Title Page

  • Audit Title

  • Conducted on

  • Prepared by

  • Location

Live line task and site conditions

  • Live Line task to be carried out.

  • Site conditions

  • Weather conditions and forecast?

  • Have all risks been identified and controlled?

  • Access and egress

  • Record lightning risk.

Instructions and Plans

  • Is there a current copy of the ENWL DSR's on site and available?

  • Are the relevant codes of practice on site and available?

  • Are adequate plans onsite and available?

  • Is the job instruction correct and available on site?

  • Is the extent of the work clear to all members of the team?

  • Has the control engineer been notified prior to the job commencing?

  • Has a switching schedule been prepared and adhered to?

  • Has the auto-reclose function been set to non-auto?

  • Has the job plan and sequence been agreed and signed by all team members?

Personel

Team members

  • Name

  • Authorisation to perform HV Live Line work in date

  • Date authorisation expires?

  • Team role?

  • Correct PPE available and worn?

  • Gloves and sleeves checked for correct class ,condition and in test date

  • Gloves and sleeves in test until?

  • Harness and safety lanyard checked in good condition and in date?

  • Next inspection due?

IAD

IAD inspections and setup

  • Is the IAD within test with certificate available?

  • Date of IAD Voltage withstand test?

  • Do the operators hold a current MEWP certification?

  • Was the IAD setup correctly and the vehicle check sheet completed?

  • Was the IAD earthed effectively?

  • MEWP rescue kit available in date and in good condition?

INSULATION

  • Are all line hoses of the correct class,clean, in test date and stored correctly?

  • Are all insulating blankets of the correct class,clean,in test date and stored correctly?

  • Test date for blankets and line hoses?

  • Are by-pass jumpers clean ,in good condition and within test date?

  • By-pass jumper test date?

  • Are all FRP rods clean stored correctly and in test date?

  • FRP rods test date?

Hydraulic hoses and tools

  • All hydraulic tools clean and in good condition?

  • All hydraulic hoses clean and in good condition?

  • Operator familiar with the equipment?

Task sequence and procedures

Task method and completion

  • Task carried out as agreed on the onsite job plan?

  • Adjacent structures checked?

  • Any changes to job plan agreed and changed as applicable?

  • Communication between team members

  • All secondary points of contact insulated sufficiently ?

Job completion

  • Job completed as per job instruction and ENWL codes of practice?

  • Control engineer informed job has been completed?

  • Switching schedule to be carried out and circuit set to auto?

Auditor comments

Post job site conditions

  • Finished task

AUDITOR AND TEAM COMMENTS

  • Auditor comments

  • Auditor signature.

  • Live line team agrees or disagrees with audit findings?

  • Live line team member name

  • Live Line team member signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.