Audit Information
-
Region / FSC
-
On-site leader
-
Location
-
Work to be completed
-
Conducted on
-
Auditor
Team Details
Worksite Team Members
-
Worksite Team Members
-
Name
-
Service Number
-
Worksite Team Role
- Observer
- Working aloft
- Ground attendant
- Plant operator
- Worksite Co-ordination / Leading Hand
-
Authorisation in date?
-
Authorisation Number
Worksite
Work group & Set up
-
Overall photograph of task to be completed (pre- job commencing)
-
Live Line Manual available on site - Hard Copy or Electronic copy
-
Appropriate HV Live Work Procedure(s) identified for the work
-
Stick Procedure(s)
- S1 A
- S1 B
- S2 A
- S2 B
- S2 C
- S2 D
- S2 E
- S3 A
- S3 B
- S3 C
- S3 D
- S4 A
- S4 B
- S4 C
- S4 D
- S5 A
- S5 B
- S6 A
- S6 B
- S6 C
- S7 A
- S7 B
- N/A
-
Glove & Barrier Procedure(s)
- G1 A
- G2 A
- G3 A
- G3 B
- G3 C
- G3 D
- G3 E
- G3 F
- G4 A
- G4 B
- G4 C
- G5 A
- G5 B
- G5 C
- G5 D
- G5 E
- G5 F
- G6 A
- G6 B
- G6 C
- G6 D
- G6 E
- G6 F
- G6 G
- G6 H
- G6 I
- G7 A
- G7 B
- G8 A
- G8 B
- N/A
-
All team members authorised for procedure(s)
-
WHRA discussion completed and documented
-
Photograph/screenshot from IPad front & back of WHRA
-
HV Live Work Permit Correctly Completed?
-
Photograph front & back of HVLW Permit
-
Conductor tensions calculated before commencing work
-
Screenshot of calculations from IPad
-
Telephone / communication from worksite
Equipment
-
Insulated Live Line equipment in test (hardcovers sticks etc...)
-
Test date
-
Insulating mats in test date
-
Test date
-
General condition of equipment
-
Provision for suitable equipment storage
-
Preparation of Live Line equipment
Personal Protective Equipment (PPE)
-
Arc rated clothing - long pants & long sleeves worn & in acceptable condition
-
Safety footwear worn & in acceptable condition
-
Approved eye protection worn & in acceptable condition
-
Hard hat worn, in acceptable condition and in date
Insulating gloves & sleeves
-
Inspection and inflation test performed
-
Leather protector gloves in good condition
-
Live Line gloves and sleeves in test date
-
Test date
Harnesses and Lanyards
-
In serviceable condition, clean and dry
-
Within 10 year service life from date of manufacture
EWP
-
EWP
Elevated Work Platform
-
Cleanliness/Condition of boom and basket
-
Excess gear removed from basket
EWP set up
-
Position of EWP relative to job
-
Photograph of EWP positioning
-
Stability of EWP
-
EWP effectively earthed & earth lead in test / inspection date
-
Next test date of earth lead
-
Quality of machine operation & control
Testing
-
Insulation within test date
-
Test date
-
Photograph EWP testing record
-
All hydraulic tool hoses in good condition, non-conductive and test sticker clearly displayed. (Note if battery tools used only)
Borer / Erector
-
Borer/Erector
Borer / Erector
-
Endeavour Energy lifter borer/plant
-
Name and service number
-
Authorisation number
-
Contractor - lifter borer/plant
-
Company and name of plant operator
-
Contract plant operator authorisation number.
-
Date of authorisation
Vehicle equipment
-
Overall hydraulic system (leaking?)
-
All lifting equipment in good condition?
Safety
-
Borer / erector effectively earthed & earth lead in test / inspection date
-
Next test date of earth lead
-
Position of borer / erector relative to work
-
Photograph of borer/erector position
-
Operator dressed in compliant clothing
-
Quality of machine operation and control
-
Safe work practices being utilised
-
Photographs of borer/erector operation during job
-
Quality of communication between Operator & Plant Safety Observer
HVLW application
Procedures
-
Safety observer in good position and observing correctly
-
Safe working clearances being maintained
-
Temporary insulation erected and utilised correctly
-
Safe work practices utilised?
-
Photograph(s) of work in progress
-
General worksite supervision
Worksite Conduct
-
Communication between safety observer and work face
-
Work face communication and interaction
-
Attitude towards Live Line work
-
General quality of Live Line work
Audit completion
Follow up actions
-
Do any items need to be followed up as a result of this audit - if yes then complete action(s) below
-
Action
Action item
-
Responsible person
-
Follow up action
Audit rating
-
Overall comments from auditor
-
Overall rating of the audit
- Conformance – All audit criteria met (Blue)
- Conformance after field rectification of potential non-fatal immediate consequences (Green)
- Non-conformance recorded with potential non-fatal immediate consequences (Yellow)
- Non-conformance with potential fatal immediate consequences (Pink)
- Multiple non-conformances with potential fatal immediate consequences (Red)
Completion
-
Auditor confirms the findings of the audit (sign)
-
Auditee endorsement: I am a representative of the work crew
-
Auditee comments