evacuation point?

  • 1.3 Are site boundary fences maintained and appropriate for the site?

  • 1.4 Is site vehicle and plant movement controlled and speed limit signs posted as necessary?

  • 1.5 Is the location of the site office identified?

  • 1.6 Is visitor and site parking adequately located and identified to minimise interaction with site plant?

2.0 Traffic Management

  • 2.1 Is the TMP current, signed and filed in the PMP?

  • 2.2 Is the Vehicle Management Plan completed, current and on display?

  • 2.3 Are traffic barricades erected in accordance with the TMP and do not pose a risk to traffic, pedestrians and workers?

  • 2.4 Are qualified traffic controllers on site?

3.0 Hazardous Substances / Dangerous Goods

  • 3.1 Has a Hazardous Substances register been completed?

  • 3.2 Are Safety Data Sheets provided for all chemicals onsite and current (within 5 years) ?

  • 3.3 Are all chemicals stored as defined in the S.D.S?

  • 3.4 Is there a well stocked spill kit available for use?

  • 3.5 Has bundling been provided for bulk storage tanks?

4.0 Excavations and Trenches

  • 4.1 Are permits to excavate in place and current for the works being performed. Are relevant personnel inducted into permit?

  • 4.2 Are regular trench inspections being carried out and recorded?

  • 4.3 Are unattended excavations / holes barricaded?

  • 4.4 Is benching, battering and shoring as per required?

  • 4.5 If shoring is being used, is it as per the requirements defined in WMS 04?

  • 4.6 Has a Geotechnical Engineer reviewed excavations

  • 4.7 Will Geotechnical review be required for future works?

  • 4.8 Is access into excavations adequate and safe?

  • 4.9 Is spoil adequately removed from the edges of the trench?

  • 4.10 Is dewatering being carried out as required?

  • 4.11 Is the plant being used appropriate for the task being performed?

5.0 Overhead services

  • 5.1 Are overhead services present onsite?

  • 5.2 Has a risk assessment been completed?

  • 5.3 Are overhead services identified as necessary? (Tiger tags, exclusion zones, signage)

  • 5.4 Is an appropriately qualified spotter on site controlling these works?

  • 5.5 Are exclusion zones marked appropriately for the site conditions?

6.0 Electrical / Power tools

  • 6.1 Is the electricians certificate of installation for the compound current and available?

  • 6.2 Are all electrical equipment tagged and tested (within current date) and in safe working order?

  • 6.3 Are safety switches (RCD'S) fitted to power supplies, tagged and tested (within current date) ?

  • 6.4 Are all electrical appliances tested and tagged (within current date) and in safe working order?

  • 6.5 Is correct P.P.E being worn as required?

  • 6.6 Are generators being operated safely and as intended?

  • 6.7 If used, are extension leads not more than 25 metres long and off the ground where possible?

7.0 Lifting equipment

  • 7.1 Equipment tested and current tags in place(6 monthly)?

  • 7.2 Is a lifting register onsite and current?

  • 7.3 Slings free from cuts and tears?

  • 7.4 Equipment in good condition free of damage and stored correctly?

8.0 Plant and equipment (including hired equipment)

  • 8.1 Operators licensed / deemed competent to operator mobile plant / equipment?

  • 8.2 Anti-Burst valves fitted to excavators / backhoes used for lifting?

  • 8.3 Plant fitted with flashing lights?

  • 8.4 Are safety pins being used?

  • 8.5 Spotters or traffic controllers used?

  • 8.6 Safe refuelling practices used?

  • 8.8 Hire equipment covered by appropriate insurance?

  • 8.9 Hired equipment stored correctly to ensure insurance cover?

9.0 Confined space

  • 9.1 Is confined space work being performed?

  • 9.2 Has a permit, risk assessment and sign off been completed correctly?

  • 9.3 Are all relevant workers trained and certified in confined space works?

  • 9.4 Is all the equipment available?

  • 9.5 Is all the appropriate equipment being used?

  • 9.6 Is the rescue plan completed and reviewed by relevant workers?

10.0 Sub-contractors

  • 10.1 Are all sub-contractors inducted onto the site?

  • 10.2 Have all sub-contractors on site signed into the "SIGNONSITE" app or the site register

  • 10.3 Are the sub-contractors working under an approved WMS?

  • 10.4 Are sub-contractors complying with their WMS?

  • 10.5 Are all sub-contractors licensed for the works they are performing?

  • 10.6 Is there proof of current sub-contractor insurance and workers compensation available?

11.0 Environmental

  • 11.1 EMP signed and on site?

  • 11.2 Approved plans and environmental controls defined in the EMP applied?

  • 11.5 Is the standard of house keeping acceptable?

  • 11.6 Are silt fences and silt traps in place and working as expected? And checked in C14?

  • 11.7 Are roadways and adjacent waterways clear of signs of sediment and dirt?

  • 11.8 Are dust levels acceptable?

  • 11.9 Are noise levels acceptable?

  • 11.10 Is noise monitoring required?

  • 11.11 Are vibration levels acceptable?

  • 11.12 Are cultural heritage constraints identified and managed?

  • 11.13 Is recycled water being used onsite?

  • 11.14 Is a Waste Water Management Plan required and defined?

  • 11.15 Are protected trees adequately identified and protected?

  • 11.16 Are site exit shake downs adequate and maintained correctly?

12.0 General / Site compound

  • 12.1 Is the PMP on site and signed?

  • 12.2 Are emergency procedures completed and displayed?

  • 12.3 Has the project hazard identification and risk assessment been completed and displayed (D11/ HAM) ?

  • 12.4 Toolbox sessions appropriate, regular and recorded?

  • 12.10 Are site safety notices displayed prominently?

  • 12.11 Are safety committee minutes displayed?

  • 12.12 Is the emergency information displayed?

  • 12.18 Are material storage areas clearly defined and tidy?

13.0 Other

  • Additional comments?

  • Follow up actions

  • Auditor signature

  • Auditees signature

  • Have all the follow up actions been completed?

  • Safety Managers Signature

  • Construction Managers signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.